Based on a split support cylinder, the installation schedule and Fermilab accelerator schedule call for a production schedule for the silicon tracker as indicated.
|
Milestone |
Duration |
Start Date |
Finish Date |
|
Barrel 1 Complete |
3 w |
March 29, 2000 |
April 18, 2000 |
|
Barrel 2 Complete |
3 w |
May 3, 2000 |
May 23, 2000 |
|
Barrel 3 Complete |
3 w |
June 8, 2000 |
June 28, 2000 |
|
Barrel 4 Complete |
3 w |
July 7, 2000 |
July 27, 2000 |
|
Barrel 5 Complete |
3 w |
August 4, 2000 |
August 24, 2000 |
|
Barrel 6 Complete |
3 w |
September 1, 2000 |
September 22, 2000 |
|
F Disk 0 Complete |
1 w |
March 22, 2000 |
March 28, 2000 |
|
F Disk 1 Complete |
2 w |
March 29, 2000 |
April 11, 2000 |
|
F Disk 2 Complete |
1 w |
April 19, 2000 |
April 25, 2000 |
|
F Disk 3 Complete |
1 w |
May 3, 2000 |
May 9, 2000 |
|
F Disk 4 Complete |
1 w |
May 17, 2000 |
May 23, 2000 |
|
F Disk 5 Complete |
1 w |
June 15, 2000 |
June 21, 2000 |
|
F Disk 6 Complete |
1 w |
June 29, 2000 |
July 6, 2000 |
|
Three End F-Disks Complete |
0 w |
July 13, 2000 |
July 13, 2000 |
|
F Disk 7 Complete |
1 w |
July 14, 2000 |
July 20, 2000 |
|
F Disk 8 Complete |
1 w |
July 28, 2000 |
August 3, 2000 |
|
F Disk 9 Complete |
1 w |
August 11, 2000 |
August 17, 2000 |
|
F Disk 10 Complete |
1 w |
August 25, 2000 |
August 31, 2000 |
|
F Disk 11 Complete |
1 w |
September 11, 2000 |
September 15, 2000 |
|
F Disk 12 Complete |
1 w |
October 2, 2000 |
October 6, 2000 |
|
Six End F-Disks Complete |
0 w |
October 13, 2000 |
October 13, 2000 |
|
H Disk 1 Complete |
6 w |
April 6, 2000 |
May 17, 2000 |
|
H Disk 2 Complete |
6 w |
May 25, 2000 |
July 7, 2000 |
|
H Disk 3 Complete |
6 w |
July 17, 2000 |
August 25, 2000 |
|
H Disk 4 Complete |
6 w |
September 5, 2000 |
October 16, 2000 |
|
North H-disks Ready to Move to DAB |
0 w |
August 4, 2000 |
August 4, 2000 |
|
South H-Disks Ready to Move to DAB |
0 w |
November 13, 2000 |
November 13, 2000 |
|
Install F1 disk on B1 barrel |
1 w |
May 3, 2000 |
May 9, 2000 |
|
Install F2 disk on B2 barrel |
1 w |
May 24, 2000 |
May 31, 2000 |
|
Install F3 disk on B3 barrel |
1 w |
June 29, 2000 |
July 6, 2000 |
|
Install three barrel/disk modules in north support |
3 w |
June 22, 2000 |
July 13, 2000 |
|
Assemble F4, F5, and F6 end disks into end-disk module |
1 w |
July 14, 2000 |
July 20, 2000 |
|
Install north end disk module into support |
1 w |
July 21, 2000 |
July 27, 2000 |
|
North Half-Cylinder Complete and Ready to Move to DAB |
0 w |
July 27, 2000 |
July 27, 2000 |
|
Install F7 disk on B4 barrel |
1 w |
July 28, 2000 |
August 3, 2000 |
|
Install F8 disk on B5 barrel |
1 w |
August 25, 2000 |
August 31, 2000 |
|
Install F9 disk on B6 barrel |
1 w |
September 25, 2000 |
September 29, 2000 |
|
Install three barrel/disk modules in south support |
3 w |
September 18, 2000 |
October 6, 2000 |
|
Assemble F10, F11, and F12 end disks into end-disk module |
1 w |
October 16, 2000 |
October 20, 2000 |
|
Install south end disk module into support |
1 w |
October 23, 2000 |
October 27, 2000 |
|
South Half-Cylinder Complete and Ready to Move to DAB |
0 w |
October 27, 2000 |
October 27, 2000 |
|
M1-Central Silicon Complete |
0 w |
October 27, 2000 |
October 27, 2000 |