DØ CTT Run 2b upgrade

FNAL contribution


general CTT task list for Run2b, and Fall 2004 shutdown tasks (pdf) 2004-07-06

Jamieson's hardware documents

Jamieson's plan for integration testing (pdf)

Run2b commissioning outline (txt)

Project file Trigger_CTT_FNAL_v8.mpp 2004-4-27

v8: subtasks for crate controller and backplane properly attributed; duplicate testing effort removed.
v7: same as v6, but imported into the current overall schedule.

upper part of project screen shot (jpg) with cost and chart 2004-4-27

lower part of project screen shot (jpg), with ElecEngF weekly hours 2004-4-27

Periods of more than 40 hours/week correspond to activity by a second engineer on the LVDS splitter board.

2nd draft of the Reply to Review Committee (.txt file) 2004-4-20

Proposal for Commissioning with a full parallel CTT chain (.txt file) 2004-4-12

Review Committee findings (.doc file) 2004-4-14


previous version (March 2004):

Project file Trigger_CTT_FNAL_v5.mpp

HTML view of Trigger_CTT_FNAL_v5

project screen shot (jpg) with cost and chart

previous version (Feb 2004):

Project file Trigger_CTT_FNAL_v3.mpp

HTML view of Trigger_CTT_FNAL_v3

Gantt chart screen shot (jpg)

tasks and costs screen shot (jpg)

Brief description of the project tasks

 

 

Last modified April 19th, 2004, by SG.