Previous      Next      Directory 

Folder: GENERAL From: blazey@dsc09-waf-dc-206-214-1-169.rasserver.net Subject: Standing Committee on Upgrade Installation-to-Physics Commissioning Date: 20-APR-2004 22:05 Expires: 04-JUL-2004 22:05
Dear Colleagues We are pleased to announce formation of a Standing Committee on Upgrade Installation-to-Physics Commissioning. The committee is being charged with developing an integrated experiment-wide plan for the installation and full commissioning of the upgrade elements. Their findings will be used as input to the spokesperson's deliberations as we decide on the scheduling of, and the collaboration-wide resources required for, the installation and commissioning of each of the upgrade components. The full charge to the committee is attached below. The current committee membership represents the unusually extensive nature of the task. It consists of Ela Barberis, Volker Buescher, Bill Cooper, Stefan Gruenendahl, Bob Hirosky, Rick Jesik, Ken Johns, Eric Kajfasz, Breese Quinn, Lisa Shabalina, Gordon Watts, and Taka Yasuda, and will be co-chaired by Cecilia Gerber and Rich Smith. A small number of members may be added as needed, to bring in additional expertise. The Committee will be necessarily be drawing on the expertise of many in the collaboration; we ask each of you to assist them when called upon. We thank the committee members for agreeing to take on this important and challenging task. Sincerely Jerry Blazey and John Womersley ***************************************************** Charge to the Standing Committee on Upgrade Installation-to-Physics Commissioning In order to continue to exploit and maximize the physics potential of the experiment throughout Run II, the upgrade trigger, DAQ/online, and silicon sub-projects must be installed and commissioned in a manner that to the greatest extent possible minimizes the total downtime of the experiment. The installation and technical commissioning of the hardware represents a portion of that process; full commissioning of the elements further downstream (physics commissioning) will also be required in order to resume the acquisition of physics-quality data. A collaborative effort that effectively bridges the usual hardware/software boundaries is essential in order to optimally coordinate this process. To that end, we have assembled a Standing Committee that is being asked to generate a detailed plan describing the evolution of the various activities. This plan will include, but not necessarily be limited to, the following areas: · Installation and technical commissioning of the hardware; · Calibration databases, both online and offline; · Updates to data unpacking & formatting; · Development of Level 3 filtering algorithms; · Updates to clustering and track finding, both online and offline; · Development of Monte Carlo and TRIGSIM. We have asked the Committee to come up with a plan that includes a breakdown and timelines for each of the major efforts, the resources required (including manpower type – physicist, engineer, technician, etc.), and the sequence in which the various pieces need to be developed. Given the complexity of this set of processes, we have assembled a broad group of experts to develop this plan. The Committee therefore includes personnel from the upgrade project, as well as those more closely affiliated with areas beyond the upgrade and hardware efforts. We imagine that the work associated with this effort will go on until the upgrade elements are commissioned, but that the studies will be done in more focused periods, not as a constant effort. It is understood that the Committee will work closely with the Algorithms Coordinator, the Technical Coordinator, and the Run IIb Project Manager, taking direction and guidance from them in developing the plan. The spokespersons, in conjunction with the aforementioned managers of the experiment, will be asking others in the collaboration to assist the Committee with any studies that are needed, and to generally lend their input and expertise as the plan is developed. We have also asked the co-chairs to provide periodic oral reports on their progress in various forums, including collaboration meetings and the All DZero Meeting. A written report describing the findings of the Committee will be updated and submitted to the spokespersons approximately every three to four months, and will be used to evaluate the optimal approach to, and timing for, the installation of the upgrade elements. We have requested a first update be presented at the June 2004 workshop in Fresno. This is a most challenging task, and we very much appreciate that this group has agreed to serve the experiment in this capacity. We have every hope and expectation that the timely establishment of this Committee, and the more integrated approach to installation and commissioning that their efforts represent, will enable us to most fully optimize the physics reach of the experiment during the coming run. Jerry Blazey and John Womersley

[ Active News || Post a New Message || Search || Archived News || Help ]

[ Choose Folders || List Unseen News ]

Questions: D0NEWS Admin