Schedule

 

Based on a split support cylinder, the installation schedule and Fermilab accelerator schedule call for a production schedule for the silicon tracker as indicated.

 

Milestone

Duration

Start Date

Finish Date

Barrel 1 Complete

3 w

March 29, 2000

April 18, 2000

Barrel 2 Complete

3 w

May 3, 2000

May 23, 2000

Barrel 3 Complete

3 w

June 8, 2000

June 28, 2000

Barrel 4 Complete

3 w

July 7, 2000

July 27, 2000

Barrel 5 Complete

3 w

August 4, 2000

August 24, 2000

Barrel 6 Complete

3 w

September 1, 2000

September 22, 2000

F Disk 0 Complete

1 w

March 22, 2000

March 28, 2000

F Disk 1 Complete

2 w

March 29, 2000

April 11, 2000

F Disk 2 Complete

1 w

April 19, 2000

April 25, 2000

F Disk 3 Complete

1 w

May 3, 2000

May 9, 2000

F Disk 4 Complete

1 w

May 17, 2000

May 23, 2000

F Disk 5 Complete

1 w

June 15, 2000

June 21, 2000

F Disk 6 Complete

1 w

June 29, 2000

July 6, 2000

Three End F-Disks Complete

0 w

July 13, 2000

July 13, 2000

F Disk 7 Complete

1 w

July 14, 2000

July 20, 2000

F Disk 8 Complete

1 w

July 28, 2000

August 3, 2000

F Disk 9 Complete

1 w

August 11, 2000

August 17, 2000

F Disk 10 Complete

1 w

August 25, 2000

August 31, 2000

F Disk 11 Complete

1 w

September 11, 2000

September 15, 2000

F Disk 12 Complete

1 w

October 2, 2000

October 6, 2000

Six End F-Disks Complete

0 w

October 13, 2000

October 13, 2000

H Disk 1 Complete

6 w

April 6, 2000

May 17, 2000

H Disk 2 Complete

6 w

May 25, 2000

July 7, 2000

H Disk 3 Complete

6 w

July 17, 2000

August 25, 2000

H Disk 4 Complete

6 w

September 5, 2000

October 16, 2000

North H-disks Ready to Move to DAB

0 w

August 4, 2000

August 4, 2000

South H-Disks Ready to Move to DAB

0 w

November 13, 2000

November 13, 2000

Install F1 disk on B1 barrel

1 w

May 3, 2000

May 9, 2000

Install F2 disk on B2 barrel

1 w

May 24, 2000

May 31, 2000

Install F3 disk on B3 barrel

1 w

June 29, 2000

July 6, 2000

Install three barrel/disk modules in north support

3 w

June 22, 2000

July 13, 2000

Assemble F4, F5, and F6 end disks into end-disk module

1 w

July 14, 2000

July 20, 2000

Install north end disk module into support

1 w

July 21, 2000

July 27, 2000

North Half-Cylinder Complete and Ready to Move to DAB

0 w

July 27, 2000

July 27, 2000

Install F7 disk on B4 barrel

1 w

July 28, 2000

August 3, 2000

Install F8 disk on B5 barrel

1 w

August 25, 2000

August 31, 2000

Install F9 disk on B6 barrel

1 w

September 25, 2000

September 29, 2000

Install three barrel/disk modules in south support

3 w

September 18, 2000

October 6, 2000

Assemble F10, F11, and F12 end disks into end-disk module

1 w

October 16, 2000

October 20, 2000

Install south end disk module into support

1 w

October 23, 2000

October 27, 2000

South Half-Cylinder Complete and Ready to Move to DAB

0 w

October 27, 2000

October 27, 2000

M1-Central Silicon Complete

0 w

October 27, 2000

October 27, 2000