Schedule

 

The schedule for the full Layer 0 Silicon project is summarized in the Microsoft Project file.

Below is a task list sorted by finish date. Tasks scheduled to end in the current month or before

are coded by current status.

 

  Task Complete        
  In progress on schedule        
  Delayed, no schedule impact        
  Delayed, schedule impact        
         
WBS Task Status 1-13-2004 Duration Start Finish Status
1.6.1.1 Probe Stations Ready 0 w 11/03/03 11/03/03  
1.6.2.2 SASEQ Test Stands Available 0 w 11/03/03 11/03/03  
1.6.4.2 Module Burn-in Stands Available 0 w 11/03/03 11/03/03  
1.6.3.1.1 Design mechanical structures 6 w 11/03/03 12/16/03  
1.6.3.1.2 Conduct finite element analysis (mechanical) 6 w 11/03/03 12/16/03  
1.6.3.1.3 Freeze Mechanical Parameters 0 w 12/16/03 12/16/03  
1.6.2.1 SVX4 Chips Available 0 w 01/05/04 01/05/04  
1.6.3.1.4 Design cooling components/assembly 3 w 12/17/03 01/15/04  
1.6.3.1.5 Conduct finite element analysis (thermal) 3 w 12/17/03 01/15/04  
1.6.1.2 Design short sensors 4 w 12/17/03 01/23/04  
1.6.1.3 Design long sensors 4 w 12/17/03 01/23/04  
1.6.2.7.1 Design twisted-pair cables 2 w 01/09/04 01/23/04  
1.6.2.3.1 Design hybrids 5 w 12/17/03 01/30/04  
1.6.3.1.6 Integrate designs (sensors, grounding, cooling) 2 w 01/16/04 01/30/04  
1.6.1.5 Conduct sensor production readiness review 1 w 01/26/04 01/30/04  
1.6.2.7.2 Conduct twisted-pair cable production readiness review 1 w 01/26/04 01/30/04  
1.6.2.4.1 Design analog cables and spacers 12 w 11/03/03 02/06/04  
1.6.2.6.1 Design digital cables 4 w 01/09/04 02/06/04  
1.6.1.4 Vendor RFQ 2 w 01/26/04 02/06/04  
1.6.2.3.2 Conduct hybrid production readiness review 1 w 02/02/04 02/06/04  
1.6.3.1 Support Structures Design 65 d 11/03/03 02/13/04  
1.6.3.1.7 Prepare drawings 2 w 02/02/04 02/13/04  
1.6.3.7.1 Prepare final production and assembly drawings 2 w 02/02/04 02/13/04  
1.6.2.4.2 Conduct analog cable production readiness review 1 w 02/09/04 02/13/04  
1.6.2.6.2 Conduct digital cable production readiness review 1 w 02/09/04 02/13/04  
1.6.3.3 Production Readiness Review 5 d 02/16/04 02/20/04  
1.6.3.3.1 Conduct production readiness review (UW) 1 w 02/16/04 02/20/04  
1.6.3.3.2 Conduct production readiness review (Fermilab) 1 w 02/16/04 02/20/04  
1.6.3.3.3 Support Structures Ready For Production 0 w 02/20/04 02/20/04  
1.6.2.5.1 Design grounding circuits 4 w 02/02/04 02/27/04  
1.6.2.7.3 Bid twisted-pair cable production 4 w 02/02/04 02/27/04  
1.6.2.3.3 Bid hybrid production 3 w 02/09/04 02/27/04  
1.6.2.4.3 Bid analog cable production 2 w 02/16/04 02/27/04  
1.6.2.9.1 Design adapter cards 16 w 11/03/03 03/05/04  
1.6.2.6.3 Bid digital cable production 4 w 02/16/04 03/12/04  
1.6.5.1.1 Design support structure holding fixtures 4 w 02/16/04 03/12/04  
1.6.3.4.1 Design final production tooling 3 w 02/23/04 03/12/04  
1.6.3.5.1 Design final QA tooling 3 w 02/23/04 03/12/04  
1.6.2.5.2 Bid grounding circuits 2 w 03/01/04 03/12/04  
1.6.4.3.4 Finalize L0 wirebonding fixtures 2 w 03/01/04 03/12/04  
1.6.2.8.1 Design junction cards 12 w 12/17/03 03/19/04  
1.6.1.6 Prepare sensor req and PO 6 w 02/09/04 03/19/04  
1.6.4.3.1 Finalize readout module fabrication fixtures 4 w 02/23/04 03/19/04  
1.6.1.7 Release Sensors for Production 0 w 03/19/04 03/19/04  
1.6.2.3.4 Prepare hybrid req and PO 4 w 03/01/04 03/26/04  
1.6.2.4.4 Prepare analog cable req and PO 4 w 03/01/04 03/26/04  
1.6.2.7.4 Prepare twisted-pair cable req and PO 4 w 03/01/04 03/26/04  
1.6.3.4.2 Prepare final production tooling drawings 2 w 03/15/04 03/26/04  
1.6.3.5.2 Prepare final QA tooling drawings 2 w 03/15/04 03/26/04  
1.6.2.8.2 Conduct junction card production readiness review 1 w 03/22/04 03/26/04  
1.6.2.3.5 Release Hybrids for Production 0 w 03/26/04 03/26/04  
1.6.2.4.5 Release Analog Cables for Production 0 w 03/26/04 03/26/04  
1.6.2.7.5 Release Twisted-pair Cables for Production 0 w 03/26/04 03/26/04  
1.6.5.2.1 Design module installation fixtures 8 w 02/16/04 04/09/04  
1.6.3.4 Final Fabrication Tooling 35 d 02/23/04 04/09/04  
1.6.3.5 Final Quality Assurance Tooling 35 d 02/23/04 04/09/04  
1.6.2.5.3 Procure grounding circuits 4 w 03/15/04 04/09/04  
1.6.2.6.4 Prepare digital cable req and PO 4 w 03/15/04 04/09/04  
1.6.3.4.3 Fabricate final production tooling 2 w 03/29/04 04/09/04  
1.6.3.5.3 Fabricate final QA tooling 2 w 03/29/04 04/09/04  
1.6.2.6.5 Release Digital Cables for Production 0 w 04/09/04 04/09/04  
1.6.2.5 Flex Grounding Circuits 55 d 02/02/04 04/16/04  
1.6.2.5.4 Test grounding circuits 1 w 04/12/04 04/16/04  
1.6.2.8.3 Prepare junction card req and PO 4 w 03/29/04 04/23/04  
1.6.2.8.4 Release Junction Cards for Production 0 w 04/23/04 04/23/04  
1.6.2.12.1 Test mixed SVX2/SVX4 readout 24 w 11/03/03 04/30/04  
1.6.2.3.7 Procure parts (FNAL) 12 w 02/09/04 04/30/04  
1.6.2.3.8 Procure parts (Fresno) 12 w 02/09/04 04/30/04  
1.6.2.9.2 Procure prototypes 8 w 03/08/04 04/30/04  
1.6.5.1.2 Procure support structure holding fixtures 8 w 03/15/04 05/07/04  
1.6.5.1 Layer 0 Support Structure Holding Fixtures 65 d 02/16/04 05/14/04  
1.6.5.1.3 QC support structure holding fixtures 1 w 05/10/04 05/14/04  
1.6.3.6 Produce preproduction samples for testing 6 w 04/12/04 05/21/04  
1.6.2.9.3 Test prototypes 4 w 05/03/04 05/28/04  
1.6.4.1 Fabricate module boxes 12 w 03/15/04 06/07/04  
1.6.4.3.5 Procure production L0 wirebonding fixtures 12 w 03/15/04 06/07/04  
1.6.4.3.6 QC production L0 wirebonding fixtures 1 w 06/08/04 06/14/04  
1.6.2.7.6 Procure parts for twisted-pair cables 12 w 03/29/04 06/21/04  
1.6.2.8.5 Produce junction cards 8 w 04/26/04 06/21/04  
1.6.3.2 Development and integration of design (FNAL) 26 w 12/17/03 06/28/04  
1.6.2.3.6 Produce hybrids 14 w 03/29/04 07/06/04  
1.6.2.6.6 Produce digital cables 12 w 04/12/04 07/06/04  
1.6.5.2.2 Procure module installation fixtures 12 w 04/12/04 07/06/04  
1.6.3.7.2 Procure/manufacture final production parts 6 w 05/24/04 07/06/04  
1.6.2.3.9 Hybrid Boxes Available 0 w 07/06/04 07/06/04  
1.6.5.2 Layer 0 Module Installation Fixtures 105 d 02/16/04 07/13/04  
1.6.4.3.2 Procure production layer 0 readout module fixtures 16 w 03/22/04 07/13/04  
1.6.5.2.3 QC module installation fixtures 1 w 07/07/04 07/13/04  
1.6.2.8 Junction Cards 145 d 12/17/03 07/20/04  
1.6.2.4.6 Produce analog cables 16 w 03/29/04 07/20/04  
1.6.2.8.6 Test junction cards 4 w 06/22/04 07/20/04  
1.6.2.3.10.4 Wipe hybrids 2 w 07/07/04 07/20/04  
1.6.2.8.7 All Junction Cards Produced and Tested 0 w 07/20/04 07/20/04  
1.6.5.17 Monitoring 150 d 12/17/03 07/27/04  
1.6.5.17.1 Temperature Monitoring 30 w 12/17/03 07/27/04  
1.6.4.3 Production Module Fixtures 110 d 02/23/04 07/27/04  
1.6.2.6.7 Terminate digital cables 3 w 07/07/04 07/27/04  
1.6.4.3.3 QC production readout module fixtures 2 w 07/14/04 07/27/04  
1.6.5.3 Design and fabricate detector garage 2 w 07/14/04 07/27/04  
1.6.2.3.10.1 Develop functionality test (Fresno) 4 w 07/07/04 08/03/04  
1.6.3.7.3 Assemble final support structures 4 w 07/07/04 08/03/04  
1.6.2.10.1 Design HV System 10 w 06/01/04 08/10/04  
1.6.2.3.10.5 Measure hybrids (mechanical) 3 w 07/21/04 08/10/04  
1.6.2.10.2 Release HV System for Production 0 w 08/10/04 08/10/04  
1.6.2.12.2 Test adapter card schemes 12 w 05/24/04 08/17/04  
1.6.3.7.4 Perform quality assurance checks on final support structures 2 w 08/04/04 08/17/04  
1.6.3.7.5 All Support Structures Completed 0 w 08/17/04 08/17/04  
1.6.2.6 Digital Cables 160 d 01/09/04 08/24/04  
1.6.3.7 Final Support Structures Production 145 d 02/02/04 08/24/04  
1.6.2.6.8 Test digital cables 4 w 07/28/04 08/24/04  
1.6.3.7.6 Ship to Fermilab 1 w 08/18/04 08/24/04  
1.6.2.6.9 All Digital Cables Delivered and Tested 0 w 08/24/04 08/24/04  
1.6.3.7.7 All Support Structures Received At Fermilab 0 w 08/24/04 08/24/04  
1.6.2.3.10.6 Probe bare hybrids 6 w 07/21/04 08/31/04  
1.6.2.3.10.2 Develop hybrid burn-in test (KU) 4 w 08/04/04 08/31/04  
1.6.2.3.10.3 Develop hybrid burn-in test (FNAL) 4 w 08/04/04 08/31/04  
1.6.2.12.3 Move test setup to Lab C 2 w 08/18/04 08/31/04  
1.6.2.7.7 Assemble twisted-pair cables 12 w 06/22/04 09/15/04  
1.6.2.9.4 Develop final specifications (KSU) 4 w 08/18/04 09/15/04  
1.6.2.9.5 Develop final specifications (Fermilab) 4 w 08/18/04 09/15/04  
1.6.3 Mechanical Design and Fabrication 220 d 11/03/03 09/22/04  
1.6.1.8 Produce sensors 26 w 03/22/04 09/22/04  
1.6.4.4.1 Qualify fixtures and procedures 8 w 07/28/04 09/22/04  
1.6.3.8 Perform final article QA checks of support structure components/assemblies 4 w 08/25/04 09/22/04  
1.6.2.9.6 Conduct adapter card production readiness review 1 w 09/16/04 09/22/04  
1.6.2.4 Analog Cables 225 d 11/03/03 09/29/04  
1.6.2.4.7 Test analog cables 10 w 07/21/04 09/29/04  
1.6.2.4.8 All Analog Cables Delivered and Tested 0 w 09/29/04 09/29/04  
1.6.2.7 Twisted-Pair Cables 195 d 01/09/04 10/13/04  
1.6.2.7.8 Test twisted-pair cables 4 w 09/16/04 10/13/04  
1.6.2.9.7 Bid adapter card production 3 w 09/23/04 10/13/04  
1.6.2.7.9 All Twisted-pair Cables Assembled and Tested 0 w 10/13/04 10/13/04  
1.6.2.10.3 Produce HV System 10 w 08/11/04 10/20/04  
1.6.2.3.10.7 Stuff and wirebond hybrids 8 w 09/01/04 10/27/04  
1.6.2.9.8 Prepare adapter card req and PO 4 w 10/14/04 11/10/04  
1.6.2.9.9 Release Adapter Cards for Production 0 w 11/10/04 11/10/04  
1.6.2.10 High-Voltage System 120 d 06/01/04 11/17/04  
1.6.1.9 Probe sensors (FNAL) 8 w 09/23/04 11/17/04  
1.6.1.10 Probe sensors (MRI) 8 w 09/23/04 11/17/04  
1.6.1.12 Irradiate test structures 4 w 10/21/04 11/17/04  
1.6.2.10.4 Test HV System 4 w 10/21/04 11/17/04  
1.6.1.13 All Sensors Delivered and Tested 0 w 11/17/04 11/17/04  
1.6.2.3.10.8 Perform initial functionality test 4 w 10/28/04 11/24/04  
1.6.4.4.2 Produce preproduction modules 2 w 11/29/04 12/10/04  
1.6.4.4 Preproduction Modules 105 d 07/28/04 01/04/05  
1.6.4.4.3 Test preproduction modules 2 w 12/13/04 01/04/05  
1.6.4.5 Conduct L0 module production readiness review 1 w 01/05/05 01/11/05  
1.6.5.4 Certify module mounting procedures 1 w 01/05/05 01/11/05  
1.6.4.6.1 Silicon L0 Module Production Begun 0 w 01/18/05 01/18/05  
1.6.2.3 Hybrids 265 d 12/17/03 01/19/05  
1.6.2.3.10 Test Hybrids 130 d 07/07/04 01/19/05  
1.6.2.3.10.9 Perform hybrid burn-in tests 8 w 11/11/04 01/19/05  
1.6.2.3.11 All L0 Hybrids Delivered, Stuffed, and Tested 0 w 01/19/05 01/19/05  
1.6.2.9.10 Produce adapter cards 9 w 11/11/04 01/26/05  
1.6.2.9 Adapter Cards 320 d 11/03/03 02/23/05  
1.6.2.9.11 Test adapter cards 4 w 01/27/05 02/23/05  
1.6.2.9.12 All Adapter Cards Delivered and Tested 0 w 02/23/05 02/23/05  
1.6.4.6.2 Prepare sensors for module production 8 w 01/12/05 03/09/05  
1.6.4.6.3 Align and glue pair of flex cables 8 w 01/18/05 03/14/05  
1.6.4.6.4 Align and glue sensor to flex cable 8 w 01/20/05 03/16/05  
1.6.4.6.5 Perform sensor-to-flex cable wirebonds 8 w 01/24/05 03/18/05  
1.6.4.6.6 Attach end hybrids to flex cable 8 w 01/26/05 03/22/05  
1.6.4.6.7 Wirebond end hybrid to flex cable 8 w 01/28/05 03/24/05  
1.6.4.6.8 Silicon L0 Module Production Complete 0 w 03/24/05 03/24/05  
1.6.4.6.9 Debug sensor modules 8 w 02/01/05 03/28/05  
1.6.4.6.10 Burn-in sensor modules 8 w 02/08/05 04/04/05  
1.6.2.12.4 Test with final adapter cards 8 w 02/17/05 04/13/05  
1.6.4.6.11 Evaluate and repair sensor modules 8 w 02/22/05 04/18/05  
1.6.5.5 Mount layer 0 sensor modules 8 w 03/15/05 05/09/05  
1.6.5.18 Software and Simulation 75 w 11/03/03 05/11/05  
1.6.4 Layer 0 Detector Modules 378 d 11/03/03 05/16/05  
1.6.4.6 Module Production 88 d 01/12/05 05/16/05  
1.6.4.6.12 Perform quality assurance tests 14 w 02/08/05 05/16/05  
1.6.5.6 Verify sensor alignment 1 w 05/10/05 05/16/05  
1.6.4.6.13 Silicon L0 Module Production and Testing Complete 0 w 05/16/05 05/16/05  
1.6.5.7 Install temperature sensors 1 w 05/17/05 05/23/05  
1.6.2.11 Readout Chain Integration 78 w 11/03/03 06/02/05  
1.6.5.10 Beams Div bakeout and leak check of beam pipe 2 w 05/19/05 06/02/05  
1.6.5.8 Perform initial electrical test of readout 2 w 05/24/05 06/07/05  
1.6.5.11 SiDet leak check of beam pipe 0.6 w 06/03/05 06/07/05  
1.6.2 Readout Electronics 395 d 11/03/03 06/09/05  
1.6.2.12 Full Chain Tests 395 d 11/03/03 06/09/05  
1.6.2.12.5 Test full, final system 8 w 04/14/05 06/09/05  
1.6.2.12.6 Full Chain System Test Completed 0 w 06/09/05 06/09/05  
1.6.5.9 Install outer shell 1 w 06/08/05 06/14/05  
1.6.5.12 Install beam pipe 0.2 w 06/15/05 06/15/05  
1.6.1 Sensors 415 d 11/03/03 07/08/05  
1.6.1.11 Long-term sensor tests 39 w 09/23/04 07/08/05  
1.6.5.13 Test final system 4 w 06/16/05 07/14/05  
1.6.5.14 Layer 0 Silicon Detector Assembly and Testing Complete 0 w 07/14/05 07/14/05  
1.6 Layer 0 Silicon Detector 424 d 11/03/03 07/21/05  
1.6.5 Final Detector Integration and Assembly 424 d 11/03/03 07/21/05  
1.6.5.15 Prepare for transport to DAB 1 w 07/15/05 07/21/05  
1.6.5.16 Layer 0 Silicon Detector Ready to Move to DAB 0 w 07/21/05 07/21/05  

 

 