Run IIb trigger Schedule


Project Start Date: Mon 10/1/01
Project Finish Date: Thu 5/12/05

Tasks

ID
Task Name
DurationStartFinishResource Names% Complete
1
Run IIb Trigger Upgrade
873 d?Thu 11/1/01Thu 5/12/05 44%
2
Level 1 Calorimeter Trigger
838 dWed 1/2/02Thu 5/12/05 57%
3
ADC/Digital Filter (ADF)
753 dWed 1/2/02Wed 1/12/05 56%
4
Saclay Tasks
697 dWed 1/2/02Wed 10/13/04 73%
5
Design prototype ADF
53 wWed 1/2/02Fri 1/24/03ElecEngU,InKind[189,655.6]100%
6
Layout prototype ADF
17 wMon 1/27/03Fri 5/23/03ElecTechU,InKind[15,110.4]100%
7
Fabricate/Assemble Prototype ADF
5.2 wTue 5/27/03Tue 7/1/03ElecTechU[50%],InKind[60,055.2]100%
8
Bench Test Prototype ADF
13.6 wTue 7/15/03Fri 10/17/03PhysicistU[30%],ElecEngU[20%],ElecTechU[20%],InKind[20,632.24]100%
9
Prototype L1 Calorimeter Trigger ADF Shipped To Fermilab
0 wTue 10/7/03Tue 10/7/03 100%
10
Design analog splitter
4 wFri 3/1/02Thu 3/28/02ElecEngU,InKind[16,494.4]100%
11
Layout and fabricate analog splitter
8 wMon 7/1/02Mon 8/26/02ElecTechU[50%],InKind[9,150.2]100%
12
Bench test analog splitter
9.2 wMon 11/4/02Fri 1/17/03ElecTechU[50%],InKind[1,888.8]100%
13
Design SCL interface
46.8 wMon 7/15/02Mon 6/23/03ElecEngU[30%],InKind[41,236]100%
14
Layout and fabricate SCL interface
8.6 wTue 6/24/03Fri 8/22/03ElecTechU[50%],InKind[11,199.2]100%
15
Bench test SCL interface
7.8 wMon 8/25/03Fri 10/17/03ElecTechU[50%],InKind[3,777.6]100%
16
ADF Prototype in-situ tests
9.4 wWed 10/15/03Mon 12/22/03PhysicistU,ElecEngU[20%],InKind[13,193.43]100%
17
Final ADF design - Production readiness review
10 wTue 12/9/03Thu 2/26/04ElecEngU,InKind[41,236]0%
18
Bench test 10% ADF
8 wWed 8/18/04Wed 10/13/04ElecTechU,ElecEngU[10%],PhysicistU[30%],InKind[18,409.28]0%
19
Digital filter FPGA programming
80 wMon 1/27/03Fri 8/27/04PhysicistU[30%],ElecEngU[10%],InKind[32,988.8]50%
20
ADF offline software and analysis
23 wMon 10/20/03Fri 4/9/04PhysicistU[50%]0%
21
MSU Tasks
301 dMon 10/20/03Wed 1/12/05 5%
22
Develop in-situ exercizing/debugging software
20 wMon 10/20/03Fri 3/19/04ElecEngU[50%],PhysicistU[50%],InKind[41,234.93]25%
23
ADF Prototype v.2
140 dMon 1/5/04Wed 7/21/04 0%
24
Layout ADF v.2 prototype
12 wMon 1/5/04Mon 3/29/04 0%
25
Fabricate ADF v.2 prototype
3 wTue 3/30/04Mon 4/19/04 0%
26
Assemble ADF v.2 prototype
3 wTue 4/20/04Mon 5/10/04 0%
27
Three ADF Cards Received By MSU
0 wMon 5/10/04Mon 5/10/04 0%
28
Two ADF Cards Received By Saclay
0 wMon 5/10/04Mon 5/10/04 0%
29
Perform bench tests at MSU
5 wTue 5/11/04Tue 6/15/04 0%
30
Perform tests at Fermilab
4 wWed 6/16/04Wed 7/14/04 0%
31
Production Design Approved
0 wWed 7/14/04Wed 7/14/04 0%
32
Production readiness review
1 wThu 7/15/04Wed 7/21/04 0%
33
Release ADF For Production
0 wWed 7/21/04Wed 7/21/04 0%
34
ADF Production
195 dTue 3/30/04Wed 1/12/05 0%
35
Procure ADF components
16 wTue 3/30/04Wed 7/21/04ElecEngU[4%],MandSPass[118,646.8]0%
36
Fabricate production ADF
18 wThu 8/12/04Mon 12/20/04ElecTechU[10%],MandSPass[51,746.88]0%
37
Bench test production ADF
18 wThu 8/26/04Wed 1/12/05ElecTechU,ElecEngU[10%],PhysicistU[30%],MandSPass[59,830.16]0%
38
L1 Calorimeter Trigger ADF Production Complete And Tested
0 wWed 1/12/05Wed 1/12/05 0%
39
ADF Crates
233 dThu 5/1/03Thu 4/8/04 48%
40
Prototypes
203 dThu 5/1/03Thu 2/26/04 55%
41
Design transition backplane
3.4 wThu 5/1/03Fri 5/23/03ElecEngU,InKind[24,741.6]100%
42
Layout and fabricate transition backplane
8 wTue 5/27/03Tue 7/22/03ElecTechU[50%],InKind[7,555.2]100%
43
Fabricate/Assemble prototype crate
9.2 wWed 7/23/03Thu 9/25/03ElecTechU[50%],InKind[7,555.2]100%
44
Test prototype ADF in prototype crate
16 wFri 9/26/03Thu 1/29/04PhysicistU[30%],ElecEngU[20%],ElecTechU[20%],InKind[9,619.84]10%
45
L1 Calorimeter Trigger ADF+Crate Prototype Complete
0 wThu 1/29/04Thu 1/29/04 0%
46
Final backplane design
4 wFri 1/30/04Thu 2/26/04ElecEngU,InKind[16,494.4]0%
47
Production
30 dFri 2/27/04Thu 4/8/04 0%
48
Procure crate components
5 wFri 2/27/04Thu 4/1/04MandSPass[51,144.44],ElecTechU[10%]0%
49
Assemble ADF crates
1 wFri 4/2/04Thu 4/8/04ElecTechU,MandSPass[5,388.8]0%
50
Trigger Algorithm Board
746 dFri 2/1/02Thu 2/3/05 76%
51
Prototypes
515 dFri 2/1/02Fri 2/27/04 96%
52
Choose L1 Calorimeter Trigger Baseline Jet Algorithm
0 wThu 8/8/02Thu 8/8/02 100%
53
Design prototype Trigger Algorithm Board (TAB)
49 wFri 2/1/02Tue 1/28/03ElecEngU[75%],InKind[94,972.2]100%
54
Layout prototype TAB
36.6 wFri 8/9/02Wed 5/7/03ElecEngU[15%],InKind[14,897.6]100%
55
Procure prototype TAB parts
33.6 wFri 8/23/02Wed 4/30/03ElecTechU[5%],InKind[17,931.2]100%
56
Fabricate/Assemble Prototype TAB
6.6 wThu 5/8/03Tue 6/24/03ElecTechU[10%],InKind[11,706.56]100%
57
Develop TAB/GAB test software
60 wMon 11/4/02Wed 1/28/04PostdocU[10%],StudentU[10%]94%
58
Test prototype TAB
9.4 wWed 6/25/03Fri 8/29/03PhysicistU[20%],ElecEngU[20%],ElecTechU[5%],StudentU[50%],InKind[15,327.72]100%
59
L1 Calorimeter Trigger TAB Prototype Complete
0 wFri 8/29/03Fri 8/29/03 100%
60
Pre-production TAB design
4 wMon 2/2/04Fri 2/27/04ElecEngU[20%],InKind[2,979.62]0%
61
Production
171 dMon 3/1/04Thu 10/28/04 0%
62
Procure TAB parts
10 wMon 3/1/04Fri 5/7/04ElecTechU[10%],MandSPass[60,373.2]0%
63
Layout pre-production TAB
6 wMon 3/1/04Fri 4/9/04ElecEngU[50%],MandSPass[11,173.2]0%
64
Fabricate/Assemple pre-production TAB
8 wMon 4/12/04Mon 6/7/04ElecTechU[10%],MandSPass[11,706.56]0%
65
Final design and layout changes to TAB
2 wThu 8/19/04Wed 9/1/04ElecEngU[50%],MandSPass[3,724.4]0%
66
Start Production TAB Fabrication
0 wThu 9/2/04Thu 9/2/04 0%
67
Fabricate production TAB
8 wThu 9/2/04Thu 10/28/04ElecTechU[10%],MandSPass[16,706.56]0%
68
Bench Testing
161 dTue 6/8/04Thu 2/3/05 0%
69
Bench test pre-production TAB
6 wTue 6/8/04Tue 7/20/04PhysicistU[30%],StudentU[75%],ElecEngU[30%],ElecTechU[10%],InKind[7,983.84]0%
70
Bench test production TAB
12 wFri 10/29/04Thu 2/3/05StudentU[20%],ElecEngU[5%],ElecTechU[5%],InKind[3,514.56]0%
71
Global Algorithm Board (GAB)
692 dMon 7/29/02Thu 5/12/05 68%
72
Prototype
394 dMon 7/29/02Wed 3/3/04 92%
73
Design prototype GAB
45.8 wMon 7/29/02Mon 6/30/03ElecEngU[36%],InKind[49,609.01]100%
74
Layout prototype GAB
18.4 wMon 7/21/03Wed 11/26/03ElecEngU[50%],InKind[7,443.29]100%
75
Procure prototype GAB parts
37 wFri 8/23/02Fri 5/23/03ElecTechU[4%],InKind[10,486.66]100%
76
Fabricate/Assemble Prototype GAB
4 wMon 12/1/03Tue 1/6/04ElecTechU[10%],InKind[5,353.28]33%
77
Test Prototype GAB
8 wWed 1/7/04Wed 3/3/04PhysicistU[10%],ElecEngU[10%],ElecTechU[5%],StudentU[25%],InKind[3,832.85]0%
78
L1 Calorimeter Trigger GAB Prototype Complete
0 wWed 3/3/04Wed 3/3/04 0%
79
Design/layout prototype VME/SCL interface
7 wMon 2/24/03Fri 4/11/03InKind[19,553.1],ElecEngU[75%]100%
80
Fabricate/assemble prototype VME/SCL interface
4.2 wMon 4/14/03Mon 5/12/03InKind[5,140],ElecTechU[10%]100%
81
Test prototype VME/SCL interface
9.4 wThu 5/22/03Tue 7/29/03InKind[3,832.85],ElecEngU[10%],ElecTechU[5%],StudentU[25%],PhysicistU[10%]100%
82
Production
321 dMon 2/2/04Thu 5/12/05 0%
83
Final GAB design - Production readiness review
4 wMon 2/2/04Fri 2/27/04ElecEngU[20%],MandSPass[2,979.52]0%
84
Procure GAB parts
10 wMon 3/1/04Fri 5/7/04ElecTechU[10%],MandSPass[7,133.2]0%
85
Layout final GAB
6 wMon 3/1/04Fri 4/9/04ElecEngU[12%],MandSPass[2,681.57]0%
86
Fabricate production GAB
8 wFri 2/4/05Thu 3/31/05ElecTechU[5%],MandSPass[3,853.33]0%
87
Bench test production GAB
6 wFri 4/1/05Thu 5/12/05PhysicistU[30%],StudentU[75%],ElecEngU[18%],ElecTechU[6%],MandSPass[4,790.35]0%
88
Final design/layout changes to production VME/SCL interface
4 wThu 3/4/04Wed 3/31/04MandSPass[2,979.52],ElecEngU[20%]0%
89
Fabricate/assemble production VME/SCL interface
4 wThu 4/1/04Wed 4/28/04MandSPass[3,426.67],ElecTechU[5%]0%
90
Bench test production VME/SCL interface
4 wThu 4/29/04Wed 5/26/04MandSPass[3,193.57],ElecEngU[18%],ElecTechU[6%],StudentU[25%],PhysicistU[10%]0%
91
Cables
603 dMon 9/9/02Thu 2/17/05 44%
92
Design and Fabricate system to test ADF to TAB cables
6 wMon 9/9/02Fri 10/18/02ElecTechU[10%],InKind[10,983.92],ElecEngU[30%]100%
93
Test ADF to TAB cables
2 wMon 10/21/02Fri 11/1/02ElecEngU[20%],StudentU[50%],InKind[1,489.76]100%
94
Procure ADF to TAB cables
10 wTue 11/30/04Thu 2/17/05ElecTechU[10%],MandSPass[19,914.1]0%
95
TAB Crates and Services
598 dMon 10/28/02Thu 3/31/05 45%
96
Prototype
101 dMon 10/28/02Mon 3/31/03 100%
97
Procure TAB crate for prototype TAB/GAB
11.2 wMon 10/28/02Mon 1/27/03ElecTechU[10%],InKind[11,513.12]100%
98
Procure VME CPU for prototype TAB/GAB
10.2 wFri 1/17/03Mon 3/31/03ElecTechU[10%],InKind[4,956.56]100%
99
Production
235 dTue 4/20/04Thu 3/31/05 0%
100
Specify TAB crate/power/cooling
2 wTue 4/20/04Mon 5/3/04ElecEngU[20%],MandSPass[1,489.76]0%
101
Procure TAB crate
16 wTue 11/30/04Thu 3/31/05ElecTechU[10%],MandSPass[12,513.12]0%
102
Procure TAB VME CPU
8 wTue 11/30/04Thu 2/3/05ElecTechU[10%],MandSPass[4,956.56]0%
103
L1 Calorimeter Trigger TAB/GAB Prototyping Complete
0 wWed 3/3/04Wed 3/3/04 0%
104
L1 Calorimeter Trigger TAB/GAB Production and Testing Complete
0 wThu 5/12/05Thu 5/12/05 0%
105
Prototype Integration
142 dTue 7/1/03Fri 1/30/04 59%
106
Develop in-situ exercizing/debugging software
28 wTue 7/1/03Wed 1/28/04ElecEngU[50%],PhysicistU[50%],InKind[16,494.4]87%
107
Prototype integration test ADF+TAB:Columbia
11.4 wWed 7/30/03Fri 10/17/03PhysicistU[10%],ElecEngU[20%],StudentU[50%],InKind[2,979.52]100%
108
Prototype integration test ADF+TAB:Saclay
11.4 wWed 7/30/03Fri 10/17/03PhysicistU[10%],ElecEngU[20%],StudentU[50%],InKind[3,298.88]100%
109
Prototype integration test ADF+TAB+GAB+TFW: MSU
13 wMon 10/20/03Fri 1/30/04PhysicistU[30%],ElecEngU[20%],InKind[6,597.58]25%
110
Prototype integration test ADF+TAB+GAB+TFW: Columbia
13 wMon 10/20/03Fri 1/30/04PhysicistU[10%],ElecEngU[20%],StudentU[50%],InKind[5,959.04]25%
111
Prototype integration test ADF+TAB+GAB+TFW: Saclay
13 wMon 10/20/03Fri 1/30/04PhysicistU[10%],ElecEngU[20%],StudentU[50%],InKind[6,597.76]25%
112
Prototype integration test ADF+TAB+GAB+TFW: Fermilab
13 wMon 10/20/03Fri 1/30/04ElecTechF[20%]25%
113
Pre-Production Integration
25 dThu 7/15/04Wed 8/18/04 0%
114
Pre-production integration test ADF+TAB+TFW: MSU
4 wThu 7/15/04Wed 8/11/04ElecEngU[20%],PhysicistU[30%],MandSPass[3,298.79]0%
115
Pre-production integration test ADF+TAB+TFW: Columbia
4 wThu 7/15/04Wed 8/11/04ElecEngU[20%],PhysicistU[30%],MandSPass[2,979.52]0%
116
Pre-production integration test ADF+TAB+TFW: Saclay
4 wThu 7/15/04Wed 8/11/04ElecEngU[20%],PhysicistU[30%],InKind[3,298.36]0%
117
Pre-production integration test ADF+TAB+TFW: Fermilab
4 wThu 7/15/04Wed 8/11/04ElecTechF[60%]0%
118
Production readiness review
1 wThu 8/12/04Wed 8/18/04ElecEngU,PhysicistU,MandSPass[4,000]0%
119
Production readiness review
1 wThu 8/12/04Wed 8/18/04ElecEngF[20%]0%
120
L1 Cal Online Software
475 dTue 4/15/03Tue 3/15/05 33%
121
ADF online software
95 wTue 4/15/03Tue 3/15/05PostdocU[25%],PhysicistU[10%]37%
122
TAB/GAB online software
87 wWed 6/11/03Tue 3/15/05PostdocU[25%],PhysicistU[10%]28%
123
L1 Calorimeter Trigger Production And Testing Complete
0 wThu 5/12/05Thu 5/12/05 0%
124
Level 1 Calorimeter Track Matching
590 dThu 8/1/02Tue 12/14/04 54%
125
D0 Reviews
37 dThu 6/12/03Tue 8/5/03 100%
126
D0 Internal Design Review Complete
0 wThu 6/12/03Thu 6/12/03 100%
127
D0 Production Readiness Review
1 wWed 7/30/03Tue 8/5/03ElecEngU[50%],PhysicistU[50%],MandSPass[2,000]100%
128
D0 Production Readiness Review
1 wWed 7/30/03Tue 8/5/03ElecEngF[20%]100%
129
L1 Trigger Cal-Trk Match R&D MOU (UAZ) Complete
0 wFri 3/14/03Fri 3/14/03 100%
130
L1 Trigger Cal-Trk Match Equipment MOU (UAZ) Complete
0 wFri 3/14/03Fri 3/14/03 100%
131
SLDB
270 dFri 3/14/03Tue 4/13/04 73%
132
Procure SLDB parts
19 wFri 3/14/03Mon 7/28/03ElecEngU[5%],MandSPass[29,153.22]100%
133
Fabricate and assemble SLDBs
33 wMon 6/16/03Tue 2/17/04ElecEngU[3%],MandSPass[11,419.14]75%
134
Test SLDBs
8 wWed 2/18/04Tue 4/13/04ElecTechU[60%],ElecEngU[20%],PhysicistU[20%],MandSPass[3,170.24]0%
135
MTCxx
440 dFri 3/14/03Tue 12/14/04 54%
136
(Small) design changes to MTCxx
41 wFri 3/14/03Mon 1/12/04ElecEngU[257%],MandSPass[2,296.32]98%
137
Procure MTCxx parts
16 wMon 6/9/03Tue 9/30/03ElecEngU[10%],MandSPass[23,325.38]100%
138
Fabricate and assemble preproduction MTCxx
6 wTue 1/13/04Tue 2/24/04ElecEngU[5%],MandSPass[4,005.04]0%
139
Fabrication and Assembly of L1 Trigger Cal-Trk Match Preproduction MTCxx Complete
0 wTue 2/24/04Tue 2/24/04 0%
140
Test preproduction MTCxx
8 wWed 2/25/04Tue 4/20/04ElecTechU[80%],ElecEngU[30%],PhysicistU[20%],MandS[4,354.56]0%
141
Final design changes to MTCxx
6 wWed 4/21/04Wed 6/2/04ElecEngU[40%],MandSPass[1,148.16]0%
142
Fabricate and assemble MTCxx's
16 wThu 6/3/04Fri 9/24/04ElecEngU[5%],MandSPass[8,500.72]0%
143
Fabrication and Assembly of L1 Trigger Cal-Trk Match MTCxx's Complete
0 wFri 9/24/04Fri 9/24/04 0%
144
Test MTCxx's
11 wMon 9/27/04Tue 12/14/04ElecEngU[20%],ElecTechU[80%],PhysicistF[20%],MandSPass[6,950.72]0%
145
MTCM
205 dMon 10/20/03Tue 8/17/04 24%
146
(Small) design changes to MTCM
11 wMon 10/20/03Thu 1/15/04ElecEngU[30%],MandSPass[1,148.16]90%
147
Procure MTCM parts
12 wFri 1/16/04Fri 4/9/04ElecEngU[10%],MandSPass[8,626.08]0%
148
Fabricate and assemble MTCMs
6 wMon 4/12/04Fri 5/21/04ElecEngU[5%],MandSPass[4,511.04]0%
149
Fabrication and Assembly of L1 Trigger Cal-Trk Match MTCM's Complete
0 wFri 5/21/04Fri 5/21/04 0%
150
Test MTCMs
12 wMon 5/24/04Tue 8/17/04ElecEngU[30%],MandSPass[1,722.24]0%
151
MT Flavor Board
500 dThu 8/1/02Thu 8/5/04 75%
152
Design prototype cal-trk algorithm
31.4 wThu 8/1/02Mon 3/24/03PhysicistU[25%]100%
153
Prototype
346 dThu 10/17/02Tue 3/16/04 89%
154
Design prototype MTFB
13.4 wThu 10/17/02Fri 1/31/03ElecEngU[30%],PhysicistU[20%],ElecTechU[50%],MandS[6,304.32]100%
155
Procure prototype MTFB parts
4 wMon 6/2/03Fri 6/27/03ElecEngU[5%],MandS[1,635.68]100%
156
Fabricate and assemble prototype MTFB
6 wMon 6/30/03Mon 8/11/03ElecEngU[5%],MandS[4,631.36]100%
157
Fabrication and Assembly of L1 Trigger Cal-Trk Match Prototype MTFB Complete
0 wMon 8/11/03Mon 8/11/03 100%
158
Test prototype MTFB
29 wTue 8/12/03Tue 3/16/04ElecEngU,PhysicistU,ElecTechU,MandS[1,985.92]80%
159
Production
100 dWed 3/17/04Thu 8/5/04 0%
160
Procure MTFB parts
4 wWed 3/17/04Tue 4/13/04ElecEngU[4%],MandSPass[8,623.09]0%
161
Fabricate and assemble MTFB
8 wWed 4/14/04Wed 6/9/04ElecEngU[5%],MandSPass[6,546.04]0%
162
Fabrication and Assembly of L1 Trigger Cal-Trk Match MTFB's Complete
0 wWed 6/9/04Wed 6/9/04 0%
163
Test MTFB
8 wThu 6/10/04Thu 8/5/04ElecTechU[60%],ElecEngU[10%],PhysicistU[20%],MandSPass[2,787.52]0%
164
Infrastructure
387 dFri 3/14/03Tue 9/28/04 41%
165
University of Arizona Tasks
387 dFri 3/14/03Tue 9/28/04 47%
166
Procure cables and connectors
16 wMon 6/30/03Tue 10/21/03ElecEngU[3%],MandSPass[16,639.36]100%
167
Assemble cables
12 wMon 5/24/04Tue 8/17/04PhysicistU[25%],ElecTechU[20%],MandSPass[601.2]0%
168
Procure VME crates
14 wMon 6/23/03Tue 9/30/03ElecTechU[3%],MandSPass[8,973.15]100%
169
Procure VME processors
26 wFri 3/14/03Tue 9/16/03ElecEngU[1%],MandSPass[8,492.38]100%
170
Procure power supplies
12.8 wTue 7/1/03Tue 9/30/03ElecEngU[1%],MandSPass[13,689.58]100%
171
Assemble and test power supplies
12.4 wTue 1/20/04Wed 4/14/04PhysicistU[10%],MandSPass[4,304.38],ElecEngU[1%]0%
172
Procure MSPLIT crates, backplanes, and power supplies
16 wThu 1/15/04Thu 5/6/04ElecTechU[5%],MandSPass[809.6]0%
173
Procure MSPLIT card parts
16 wThu 1/15/04Thu 5/6/04ElecEngU[5%],MandSPass[7,507.8]0%
174
Fabricate and assemble MSPLIT cards
12 wFri 5/7/04Mon 8/2/04ElecEngU[5%],ElecTechU[20%],MandSPass[12,808.44]0%
175
Test MSPLIT cards
8 wTue 8/3/04Tue 9/28/04ElecTechU[20%],ElecEngU[5%],PhysicistU[5%],MandSPass[992.96]0%
176
Fermilab Tasks
149 dTue 1/20/04Tue 8/17/04 0%
177
Assemble cables
12 wMon 5/24/04Tue 8/17/04ElecTechF[50%]0%
178
Assemble and test power supplies
12.4 wTue 1/20/04Wed 4/14/04ElecTechF[50%]0%
179
L1 Trigger Cal-Trk Match Production and Testing Completed
0 wTue 12/14/04Tue 12/14/04 0%
180
Level 1 Tracking
604 d?Thu 11/7/02Wed 4/20/05 22%
181
Prototype L1 Central Track Trigger Algorithm Coded And Simulated With FPGA Simulation Tools
0 wThu 11/7/02Thu 11/7/02 100%
182
Develop Target CTT Algorithm
154 dThu 11/7/02Wed 6/25/03 100%
183
Develop firmware for target CTT algorithm
22.8 wThu 11/7/02Tue 4/29/03ElecEngU,InKind[72,352]100%
184
Fit CTT firmware in selected FPGA, do timing studies
8 wWed 4/30/03Wed 6/25/03ElecEngU,InKind[12,920]100%
185
Target L1 Central Track Trigger Algorithm Firmware Coded And Simulated With FPGA Simulation Tools
0 wWed 6/25/03Wed 6/25/03 100%
186
Develop Test Procedures
140 dThu 6/26/03Fri 1/23/04 90%
187
Develop test procedures
28 wThu 6/26/03Fri 1/23/04ElecEngU[10%],InKind[1,550.4]90%
188
Develop test procedures
28 wThu 6/26/03Fri 1/23/04PhysicistU90%
189
DFEA Preproduction I
184 dThu 6/26/03Thu 3/25/04 82%
190
MRI Tasks - BU
184 dThu 6/26/03Thu 3/25/04 72%
191
Layout
11.2 wThu 6/26/03Mon 9/15/03ElecEngU,ElecTechU[10%],InKind[22,739]100%
192
Procure preproduction DFEA parts
5.4 wFri 8/22/03Tue 9/30/03ElecTechU[20%],InKind[2,067.2]100%
193
PCB fabrication
4 wMon 9/22/03Fri 10/17/03ElecTechU[20%],InKind[1,033.6]100%
194
Assembly
8.8 wMon 10/20/03Mon 12/22/03ElecTechU[15%],InKind[1,162.8]100%
195
Test
12 wTue 12/23/03Thu 3/25/04ElecEngU[75%],InKind[23,256],PhysicistU[50%]3%
196
DOE EQ Tasks - BU
124 dThu 6/26/03Mon 12/22/03 100%
197
Procure preproduction DFEA FPGAs
6 wThu 6/26/03Thu 8/7/03MandSPass[48,000],PhysicistU[2%]100%
198
Procure preproduction DFEA parts
5.4 wFri 8/22/03Tue 9/30/03MandSPass[1,500]100%
199
PCB fabrication
4 wMon 9/22/03Fri 10/17/03MandSPass[5,801]100%
200
Assembly
8.8 wMon 10/20/03Mon 12/22/03MandSPass[788]100%
201
DFEA Preproduction II
80 dMon 2/2/04Fri 5/21/04 0%
202
MRI Tasks - BU
80 dMon 2/2/04Fri 5/21/04 0%
203
Layout
4 wMon 2/2/04Fri 2/27/04ElecEngU,ElecTechU[25%],InKind[12,920]0%
204
PCB fabrication
2 wMon 3/1/04Fri 3/12/04ElecTechU[20%],InKind[1,033.6]0%
205
Procure preproduction parts
3 wMon 2/23/04Fri 3/12/04ElecTechU[1%],InKind[77.52]0%
206
Assembly
2 wMon 3/15/04Fri 3/26/04ElecTechU[20%],InKind[1,033.6]0%
207
Test
8 wMon 3/29/04Fri 5/21/04ElecEngU[50%],InKind[10,336],PhysicistU0%
208
Test at Fermilab
6 wMon 4/12/04Fri 5/21/04ElecEngU[10%],InKind[1,550.4],PhysicistU0%
209
DOE EQ Tasks-BU
25 dMon 2/23/04Fri 3/26/04 0%
210
PCB fabrication
2 wMon 3/1/04Fri 3/12/04MandSPass[5,801]0%
211
Procure preproduction parts
3 wMon 2/23/04Fri 3/12/04MandSPass[200]0%
212
Assembly
2 wMon 3/15/04Fri 3/26/04MandSPass[788]0%
213
Test at Fermilab
6 wMon 4/12/04Fri 5/21/04ElecTechF[50%],ElecEngF0%
214
Test at Fermilab
6 wMon 4/12/04Fri 5/21/04PhysicistU0%
215
Test at Fermilab
6 wMon 4/12/04Fri 5/21/04PhysicistU0%
216
L1 Central Track Trigger DFEA Prototype Tested At Fermilab
0 wFri 5/21/04Fri 5/21/04 0%
217
DFEA Production
225 dMon 5/24/04Wed 4/20/05 0%
218
MRI Tasks - BU
220 dTue 6/1/04Wed 4/20/05 0%
219
Procure FPGAs
20 wTue 6/29/04Wed 11/17/04InKind[356,000]0%
220
Procure FPGAs
20 wTue 6/1/04Wed 10/20/04ElecTechU[1%],InKind[516.8]0%
221
Design, layout
4 wTue 6/1/04Mon 6/28/04ElecEngU[50%],ElecTechU[50%],InKind[10,336]0%
222
Procure production parts
6 wTue 6/29/04Tue 8/10/04ElecTechU[10%],InKind[1,550.4]0%
223
PCB Fabricate
6 wWed 7/21/04Tue 8/31/04ElecTechU[5%],InKind[775.2]0%
224
Assembly
4 wWed 9/1/04Wed 9/29/04ElecTechU[3%],InKind[351.95]0%
225
Bench test
8 wThu 9/30/04Wed 11/24/04ElecEngU[75%],InKind[15,504],PhysicistU[50%]0%
226
Test at Fermilab
25 wThu 10/14/04Wed 4/20/05ElecEngU[20%],InKind[12,920],PhysicistU0%
227
DOE EQ Tasks-BU
225 dMon 5/24/04Wed 4/20/05 0%
228
Procure FPGAs
20 wTue 6/29/04Wed 11/17/04MandSPass[83,296]0%
229
Production readiness review-BU
1 wMon 5/24/04Fri 5/28/04ElecEngU[50%],PhysicistU,MandSPass[1,292]0%
230
Procure production parts
6 wTue 6/29/04Tue 8/10/04MandSPass[17,600]0%
231
PCB Fabricate
6 wWed 7/21/04Tue 8/31/04MandSPass[30,800]0%
232
Assembly
4 wWed 9/1/04Wed 9/29/04MandSPass[8,800]0%
233
Board rework
25 wThu 10/14/04Wed 4/20/05PhysicistU,MandSPass[8,800]0%
234
Production readiness review-Fermilab
1 wMon 5/24/04Fri 5/28/04ElecEngF[50%]0%
235
Test at Fermilab
25 wThu 10/14/04Wed 4/20/05PhysicistU0%
236
Test at Fermilab
25 wThu 10/14/04Wed 4/20/05PhysicistU,MandS[36,750],ElecTechU0%
237
Test at Fermilab
25 wThu 10/14/04Wed 4/20/05PhysicistF[50%],ElecTechF0%
238
L1 Central Track Trigger Production And Testing Complete
0 wWed 4/20/05Wed 4/20/05 0%
239
DFEA Backplane (BP)
183 d?Fri 1/2/04Mon 9/20/04 0%
240
hardware spec
21 dWed 1/14/04Thu 2/12/04Jamieson Olsen[20%]0%
241
timing spec (for CC/BP/DFEA)
14 dTue 1/27/04Fri 2/13/04Jamieson Olsen[20%]0%
242
interface specs (hardware+timing) finished
1 d?Mon 2/16/04Mon 2/16/04 0%
243
schematic + layout
4 monsFri 1/2/04Fri 4/23/04Jamieson Olsen[20%]0%
244
ready for production
1 d?Mon 4/26/04Mon 4/26/04 0%
245
production + vendor checkout
3 monsTue 4/27/04Wed 7/21/04InKind[14,000]0%
246
first BP received
1 d?Thu 7/22/04Thu 7/22/04 0%
247
FNAL checkout
2 wFri 7/23/04Thu 8/5/04Jamieson Olsen[20%]0%
248
crate assembly + bench test
2 wFri 8/6/04Thu 8/19/04Jamieson Olsen[20%],InKind[7,000]0%
249
test with CC
2 wFri 8/20/04Thu 9/2/04Jamieson Olsen[20%]0%
250
test with CC + DFEA
2 wFri 9/3/04Fri 9/17/04Jamieson Olsen[20%]0%
251
delivered to Boston
1 d?Mon 9/20/04Mon 9/20/04Jamieson Olsen0%
252
DFEA Crate Controller (CC)
297 d?Mon 12/1/03Wed 2/16/05Jamieson Olsen0%
253
interface specs
1 monMon 12/1/03Tue 1/6/04Jamieson Olsen0%
254
schematic + layout; order long leadtime parts
3 monsWed 1/14/04Wed 4/7/04Jamieson Olsen[20%]0%
255
PCB production + vendor testing
1 monThu 4/8/04Wed 5/5/04 0%
256
assembly (vendor)
2 monsThu 5/6/04Thu 7/1/04InKind[7,500]0%
257
checkout
2 wMon 7/5/04Fri 7/16/04Jamieson Olsen[20%]0%
258
Serial Command Link Receiver procurement
2 monsMon 3/1/04Fri 4/23/04Jamieson Olsen[5%],InKind[625]0%
259
test software/firmware
4 monsMon 3/1/04Mon 6/21/04Jamieson Olsen[20%]0%
260
finish software/firmware
8 monsTue 6/22/04Wed 2/16/05Jamieson Olsen[20%]0%
261
bench test
2 wMon 7/19/04Fri 7/30/04Jamieson Olsen[50%]0%
262
CC ready
1 d?Mon 8/2/04Mon 8/2/04 0%
263
optical Download and Control Link (DCL)
160 d?Thu 2/12/04Mon 9/27/04Jamieson Olsen0%
264
interface specs
1 monThu 2/12/04Wed 3/10/04Jamieson Olsen[20%]0%
265
hardware specs
1 monThu 3/11/04Wed 4/7/04Jamieson Olsen[20%]0%
266
specs done
1 d?Thu 4/8/04Thu 4/8/04 0%
267
hardware procurement
1 monFri 4/9/04Thu 5/6/04Jamieson Olsen[10%],InKind[1,000]0%
268
software: Linux driver
3 monsThu 4/8/04Thu 7/1/04Ron Rechenmacher or eqv.[30%]0%
269
software: EPICS driver + integration
3 monsThu 5/20/04Fri 8/13/04Geoff Savage or eqv.[30%]0%
270
software: dfe_ware integration
3 monsMon 7/5/04Mon 9/27/04Yurii Maravin replacement[50%]0%
271
bench test PC - CC
2 wMon 7/5/04Fri 7/16/04Jamieson Olsen[20%]0%
272      
273
L1 Trigger Upgrade Production and Testing Complete
0 wThu 5/12/05Thu 5/12/05 0%
274
Level 2 Beta Processor
305 dMon 12/1/03Mon 2/28/05 3%
275
Finalize Targets For Run2b Beta Upgrades
195 dMon 12/1/03Mon 9/13/04 6%
276
UVA Tasks
195 dMon 12/1/03Mon 9/13/04 9%
277
Assess Performance of Run2a Betas
8 wMon 12/1/03Wed 2/4/04PhysicistU[25%]43%
278
Develop & Simulate New Run2b Algortihms
30 wThu 2/5/04Fri 9/3/04PhysicistU0%
279
Production readiness review
1 wTue 9/7/04Mon 9/13/04PhysicistU[200%]0%
280
University-Other Tasks
190 dMon 12/1/03Fri 9/3/04 9%
281
Assess Performance of Run2a Betas
8 wMon 12/1/03Wed 2/4/04PhysicistU[200%]43%
282
Develop & Simulate New Run2b Algortihms
30 wThu 2/5/04Fri 9/3/04PhysicistU[400%]0%
283
Orsay Tasks
150 dThu 2/5/04Fri 9/3/04 0%
284
Develop & Simulate New Run2b Algortihms
30 wThu 2/5/04Fri 9/3/04PhysicistU0%
285
Develop Prototype
100 dThu 3/18/04Fri 8/6/04 0%
286
UVA Tasks
20 dThu 3/18/04Wed 4/14/04 0%
287
Survey processor market, chose candidate SBCs
4 wThu 3/18/04Wed 4/14/04PhysicistU[25%]0%
288
Evaluate software impact of new SBCs
4 wThu 3/18/04Wed 4/14/04PhysicistU[25%]0%
289
Evaluate firmware impact of new SBCs (function)
4 wThu 3/18/04Wed 4/14/04PhysicistU[25%]0%
290
Acquire 2 new processor SBCs for evaluation
12 wThu 4/15/04Fri 7/9/04PhysicistU[5%],MandS[8,160]0%
291
Orsay Tasks
100 dThu 3/18/04Fri 8/6/04 0%
292
Evaluate firmware impact of new SBCs (coding)
4 wThu 3/18/04Wed 4/14/04ElecEngU[50%],InKind[8,247.2]0%
293
Design disk adapter
4 wThu 4/15/04Wed 5/12/04ElecEngU[25%],InKind[4,123.6]0%
294
Specify/Acquire adapter components
4 wThu 5/13/04Thu 6/10/04ElecEngU[5%],InKind[1,024.72]0%
295
Layout adapter, generate artwork, etc
2 wFri 6/11/04Thu 6/24/04ElecEngU,InKind[8,247.2]0%
296
Find manufacturer for disk adapters
2 wFri 6/25/04Fri 7/9/04ElecEngU[25%],InKind[2,061.8]0%
297
Produce prototype adapters
3 wMon 7/12/04Fri 7/30/04ElecEngU[5%],InKind[868.54]0%
298
Test prototype adapters
1 wMon 8/2/04Fri 8/6/04PhysicistU[25%]0%
299
Level 2 Beta Trigger Prototype Preparation Complete
0 wFri 8/6/04Fri 8/6/04 0%
300
Test Prototype
60 dMon 8/9/04Mon 11/1/04 0%
301
UVA Tasks
60 dMon 8/9/04Mon 11/1/04 0%
302
Verify software compatibiity / hardware interface patches
8 wMon 8/9/04Mon 10/4/04PhysicistU[30%]0%
303
Verify processor operability in Beta motherboards
8 wMon 8/9/04Mon 10/4/04PhysicistU[60%]0%
304
Shadow mode studies
4 wTue 10/5/04Mon 11/1/04 0%
305
Orsay Tasks
40 dMon 8/9/04Mon 10/4/04 0%
306
Firmware support and tuning
8 wMon 8/9/04Mon 10/4/04ElecEngU[60%],InKind[19,793.28]0%
307
Level 2 Beta Trigger Prototype Testing Complete
0 wMon 11/1/04Mon 11/1/04 0%
308
Assemble Production Processors
95 dTue 10/5/04Mon 2/28/05 0%
309
Produce Disk Adapters
3 wTue 10/5/04Mon 10/25/04InKind[1,050],ElecTechU[10%]0%
310
Finalize Run2b SBC order
2 wTue 11/2/04Mon 11/15/04PhysicistU[30%]0%
311
Acquire Run2b SBCs
12 wTue 11/16/04Mon 2/21/05PhysicistU[5%],MandS[39,840]0%
312
Test production disk adapters
1 wTue 10/26/04Mon 11/1/04PhysicistU[25%]0%
313
Test SBCs
1 wTue 2/22/05Mon 2/28/05PhysicistU[25%]0%
314
L2 Beta Trigger Production And Testing Complete
0 wMon 2/28/05Mon 2/28/05 0%
315
Silicon Track Trigger Upgrade
504 dTue 1/21/03Mon 1/31/05 8%
316
Place Parts Orders for L2 Silicon Track Trigger
0 wMon 12/15/03Mon 12/15/03 100%
317
Production Readiness Review
1 wMon 7/26/04Fri 7/30/04ElecEngU[50%],PhysicistU,PhysicistF[20%],MandSPass[1,292]0%
318
Begin L2 Silicon Track Trigger Run IIb PCB Production
0 wMon 8/2/04Mon 8/2/04 0%
319
L2 Silicon Track Trigger Run IIb Inputs Finalized
0 wMon 12/15/03Mon 12/15/03 100%
320
VME Motherboard
235 dMon 12/15/03Mon 11/22/04 6%
321
Place orders
24 hMon 12/15/03Wed 12/17/03ElecTechU,MandSPass[480]100%
322
Parts
8 wThu 12/18/03Mon 2/23/04MandSPass[13,591]10%
323
Fabricate PCB
4 wMon 8/2/04Fri 8/27/04MandSPass[7,800]0%
324
Assemble
4 wMon 8/30/04Mon 9/27/04MandSPass[14,600]0%
325
All L2 Silicon Track Trigger Motherboards Delivered
0 wMon 9/27/04Mon 9/27/04 0%
326
Test
8 wTue 9/28/04Mon 11/22/04ElecEngU[10%],ElecTechU[20%],MandSPass[2,400]0%
327
L2 Silicon Track Trigger Motherboard Production Complete
0 wMon 11/22/04Mon 11/22/04 0%
328
STC Module
235 dMon 12/15/03Mon 11/22/04 6%
329
Place orders
0.6 wMon 12/15/03Wed 12/17/03ElecTechU,MandSPass[480]100%
330
Parts
8 wThu 12/18/03Mon 2/23/04MandSPass[15,786]10%
331
Fabricate PCB
4 wMon 8/2/04Fri 8/27/04MandSPass[4,182]0%
332
Assemble
4 wMon 8/30/04Mon 9/27/04MandSPass[1,090]0%
333
All L2 Silicon Track Trigger STCs Delivered
0 wMon 9/27/04Mon 9/27/04 0%
334
Test
8 wTue 9/28/04Mon 11/22/04ElecEngU[4%],ElecTechU[8%],MandSPass[1,120]0%
335
L2 Silicon Track Trigger STC Production Complete
0 wMon 11/22/04Mon 11/22/04 0%
336
VTM
86.5 dTue 1/21/03Wed 5/21/03 100%
337
Place order
12 hTue 1/21/03Wed 1/22/03 100%
338
Production
4 wWed 1/22/03Wed 2/19/03 100%
339
Test
13 wWed 2/19/03Wed 5/21/03 100%
340
VTM Production Complete for L2 Silicon Track Trigger
0 wWed 5/21/03Wed 5/21/03 100%
341
Link Transmitter Board
225 dMon 12/15/03Mon 11/8/04 6%
342
Place orders
12 hMon 12/15/03Tue 12/16/03ElecTechU,MandSPass[240]100%
343
Parts
8 wTue 12/16/03Fri 2/20/04MandSPass[6,561]14%
344
Fabricate PCB
4 wMon 8/2/04Fri 8/27/04MandSPass[2,190]0%
345
Assemble
4 wMon 8/30/04Mon 9/27/04MandSPass[718]0%
346
All L2 Silicon Track Trigger LTBs Delivered
0 wMon 9/27/04Mon 9/27/04 0%
347
Test
6 wTue 9/28/04Mon 11/8/04ElecTechU[33%],MandSPass[1,040]0%
348
L2 Silicon Track Trigger LTB Production Complete
0 wMon 11/8/04Mon 11/8/04 0%
349
Link Receiver Board
230 dMon 12/15/03Mon 11/15/04 6%
350
Place orders
12 hMon 12/15/03Tue 12/16/03ElecTechU,MandSPass[240]100%
351
Parts
8 wTue 12/16/03Fri 2/20/04MandSPass[9,297]14%
352
Fabricate PCB
4 wMon 8/2/04Fri 8/27/04MandSPass[2,010]0%
353
Assemble
4 wMon 8/30/04Mon 9/27/04MandSPass[710]0%
354
All L2 Silicon Track Trigger LRBs Delivered
0 wMon 9/27/04Mon 9/27/04 0%
355
Test
7 wTue 9/28/04Mon 11/15/04ElecTechU[30%],MandSPass[920]0%
356
L2 Silicon Track Trigger LRB Production Complete
0 wMon 11/15/04Mon 11/15/04 0%
357
BC Module
209 dFri 1/30/04Mon 11/22/04 0%
358
Place orders
0.6 wFri 1/30/04Tue 2/3/04ElecTechU,MandSPass[480]0%
359
Parts
8 wWed 2/4/04Tue 3/30/04MandSPass[13,000]0%
360
Fabricate PCB
4 wMon 8/2/04Fri 8/27/04MandSPass[3,950]0%
361
Assemble
4 wMon 8/30/04Mon 9/27/04MandSPass[1,960]0%
362
All L2 Silicon Track Trigger BCs Delivered
0 wMon 9/27/04Mon 9/27/04 0%
363
Test
8 wTue 9/28/04Mon 11/22/04ElecEngU[6%],ElecTechU[20%],MandSPass[2,000]0%
364
L2 Silicon Track Trigger BC Production Complete
0 wMon 11/22/04Mon 11/22/04 0%
365
TFC Module
227 dTue 1/20/04Wed 12/8/04 0%
366
Parts
8 wTue 1/20/04Mon 3/15/04MandS[25,997]0%
367
Fabricate PCB
4 wMon 8/2/04Fri 8/27/04MandS[7,800]0%
368
Assemble and rework
4 wMon 8/30/04Mon 9/27/04MandS[4,600]0%
369
All L2 Silicon Track Trigger TFCs Delivered
0 wMon 9/27/04Mon 9/27/04 0%
370
Test
10 wTue 9/28/04Wed 12/8/04ElecEngU[25%],MandS[4,000]0%
371
L2 Silicon Track Trigger TFC Production Complete
0 wWed 12/8/04Wed 12/8/04 0%
372
Hotlink Repeaters
200 dTue 1/20/04Thu 10/28/04 0%
373
Design & prototyping
8 wTue 1/20/04Mon 3/15/04ElecEngU,MandS[5,000]0%
374
Production
12 wTue 3/16/04Tue 6/8/04MandS[7,500]0%
375
Test
20 wWed 6/9/04Thu 10/28/04ElecTechU[4%],MandS[600]0%
376
L2 Silicon Track Trigger Hotlink Repeaters Complete
0 wThu 10/28/04Thu 10/28/04 0%
377
LVDS Cables
30 dWed 9/1/04Wed 10/13/04 0%
378
Fabricate
4 wWed 9/1/04Wed 9/29/04MandSPass[833]0%
379
Test
2 wThu 9/30/04Wed 10/13/04ElecTechU[10%],MandSPass[160]0%
380
L2 Silicon Track Trigger LVDS Cable Production Complete
0 wWed 10/13/04Wed 10/13/04 0%
381
Splitters
223 dWed 7/23/03Tue 6/15/04 9%
382
Go out for bids
2 wWed 7/23/03Tue 8/5/03 100%
383
Procure
16 wTue 1/20/04Mon 5/10/04MandS[3,250]0%
384
Test
5 wTue 5/11/04Tue 6/15/04ElecTechF[12%]0%
385
L2 Silicon Track Trigger Splitter Procurement Complete
0 wTue 6/15/04Tue 6/15/04 0%
386
Fibers
268 dWed 7/23/03Wed 8/18/04 9%
387
Go out for bids
2 wWed 7/23/03Tue 8/5/03 100%
388
Procure
16 wTue 3/30/04Wed 7/21/04MandS[1,300]0%
389
Test
4 wThu 7/22/04Wed 8/18/04ElecTechF[20%]0%
390
L2 Silicon Track Trigger Fiber Procurement Complete
0 wWed 8/18/04Wed 8/18/04 0%
391
L2 Silicon Track Trigger Hardware Production Complete
0 wWed 12/8/04Wed 12/8/04 0%
392
STC firmware
120 dTue 6/1/04Wed 11/17/04 0%
393
Update STC firmware
24 wTue 6/1/04Wed 11/17/04ElecEngU,MandSPass[38,400]0%
394
TFC Code
120 dMon 8/2/04Mon 1/31/05 0%
395
Change TFC code
24 wMon 8/2/04Mon 1/31/05PhysicistU0%
396
Downloading & Monitoring
100 dMon 8/2/04Wed 12/22/04 0%
397
Update downloading & monitoring software
20 wMon 8/2/04Wed 12/22/04PhysicistU0%
398
L2 Silicon Track Trigger Production and Testing Complete
0 wMon 1/31/05Mon 1/31/05 0%
399
L2 Trigger Upgrade Production and Testing Complete
0 wMon 2/28/05Mon 2/28/05 0%
400
Trigger Simulation
827 dThu 11/1/01Wed 3/9/05 59%
401
L1 Cal Simulation Software
742 dThu 11/1/01Wed 10/27/04 49%
402
Develop prototype L1Cal trigger algorithm
58.4 wThu 11/1/01Mon 1/13/03PhysicistU[50%],StudentU[50%]100%
403
Optimize algorithm performance with simulations
90 wTue 1/14/03Wed 10/27/04PhysicistU[20%]30%
404
Integrate algorithm into Dzero Trigger Simulation
83 wMon 2/3/03Mon 9/27/04PhysicistU[20%]33%
405
L1 Cal/Track Match Simulation Software
530 dWed 1/22/03Wed 3/9/05 21%
406
Develop prototype L1Cal/Track match trigger algorithm
90 wWed 1/22/03Wed 11/3/04PhysicistU[50%],StudentU[50%]25%
407
Optimize algorithm performance with simulations
10 wThu 11/4/04Wed 1/26/05PhysicistU[20%]0%
408
Integrate algorithm into Dzero Trigger Simulation
6 wThu 1/27/05Wed 3/9/05PhysicistU[20%]0%
409
L1CTT Simulation
690 dFri 2/1/02Wed 11/3/04 78%
410
Develop prototype CTT algorithm
48 wFri 2/1/02Tue 1/21/03PhysicistU[50%]100%
411
Develop prototype CTT algorithm
48 wFri 2/1/02Tue 1/21/03PhysicistF100%
412
Develop prototype CTT algorithm
48 wFri 2/1/02Tue 1/21/03PhysicistU[50%]100%
413
Develop prototype CTT algorithm
48 wFri 2/1/02Tue 1/21/03PhysicistU[50%]100%
414
Develop prototype CTT algorithm
48 wFri 2/1/02Tue 1/21/03PhysicistU[50%]100%
415
Optimize algorithm performance with simulations
90 wWed 1/22/03Wed 11/3/04PhysicistU[50%]70%
416
Integrate algorithm into Dzero Trigger Simulation
75 wTue 4/1/03Tue 9/28/04PhysicistU[50%]15%
417
STT Simulator
100 dMon 12/15/03Wed 5/12/04 0%
418
Update simulator
20 wMon 12/15/03Wed 5/12/04PhysicistU0%
419
Administration
520 dMon 2/3/03Mon 3/7/05 41%
420
Project Management
104 wMon 2/3/03Mon 3/7/05PhysicistU[280%]41%
421
Travel vendor and collaborator visits
104 wMon 2/3/03Mon 3/7/05MandS[3,500]41%
422
Shipping costs
104 wMon 2/3/03Mon 3/7/05MandS[2,000]41%

Resources

IDNameGroupMax UnitsPeak Units
1MechEngFF1,000%0%
2MechEngUU1,000%0%
3ElecEngFF1,000%100%
4ElecEngUU1,000%767%
5MechTechFF1,000%0%
6MechTechUU1,000%0%
7ElecTechFF1,000%130%
8ElecTechUU1,000%534%
9PhysicistFF1,000%70%
10PhysicistUU1,000%1,745%
11CompProfFF1,000%0%
12CompProfUU1,000%0%
13StudentUU400%210%
14PostdocUU100%60%
15MandS  0/d
16MandSPass  0/h
17MandSExempt  0/d
18InKind  0/d
19AdminAsstFF100%0%
20Jamieson Olsen 100%320%
21Ron Rechenmacher or eqv. 100%30%
22Geoff Savage or eqv. 100%30%
23Yurii Maravin replacement 100%50%

Assignments

Task IDTask NameResource NameWorkStartFinish% Work Complete
5Design prototype ADFElecEngU2,120 hWed 1/2/02Fri 1/24/03100%
5Design prototype ADFInKind189,655.6Wed 1/2/02Fri 1/24/03100%
6Layout prototype ADFElecTechU680 hMon 1/27/03Fri 5/23/03100%
6Layout prototype ADFInKind15,110.4Mon 1/27/03Fri 5/23/03100%
7Fabricate/Assemble Prototype ADFElecTechU104 hTue 5/27/03Tue 7/1/03100%
7Fabricate/Assemble Prototype ADFInKind60,055.2Tue 5/27/03Tue 7/1/03100%
8Bench Test Prototype ADFPhysicistU163.2 hTue 7/15/03Fri 10/17/03100%
8Bench Test Prototype ADFElecEngU108.8 hTue 7/15/03Fri 10/17/03100%
8Bench Test Prototype ADFElecTechU108.8 hTue 7/15/03Fri 10/17/03100%
8Bench Test Prototype ADFInKind20,632.24Tue 7/15/03Fri 10/17/03100%
10Design analog splitterElecEngU160 hFri 3/1/02Thu 3/28/02100%
10Design analog splitterInKind16,494.4Fri 3/1/02Fri 3/1/02100%
11Layout and fabricate analog splitterElecTechU160 hMon 7/1/02Mon 8/26/02100%
11Layout and fabricate analog splitterInKind9,150.2Mon 7/1/02Mon 8/26/02100%
12Bench test analog splitterElecTechU116 hMon 11/4/02Fri 1/17/03100%
12Bench test analog splitterInKind1,888.8Mon 11/4/02Fri 1/17/03100%
13Design SCL interfaceElecEngU561.6 hMon 7/15/02Mon 6/23/03100%
13Design SCL interfaceInKind41,236Mon 7/15/02Mon 6/23/03100%
14Layout and fabricate SCL interfaceElecTechU172 hTue 6/24/03Fri 8/22/03100%
14Layout and fabricate SCL interfaceInKind11,199.2Tue 6/24/03Fri 8/22/03100%
15Bench test SCL interfaceElecTechU156 hMon 8/25/03Fri 10/17/03100%
15Bench test SCL interfaceInKind3,777.6Mon 8/25/03Fri 10/17/03100%
16ADF Prototype in-situ testsPhysicistU376 hWed 10/15/03Mon 12/22/03100%
16ADF Prototype in-situ testsElecEngU75.2 hWed 10/15/03Mon 12/22/03100%
16ADF Prototype in-situ testsInKind13,193.43Wed 10/15/03Mon 12/22/03100%
17Final ADF design - Production readiness reviewElecEngU400 hTue 12/9/03Thu 2/26/040%
17Final ADF design - Production readiness reviewInKind41,236Tue 12/9/03Thu 2/26/040%
18Bench test 10% ADFElecTechU320 hWed 8/18/04Wed 10/13/040%
18Bench test 10% ADFElecEngU32 hWed 8/18/04Wed 10/13/040%
18Bench test 10% ADFPhysicistU96 hWed 8/18/04Wed 10/13/040%
18Bench test 10% ADFInKind18,409.28Wed 8/18/04Wed 10/13/040%
19Digital filter FPGA programmingPhysicistU960 hMon 1/27/03Fri 8/27/0450%
19Digital filter FPGA programmingElecEngU320 hMon 1/27/03Fri 8/27/0450%
19Digital filter FPGA programmingInKind32,988.8Mon 1/27/03Fri 8/27/0450%
20ADF offline software and analysisPhysicistU460 hMon 10/20/03Fri 4/9/040%
22Develop in-situ exercizing/debugging softwareElecEngU400 hMon 10/20/03Fri 3/19/0425%
22Develop in-situ exercizing/debugging softwarePhysicistU400 hMon 10/20/03Fri 3/19/0425%
22Develop in-situ exercizing/debugging softwareInKind41,234.93Mon 10/20/03Fri 3/19/0425%
35Procure ADF componentsElecEngU24.62 hTue 3/30/04Wed 7/21/040%
35Procure ADF componentsMandSPass118,646.8Tue 3/30/04Wed 7/21/040%
36Fabricate production ADFElecTechU72 hThu 8/12/04Mon 12/20/040%
36Fabricate production ADFMandSPass51,746.88Thu 8/12/04Mon 12/20/040%
37Bench test production ADFElecTechU720 hThu 8/26/04Wed 1/12/050%
37Bench test production ADFElecEngU72 hThu 8/26/04Wed 1/12/050%
37Bench test production ADFPhysicistU216 hThu 8/26/04Wed 1/12/050%
37Bench test production ADFMandSPass59,830.16Thu 8/26/04Wed 1/12/050%
41Design transition backplaneElecEngU136 hThu 5/1/03Fri 5/23/03100%
41Design transition backplaneInKind24,741.6Thu 5/1/03Fri 5/23/03100%
42Layout and fabricate transition backplaneElecTechU160 hTue 5/27/03Tue 7/22/03100%
42Layout and fabricate transition backplaneInKind7,555.2Tue 5/27/03Tue 7/22/03100%
43Fabricate/Assemble prototype crateElecTechU184 hWed 7/23/03Thu 9/25/03100%
43Fabricate/Assemble prototype crateInKind7,555.2Wed 7/23/03Thu 9/25/03100%
44Test prototype ADF in prototype cratePhysicistU192 hFri 9/26/03Thu 1/29/0410%
44Test prototype ADF in prototype crateElecEngU128 hFri 9/26/03Thu 1/29/0410%
44Test prototype ADF in prototype crateElecTechU128 hFri 9/26/03Thu 1/29/0410%
44Test prototype ADF in prototype crateInKind9,619.84Fri 9/26/03Thu 1/29/0420%
46Final backplane designElecEngU160 hFri 1/30/04Thu 2/26/040%
46Final backplane designInKind16,494.4Fri 1/30/04Thu 2/26/040%
48Procure crate componentsMandSPass51,144.44Fri 2/27/04Thu 4/1/040%
48Procure crate componentsElecTechU20 hFri 2/27/04Thu 4/1/040%
49Assemble ADF cratesElecTechU40 hFri 4/2/04Thu 4/8/040%
49Assemble ADF cratesMandSPass5,388.8Fri 4/2/04Thu 4/8/040%
53Design prototype Trigger Algorithm Board (TAB)ElecEngU1,453.68 hFri 2/1/02Tue 1/28/03100%
53Design prototype Trigger Algorithm Board (TAB)InKind94,972.2Fri 2/1/02Tue 1/28/03100%
54Layout prototype TABElecEngU219.6 hFri 8/9/02Wed 5/7/03100%
54Layout prototype TABInKind14,897.6Fri 8/9/02Wed 5/7/03100%
55Procure prototype TAB partsElecTechU67.2 hFri 8/23/02Wed 4/30/03100%
55Procure prototype TAB partsInKind17,931.2Fri 8/23/02Wed 4/30/03100%
56Fabricate/Assemble Prototype TABElecTechU26.4 hThu 5/8/03Tue 6/24/03100%
56Fabricate/Assemble Prototype TABInKind11,706.56Thu 5/8/03Tue 6/24/03100%
57Develop TAB/GAB test softwarePostdocU240 hMon 11/4/02Wed 1/28/0494%
57Develop TAB/GAB test softwareStudentU240 hMon 11/4/02Wed 1/28/0494%
58Test prototype TABPhysicistU75.2 hWed 6/25/03Fri 8/29/03100%
58Test prototype TABElecEngU75.2 hWed 6/25/03Fri 8/29/03100%
58Test prototype TABElecTechU18.8 hWed 6/25/03Fri 8/29/03100%
58Test prototype TABStudentU188 hWed 6/25/03Fri 8/29/03100%
58Test prototype TABInKind15,327.72Wed 6/25/03Fri 8/29/03100%
60Pre-production TAB designElecEngU32 hMon 2/2/04Fri 2/27/040%
60Pre-production TAB designInKind2,979.62Mon 2/2/04Fri 2/27/040%
62Procure TAB partsElecTechU40 hMon 3/1/04Fri 5/7/040%
62Procure TAB partsMandSPass60,373.2Mon 3/1/04Fri 5/7/040%
63Layout pre-production TABElecEngU120 hMon 3/1/04Fri 4/9/040%
63Layout pre-production TABMandSPass11,173.2Mon 3/1/04Fri 4/9/040%
64Fabricate/Assemple pre-production TABElecTechU32 hMon 4/12/04Mon 6/7/040%
64Fabricate/Assemple pre-production TABMandSPass11,706.56Mon 4/12/04Mon 6/7/040%
65Final design and layout changes to TABElecEngU40 hThu 8/19/04Wed 9/1/040%
65Final design and layout changes to TABMandSPass3,724.4Thu 8/19/04Wed 9/1/040%
67Fabricate production TABElecTechU32 hThu 9/2/04Thu 10/28/040%
67Fabricate production TABMandSPass16,706.56Thu 9/2/04Thu 10/28/040%
69Bench test pre-production TABPhysicistU72 hTue 6/8/04Tue 7/20/040%
69Bench test pre-production TABStudentU180 hTue 6/8/04Tue 7/20/040%
69Bench test pre-production TABElecEngU72 hTue 6/8/04Tue 7/20/040%
69Bench test pre-production TABElecTechU24 hTue 6/8/04Tue 7/20/040%
69Bench test pre-production TABInKind7,983.84Tue 6/8/04Tue 7/20/040%
70Bench test production TABStudentU96 hFri 10/29/04Thu 2/3/050%
70Bench test production TABElecEngU24 hFri 10/29/04Thu 2/3/050%
70Bench test production TABElecTechU24 hFri 10/29/04Thu 2/3/050%
70Bench test production TABInKind3,514.56Fri 10/29/04Thu 2/3/050%
73Design prototype GABElecEngU450.9 hMon 7/29/02Mon 6/30/03100%
73Design prototype GABInKind49,609.01Mon 7/29/02Mon 6/30/03100%
74Layout prototype GABElecEngU368 hMon 7/21/03Wed 11/26/03100%
74Layout prototype GABInKind7,443.29Mon 7/21/03Wed 11/26/03100%
75Procure prototype GAB partsElecTechU59.2 hFri 8/23/02Fri 5/23/03100%
75Procure prototype GAB partsInKind10,486.66Fri 8/23/02Fri 5/23/03100%
76Fabricate/Assemble Prototype GABElecTechU16 hMon 12/1/03Tue 1/6/0433%
76Fabricate/Assemble Prototype GABInKind5,353.28Mon 12/1/03Tue 1/6/0433%
77Test Prototype GABPhysicistU32 hWed 1/7/04Wed 3/3/040%
77Test Prototype GABElecEngU32 hWed 1/7/04Wed 3/3/040%
77Test Prototype GABElecTechU16 hWed 1/7/04Wed 3/3/040%
77Test Prototype GABStudentU80 hWed 1/7/04Wed 3/3/040%
77Test Prototype GABInKind3,832.85Wed 1/7/04Wed 3/3/040%
79Design/layout prototype VME/SCL interfaceInKind19,553.1Mon 2/24/03Fri 4/11/03100%
79Design/layout prototype VME/SCL interfaceElecEngU210 hMon 2/24/03Fri 4/11/03100%
80Fabricate/assemble prototype VME/SCL interfaceInKind5,140Mon 4/14/03Mon 5/12/03100%
80Fabricate/assemble prototype VME/SCL interfaceElecTechU16.8 hMon 4/14/03Mon 5/12/03100%
81Test prototype VME/SCL interfaceInKind3,832.85Thu 5/22/03Tue 7/29/03100%
81Test prototype VME/SCL interfaceElecEngU37.6 hThu 5/22/03Tue 7/29/03100%
81Test prototype VME/SCL interfaceElecTechU18.8 hThu 5/22/03Tue 7/29/03100%
81Test prototype VME/SCL interfaceStudentU94 hThu 5/22/03Tue 7/29/03100%
81Test prototype VME/SCL interfacePhysicistU37.6 hThu 5/22/03Tue 7/29/03100%
83Final GAB design - Production readiness reviewElecEngU32 hMon 2/2/04Fri 2/27/040%
83Final GAB design - Production readiness reviewMandSPass2,979.52Mon 2/2/04Fri 2/27/040%
84Procure GAB partsElecTechU40 hMon 3/1/04Fri 5/7/040%
84Procure GAB partsMandSPass7,133.2Mon 3/1/04Fri 5/7/040%
85Layout final GABElecEngU28.8 hMon 3/1/04Fri 4/9/040%
85Layout final GABMandSPass2,681.57Mon 3/1/04Fri 4/9/040%
86Fabricate production GABElecTechU16 hFri 2/4/05Thu 3/31/050%
86Fabricate production GABMandSPass3,853.33Fri 2/4/05Thu 3/31/050%
87Bench test production GABPhysicistU72 hFri 4/1/05Thu 5/12/050%
87Bench test production GABStudentU180 hFri 4/1/05Thu 5/12/050%
87Bench test production GABElecEngU43.2 hFri 4/1/05Thu 5/12/050%
87Bench test production GABElecTechU14.4 hFri 4/1/05Thu 5/12/050%
87Bench test production GABMandSPass4,790.35Fri 4/1/05Thu 5/12/050%
88Final design/layout changes to production VME/SCL interfaceMandSPass2,979.52Thu 3/4/04Wed 3/31/040%
88Final design/layout changes to production VME/SCL interfaceElecEngU32 hThu 3/4/04Wed 3/31/040%
89Fabricate/assemble production VME/SCL interfaceMandSPass3,426.67Thu 4/1/04Wed 4/28/040%
89Fabricate/assemble production VME/SCL interfaceElecTechU8 hThu 4/1/04Wed 4/28/040%
90Bench test production VME/SCL interfaceMandSPass3,193.57Thu 4/29/04Wed 5/26/040%
90Bench test production VME/SCL interfaceElecEngU28.8 hThu 4/29/04Wed 5/26/040%
90Bench test production VME/SCL interfaceElecTechU9.6 hThu 4/29/04Wed 5/26/040%
90Bench test production VME/SCL interfaceStudentU40 hThu 4/29/04Wed 5/26/040%
90Bench test production VME/SCL interfacePhysicistU16 hThu 4/29/04Wed 5/26/040%
92Design and Fabricate system to test ADF to TAB cablesElecTechU9.6 hMon 9/9/02Fri 10/18/02100%
92Design and Fabricate system to test ADF to TAB cablesInKind10,983.92Mon 9/9/02Fri 10/18/02100%
92Design and Fabricate system to test ADF to TAB cablesElecEngU7.2 hWed 10/16/02Fri 10/18/02100%
93Test ADF to TAB cablesElecEngU16 hMon 10/21/02Fri 11/1/02100%
93Test ADF to TAB cablesStudentU40 hMon 10/21/02Fri 11/1/02100%
93Test ADF to TAB cablesInKind1,489.76Mon 10/21/02Fri 11/1/02100%
94Procure ADF to TAB cablesElecTechU40 hTue 11/30/04Thu 2/17/050%
94Procure ADF to TAB cablesMandSPass19,914.1Tue 11/30/04Thu 2/17/050%
97Procure TAB crate for prototype TAB/GABElecTechU44.8 hMon 10/28/02Mon 1/27/03100%
97Procure TAB crate for prototype TAB/GABInKind11,513.12Mon 10/28/02Mon 1/27/03100%
98Procure VME CPU for prototype TAB/GABElecTechU40.8 hFri 1/17/03Mon 3/31/03100%
98Procure VME CPU for prototype TAB/GABInKind4,956.56Fri 1/17/03Mon 3/31/03100%
100Specify TAB crate/power/coolingElecEngU16 hTue 4/20/04Mon 5/3/040%
100Specify TAB crate/power/coolingMandSPass1,489.76Tue 4/20/04Mon 5/3/040%
101Procure TAB crateElecTechU64 hTue 11/30/04Thu 3/31/050%
101Procure TAB crateMandSPass12,513.12Tue 11/30/04Thu 3/31/050%
102Procure TAB VME CPUElecTechU32 hTue 11/30/04Thu 2/3/050%
102Procure TAB VME CPUMandSPass4,956.56Tue 11/30/04Thu 2/3/050%
106Develop in-situ exercizing/debugging softwareElecEngU560 hTue 7/1/03Wed 1/28/0487%
106Develop in-situ exercizing/debugging softwarePhysicistU560 hTue 7/1/03Wed 1/28/0487%
106Develop in-situ exercizing/debugging softwareInKind16,494.4Tue 7/1/03Wed 1/28/0496%
107Prototype integration test ADF+TAB:ColumbiaPhysicistU45.6 hWed 7/30/03Fri 10/17/03100%
107Prototype integration test ADF+TAB:ColumbiaElecEngU91.2 hWed 7/30/03Fri 10/17/03100%
107Prototype integration test ADF+TAB:ColumbiaStudentU228 hWed 7/30/03Fri 10/17/03100%
107Prototype integration test ADF+TAB:ColumbiaInKind2,979.52Wed 7/30/03Fri 10/17/03100%
108Prototype integration test ADF+TAB:SaclayPhysicistU45.6 hWed 7/30/03Fri 10/17/03100%
108Prototype integration test ADF+TAB:SaclayElecEngU91.2 hWed 7/30/03Fri 10/17/03100%
108Prototype integration test ADF+TAB:SaclayStudentU228 hWed 7/30/03Fri 10/17/03100%
108Prototype integration test ADF+TAB:SaclayInKind3,298.88Wed 7/30/03Fri 10/17/03100%
109Prototype integration test ADF+TAB+GAB+TFW: MSUPhysicistU156 hMon 10/20/03Fri 1/30/0425%
109Prototype integration test ADF+TAB+GAB+TFW: MSUElecEngU104 hMon 10/20/03Fri 1/30/0425%
109Prototype integration test ADF+TAB+GAB+TFW: MSUInKind6,597.58Mon 10/20/03Fri 1/30/0434%
110Prototype integration test ADF+TAB+GAB+TFW: ColumbiaPhysicistU52 hMon 10/20/03Fri 1/30/0425%
110Prototype integration test ADF+TAB+GAB+TFW: ColumbiaElecEngU104 hMon 10/20/03Fri 1/30/0425%
110Prototype integration test ADF+TAB+GAB+TFW: ColumbiaStudentU260 hMon 10/20/03Fri 1/30/0425%
110Prototype integration test ADF+TAB+GAB+TFW: ColumbiaInKind5,959.04Mon 10/20/03Fri 1/30/0434%
111Prototype integration test ADF+TAB+GAB+TFW: SaclayPhysicistU52 hMon 10/20/03Fri 1/30/0425%
111Prototype integration test ADF+TAB+GAB+TFW: SaclayElecEngU104 hMon 10/20/03Fri 1/30/0425%
111Prototype integration test ADF+TAB+GAB+TFW: SaclayStudentU260 hMon 10/20/03Fri 1/30/0425%
111Prototype integration test ADF+TAB+GAB+TFW: SaclayInKind6,597.76Mon 10/20/03Fri 1/30/0434%
112Prototype integration test ADF+TAB+GAB+TFW: FermilabElecTechF104 hMon 10/20/03Fri 1/30/0425%
114Pre-production integration test ADF+TAB+TFW: MSUElecEngU32 hThu 7/15/04Wed 8/11/040%
114Pre-production integration test ADF+TAB+TFW: MSUPhysicistU48 hThu 7/15/04Wed 8/11/040%
114Pre-production integration test ADF+TAB+TFW: MSUMandSPass3,298.79Thu 7/15/04Wed 8/11/040%
115Pre-production integration test ADF+TAB+TFW: ColumbiaElecEngU32 hThu 7/15/04Wed 8/11/040%
115Pre-production integration test ADF+TAB+TFW: ColumbiaPhysicistU48 hThu 7/15/04Wed 8/11/040%
115Pre-production integration test ADF+TAB+TFW: ColumbiaMandSPass2,979.52Thu 7/15/04Wed 8/11/040%
116Pre-production integration test ADF+TAB+TFW: SaclayElecEngU32 hThu 7/15/04Wed 8/11/040%
116Pre-production integration test ADF+TAB+TFW: SaclayPhysicistU48 hThu 7/15/04Wed 8/11/040%
116Pre-production integration test ADF+TAB+TFW: SaclayInKind3,298.36Thu 7/15/04Wed 8/11/040%
117Pre-production integration test ADF+TAB+TFW: FermilabElecTechF96 hThu 7/15/04Wed 8/11/040%
118Production readiness reviewElecEngU40 hThu 8/12/04Wed 8/18/040%
118Production readiness reviewPhysicistU40 hThu 8/12/04Wed 8/18/040%
118Production readiness reviewMandSPass4,000Thu 8/12/04Wed 8/18/040%
119Production readiness reviewElecEngF8 hThu 8/12/04Wed 8/18/040%
121ADF online softwarePostdocU950 hTue 4/15/03Tue 3/15/0537%
121ADF online softwarePhysicistU380 hTue 4/15/03Tue 3/15/0537%
122TAB/GAB online softwarePostdocU870 hWed 6/11/03Tue 3/15/0528%
122TAB/GAB online softwarePhysicistU348 hWed 6/11/03Tue 3/15/0528%
127D0 Production Readiness ReviewElecEngU20 hWed 7/30/03Tue 8/5/03100%
127D0 Production Readiness ReviewPhysicistU20 hWed 7/30/03Tue 8/5/03100%
127D0 Production Readiness ReviewMandSPass2,000Wed 7/30/03Tue 8/5/03100%
128D0 Production Readiness ReviewElecEngF8 hWed 7/30/03Tue 8/5/03100%
132Procure SLDB partsElecEngU38 hFri 3/14/03Mon 7/28/03100%
132Procure SLDB partsMandSPass29,153.22Fri 3/14/03Mon 7/28/03100%
133Fabricate and assemble SLDBsElecEngU39.6 hMon 6/16/03Tue 2/17/0475%
133Fabricate and assemble SLDBsMandSPass11,419.14Mon 6/16/03Tue 2/17/0475%
134Test SLDBsElecTechU192 hWed 2/18/04Tue 4/13/040%
134Test SLDBsElecEngU64 hWed 2/18/04Tue 4/13/040%
134Test SLDBsPhysicistU64 hWed 2/18/04Tue 4/13/040%
134Test SLDBsMandSPass3,170.24Wed 2/18/04Tue 4/13/040%
136(Small) design changes to MTCxxElecEngU4,214 hFri 3/14/03Mon 1/12/0498%
136(Small) design changes to MTCxxMandSPass2,296.32Fri 3/14/03Mon 1/12/0498%
137Procure MTCxx partsElecEngU64 hMon 6/9/03Tue 9/30/03100%
137Procure MTCxx partsMandSPass23,325.38Mon 6/9/03Tue 9/30/03100%
138Fabricate and assemble preproduction MTCxxElecEngU12 hTue 1/13/04Tue 2/24/040%
138Fabricate and assemble preproduction MTCxxMandSPass4,005.04Tue 1/13/04Tue 2/24/040%
140Test preproduction MTCxxElecTechU256 hWed 2/25/04Tue 4/20/040%
140Test preproduction MTCxxElecEngU96 hWed 2/25/04Tue 4/20/040%
140Test preproduction MTCxxPhysicistU64 hWed 2/25/04Tue 4/20/040%
140Test preproduction MTCxxMandS4,354.56Wed 2/25/04Tue 4/20/040%
141Final design changes to MTCxxElecEngU96 hWed 4/21/04Wed 6/2/040%
141Final design changes to MTCxxMandSPass1,148.16Wed 4/21/04Wed 6/2/040%
142Fabricate and assemble MTCxx'sElecEngU32 hThu 6/3/04Fri 9/24/040%
142Fabricate and assemble MTCxx'sMandSPass8,500.72Thu 6/3/04Fri 9/24/040%
144Test MTCxx'sElecEngU88 hMon 9/27/04Tue 12/14/040%
144Test MTCxx'sElecTechU352 hMon 9/27/04Tue 12/14/040%
144Test MTCxx'sPhysicistF88 hMon 9/27/04Tue 12/14/040%
144Test MTCxx'sMandSPass6,950.72Mon 9/27/04Tue 12/14/040%
146(Small) design changes to MTCMElecEngU132 hMon 10/20/03Thu 1/15/0490%
146(Small) design changes to MTCMMandSPass1,148.16Mon 10/20/03Thu 1/15/0493%
147Procure MTCM partsElecEngU48 hFri 1/16/04Fri 4/9/040%
147Procure MTCM partsMandSPass8,626.08Fri 1/16/04Fri 4/9/040%
148Fabricate and assemble MTCMsElecEngU12 hMon 4/12/04Fri 5/21/040%
148Fabricate and assemble MTCMsMandSPass4,511.04Mon 4/12/04Fri 5/21/040%
150Test MTCMsElecEngU144 hMon 5/24/04Tue 8/17/040%
150Test MTCMsMandSPass1,722.24Mon 5/24/04Tue 8/17/040%
152Design prototype cal-trk algorithmPhysicistU314 hThu 8/1/02Mon 3/24/03100%
154Design prototype MTFBElecEngU160.8 hThu 10/17/02Fri 1/31/03100%
154Design prototype MTFBPhysicistU107.2 hThu 10/17/02Fri 1/31/03100%
154Design prototype MTFBElecTechU268 hThu 10/17/02Fri 1/31/03100%
154Design prototype MTFBMandS6,304.32Thu 10/17/02Fri 1/31/03100%
155Procure prototype MTFB partsElecEngU8 hMon 6/2/03Fri 6/27/03100%
155Procure prototype MTFB partsMandS1,635.68Mon 6/2/03Fri 6/27/03100%
156Fabricate and assemble prototype MTFBElecEngU12 hMon 6/30/03Mon 8/11/03100%
156Fabricate and assemble prototype MTFBMandS4,631.36Mon 6/30/03Mon 8/11/03100%
158Test prototype MTFBElecEngU1,160 hTue 8/12/03Tue 3/16/0480%
158Test prototype MTFBPhysicistU1,160 hTue 8/12/03Tue 3/16/0480%
158Test prototype MTFBElecTechU1,160 hTue 8/12/03Tue 3/16/0480%
158Test prototype MTFBMandS1,985.92Tue 8/12/03Tue 3/16/0478%
160Procure MTFB partsElecEngU6.4 hWed 3/17/04Tue 4/13/040%
160Procure MTFB partsMandSPass8,623.09Wed 3/17/04Tue 4/13/040%
161Fabricate and assemble MTFBElecEngU16 hWed 4/14/04Wed 6/9/040%
161Fabricate and assemble MTFBMandSPass6,546.04Wed 4/14/04Wed 6/9/040%
163Test MTFBElecTechU192 hThu 6/10/04Thu 8/5/040%
163Test MTFBElecEngU32 hThu 6/10/04Thu 8/5/040%
163Test MTFBPhysicistU64 hThu 6/10/04Thu 8/5/040%
163Test MTFBMandSPass2,787.52Thu 6/10/04Thu 8/5/040%
166Procure cables and connectorsElecEngU19.2 hMon 6/30/03Tue 10/21/03100%
166Procure cables and connectorsMandSPass16,639.36Mon 6/30/03Tue 10/21/03100%
167Assemble cablesPhysicistU120 hMon 5/24/04Tue 8/17/040%
167Assemble cablesElecTechU96 hMon 5/24/04Tue 8/17/040%
167Assemble cablesMandSPass601.2Mon 5/24/04Tue 8/17/040%
168Procure VME cratesElecTechU16.8 hMon 6/23/03Tue 9/30/03100%
168Procure VME cratesMandSPass8,973.15Mon 6/23/03Tue 9/30/03100%
169Procure VME processorsElecEngU10.4 hFri 3/14/03Tue 9/16/03100%
169Procure VME processorsMandSPass8,492.38Fri 3/14/03Tue 9/16/03100%
170Procure power suppliesElecEngU5.12 hTue 7/1/03Tue 9/30/03100%
170Procure power suppliesMandSPass13,689.58Tue 7/1/03Tue 9/30/03100%
171Assemble and test power suppliesPhysicistU49.6 hTue 1/20/04Wed 4/14/040%
171Assemble and test power suppliesMandSPass4,304.38Tue 1/20/04Wed 4/14/040%
171Assemble and test power suppliesElecEngU4.97 hTue 1/20/04Wed 4/14/040%
172Procure MSPLIT crates, backplanes, and power suppliesElecTechU32 hThu 1/15/04Thu 5/6/040%
172Procure MSPLIT crates, backplanes, and power suppliesMandSPass809.6Thu 1/15/04Thu 5/6/040%
173Procure MSPLIT card partsElecEngU32 hThu 1/15/04Thu 5/6/040%
173Procure MSPLIT card partsMandSPass7,507.8Thu 1/15/04Thu 5/6/040%
174Fabricate and assemble MSPLIT cardsElecEngU24 hFri 5/7/04Mon 8/2/040%
174Fabricate and assemble MSPLIT cardsElecTechU96 hFri 5/7/04Mon 8/2/040%
174Fabricate and assemble MSPLIT cardsMandSPass12,808.44Fri 5/7/04Mon 8/2/040%
175Test MSPLIT cardsElecTechU64 hTue 8/3/04Tue 9/28/040%
175Test MSPLIT cardsElecEngU16 hTue 8/3/04Tue 9/28/040%
175Test MSPLIT cardsPhysicistU16 hTue 8/3/04Tue 9/28/040%
175Test MSPLIT cardsMandSPass992.96Tue 8/3/04Tue 9/28/040%
177Assemble cablesElecTechF240 hMon 5/24/04Tue 8/17/040%
178Assemble and test power suppliesElecTechF248 hTue 1/20/04Wed 4/14/040%
183Develop firmware for target CTT algorithmElecEngU912 hThu 11/7/02Tue 4/29/03100%
183Develop firmware for target CTT algorithmInKind72,352Thu 11/7/02Tue 4/29/03100%
184Fit CTT firmware in selected FPGA, do timing studiesElecEngU320 hWed 4/30/03Wed 6/25/03100%
184Fit CTT firmware in selected FPGA, do timing studiesInKind12,920Wed 4/30/03Wed 6/25/03100%
187Develop test proceduresElecEngU56 hThu 6/26/03Fri 1/23/0497%
187Develop test proceduresInKind1,550.4Thu 6/26/03Fri 1/23/0498%
188Develop test proceduresPhysicistU560 hThu 6/26/03Fri 1/23/0497%
191LayoutElecEngU448 hThu 6/26/03Mon 9/15/03100%
191LayoutElecTechU44.8 hThu 6/26/03Mon 9/15/03100%
191LayoutInKind22,739Thu 6/26/03Mon 9/15/03100%
192Procure preproduction DFEA partsElecTechU43.2 hFri 8/22/03Tue 9/30/03100%
192Procure preproduction DFEA partsInKind2,067.2Fri 8/22/03Tue 9/30/03100%
193PCB fabricationElecTechU32 hMon 9/22/03Fri 10/17/03100%
193PCB fabricationInKind1,033.6Mon 9/22/03Fri 10/17/03100%
194AssemblyElecTechU17.12 hMon 10/20/03Mon 12/22/03100%
194AssemblyInKind1,162.8Mon 10/20/03Mon 12/22/03100%
195TestElecEngU360 hTue 12/23/03Thu 3/25/043%
195TestInKind23,256Tue 12/23/03Thu 3/25/043%
195TestPhysicistU240 hTue 12/23/03Thu 3/25/043%
197Procure preproduction DFEA FPGAsMandSPass48,000Thu 6/26/03Thu 8/7/03100%
197Procure preproduction DFEA FPGAsPhysicistU4.8 hThu 6/26/03Thu 8/7/03100%
198Procure preproduction DFEA partsMandSPass1,500Fri 8/22/03Tue 9/30/03100%
199PCB fabricationMandSPass5,801Mon 9/22/03Fri 10/17/03100%
200AssemblyMandSPass788Mon 10/20/03Mon 12/22/03100%
203LayoutElecEngU160 hMon 2/2/04Fri 2/27/040%
203LayoutElecTechU40 hMon 2/2/04Fri 2/27/040%
203LayoutInKind12,920Mon 2/2/04Fri 2/27/040%
204PCB fabricationElecTechU16 hMon 3/1/04Fri 3/12/040%
204PCB fabricationInKind1,033.6Mon 3/1/04Fri 3/12/040%
205Procure preproduction partsElecTechU1.2 hMon 2/23/04Fri 3/12/040%
205Procure preproduction partsInKind77.52Mon 2/23/04Fri 3/12/040%
206AssemblyElecTechU16 hMon 3/15/04Fri 3/26/040%
206AssemblyInKind1,033.6Mon 3/15/04Fri 3/26/040%
207TestElecEngU160 hMon 3/29/04Fri 5/21/040%
207TestInKind10,336Mon 3/29/04Fri 5/21/040%
207TestPhysicistU320 hMon 3/29/04Fri 5/21/040%
208Test at FermilabElecEngU24 hMon 4/12/04Fri 5/21/040%
208Test at FermilabInKind1,550.4Mon 4/12/04Fri 5/21/040%
208Test at FermilabPhysicistU240 hMon 4/12/04Fri 5/21/040%
210PCB fabricationMandSPass5,801Mon 3/1/04Fri 3/12/040%
211Procure preproduction partsMandSPass200Mon 2/23/04Fri 3/12/040%
212AssemblyMandSPass788Mon 3/15/04Fri 3/26/040%
213Test at FermilabElecTechF120 hMon 4/12/04Fri 5/21/040%
213Test at FermilabElecEngF240 hMon 4/12/04Fri 5/21/040%
214Test at Fermilab PhysicistU240 hMon 4/12/04Fri 5/21/040%
215Test at Fermilab PhysicistU240 hMon 4/12/04Fri 5/21/040%
219Procure FPGAsInKind356,000Tue 6/29/04Wed 11/17/040%
220Procure FPGAsElecTechU8 hTue 6/1/04Wed 10/20/040%
220Procure FPGAsInKind516.8Tue 6/1/04Wed 10/20/040%
221Design, layoutElecEngU80 hTue 6/1/04Mon 6/28/040%
221Design, layoutElecTechU80 hTue 6/1/04Mon 6/28/040%
221Design, layoutInKind10,336Tue 6/1/04Mon 6/28/040%
222Procure production partsElecTechU24 hTue 6/29/04Tue 8/10/040%
222Procure production partsInKind1,550.4Tue 6/29/04Tue 8/10/040%
223PCB FabricateElecTechU12 hWed 7/21/04Tue 8/31/040%
223PCB FabricateInKind775.2Wed 7/21/04Tue 8/31/040%
224AssemblyElecTechU4.8 hWed 9/1/04Wed 9/29/040%
224AssemblyInKind351.95Wed 9/1/04Wed 9/29/040%
225Bench testElecEngU240 hThu 9/30/04Wed 11/24/040%
225Bench testInKind15,504Thu 9/30/04Wed 11/24/040%
225Bench testPhysicistU160 hThu 9/30/04Wed 11/24/040%
226Test at FermilabElecEngU200 hThu 10/14/04Wed 4/20/050%
226Test at FermilabInKind12,920Thu 10/14/04Wed 4/20/050%
226Test at FermilabPhysicistU1,000 hThu 10/14/04Wed 4/20/050%
228Procure FPGAsMandSPass83,296Tue 6/29/04Wed 11/17/040%
229Production readiness review-BUElecEngU20 hMon 5/24/04Fri 5/28/040%
229Production readiness review-BUPhysicistU40 hMon 5/24/04Fri 5/28/040%
229Production readiness review-BUMandSPass1,292Mon 5/24/04Fri 5/28/040%
230Procure production partsMandSPass17,600Tue 6/29/04Tue 8/10/040%
231PCB FabricateMandSPass30,800Wed 7/21/04Tue 8/31/040%
232AssemblyMandSPass8,800Wed 9/1/04Wed 9/29/040%
233Board reworkPhysicistU1,000 hThu 10/14/04Wed 4/20/050%
233Board reworkMandSPass8,800Thu 10/14/04Wed 4/20/050%
234Production readiness review-FermilabElecEngF20 hMon 5/24/04Fri 5/28/040%
235Test at FermilabPhysicistU1,000 hThu 10/14/04Wed 4/20/050%
236Test at FermilabPhysicistU1,000 hThu 10/14/04Wed 4/20/050%
236Test at FermilabMandS36,750Thu 10/14/04Wed 4/20/050%
236Test at FermilabElecTechU1,000 hThu 10/14/04Wed 4/20/050%
237Test at FermilabPhysicistF500 hThu 10/14/04Wed 4/20/050%
237Test at FermilabElecTechF1,000 hThu 10/14/04Wed 4/20/050%
240hardware specJamieson Olsen33.6 hWed 1/14/04Thu 2/12/040%
241timing spec (for CC/BP/DFEA)Jamieson Olsen22.4 hTue 1/27/04Fri 2/13/040%
243schematic + layoutJamieson Olsen128 hFri 1/2/04Fri 4/23/040%
245production + vendor checkoutInKind14,000Tue 4/27/04Wed 7/21/040%
247FNAL checkoutJamieson Olsen16 hFri 7/23/04Thu 8/5/040%
248crate assembly + bench testJamieson Olsen16 hFri 8/6/04Thu 8/19/040%
248crate assembly + bench testInKind7,000Fri 8/6/04Thu 8/19/040%
249test with CCJamieson Olsen16 hFri 8/20/04Thu 9/2/040%
250test with CC + DFEAJamieson Olsen16 hFri 9/3/04Fri 9/17/040%
251delivered to BostonJamieson Olsen8 hMon 9/20/04Mon 9/20/040%
252DFEA Crate Controller (CC)Jamieson Olsen2,376 hMon 12/1/03Wed 2/16/050%
253interface specsJamieson Olsen160 hMon 12/1/03Tue 1/6/040%
254schematic + layout; order long leadtime partsJamieson Olsen96 hWed 1/14/04Wed 4/7/040%
256assembly (vendor)InKind7,500Thu 5/6/04Thu 7/1/040%
257checkoutJamieson Olsen16 hMon 7/5/04Fri 7/16/040%
258Serial Command Link Receiver procurementJamieson Olsen16 hMon 3/1/04Fri 4/23/040%
258Serial Command Link Receiver procurementInKind625Mon 3/1/04Fri 4/23/040%
259test software/firmwareJamieson Olsen128 hMon 3/1/04Mon 6/21/040%
260finish software/firmwareJamieson Olsen256 hTue 6/22/04Wed 2/16/050%
261bench testJamieson Olsen40 hMon 7/19/04Fri 7/30/040%
263optical Download and Control Link (DCL)Jamieson Olsen1,280 hThu 2/12/04Mon 9/27/040%
264interface specsJamieson Olsen32 hThu 2/12/04Wed 3/10/040%
265hardware specsJamieson Olsen32 hThu 3/11/04Wed 4/7/040%
267hardware procurementJamieson Olsen16 hFri 4/9/04Thu 5/6/040%
267hardware procurementInKind1,000Fri 4/9/04Thu 5/6/040%
268software: Linux driverRon Rechenmacher or eqv.144 hThu 4/8/04Thu 7/1/040%
269software: EPICS driver + integrationGeoff Savage or eqv.144 hThu 5/20/04Fri 8/13/040%
270software: dfe_ware integrationYurii Maravin replacement240 hMon 7/5/04Mon 9/27/040%
271bench test PC - CCJamieson Olsen16 hMon 7/5/04Fri 7/16/040%
277Assess Performance of Run2a BetasPhysicistU80 hMon 12/1/03Wed 2/4/0443%
278Develop & Simulate New Run2b AlgortihmsPhysicistU1,200 hThu 2/5/04Fri 9/3/040%
279Production readiness reviewPhysicistU80 hTue 9/7/04Mon 9/13/040%
281Assess Performance of Run2a BetasPhysicistU640 hMon 12/1/03Wed 2/4/0443%
282Develop & Simulate New Run2b AlgortihmsPhysicistU4,800 hThu 2/5/04Fri 9/3/040%
284Develop & Simulate New Run2b AlgortihmsPhysicistU1,200 hThu 2/5/04Fri 9/3/040%
287Survey processor market, chose candidate SBCsPhysicistU40 hThu 3/18/04Wed 4/14/040%
288Evaluate software impact of new SBCsPhysicistU40 hThu 3/18/04Wed 4/14/040%
289Evaluate firmware impact of new SBCs (function)PhysicistU40 hThu 3/18/04Wed 4/14/040%
290Acquire 2 new processor SBCs for evaluationPhysicistU24 hThu 4/15/04Fri 7/9/040%
290Acquire 2 new processor SBCs for evaluationMandS8,160Thu 4/15/04Fri 7/9/040%
292Evaluate firmware impact of new SBCs (coding)ElecEngU80 hThu 3/18/04Wed 4/14/040%
292Evaluate firmware impact of new SBCs (coding)InKind8,247.2Thu 3/18/04Wed 4/14/040%
293Design disk adapterElecEngU40 hThu 4/15/04Wed 5/12/040%
293Design disk adapterInKind4,123.6Thu 4/15/04Wed 5/12/040%
294Specify/Acquire adapter componentsElecEngU8 hThu 5/13/04Thu 6/10/040%
294Specify/Acquire adapter componentsInKind1,024.72Thu 5/13/04Thu 6/10/040%
295Layout adapter, generate artwork, etcElecEngU80 hFri 6/11/04Thu 6/24/040%
295Layout adapter, generate artwork, etcInKind8,247.2Fri 6/11/04Thu 6/24/040%
296Find manufacturer for disk adaptersElecEngU20 hFri 6/25/04Fri 7/9/040%
296Find manufacturer for disk adaptersInKind2,061.8Fri 6/25/04Fri 7/9/040%
297Produce prototype adaptersElecEngU6 hMon 7/12/04Fri 7/30/040%
297Produce prototype adaptersInKind868.54Mon 7/12/04Fri 7/30/040%
298Test prototype adaptersPhysicistU10 hMon 8/2/04Fri 8/6/040%
302Verify software compatibiity / hardware interface patchesPhysicistU96 hMon 8/9/04Mon 10/4/040%
303Verify processor operability in Beta motherboardsPhysicistU192 hMon 8/9/04Mon 10/4/040%
306Firmware support and tuningElecEngU192 hMon 8/9/04Mon 10/4/040%
306Firmware support and tuningInKind19,793.28Mon 8/9/04Mon 10/4/040%
309Produce Disk AdaptersInKind1,050Tue 10/5/04Mon 10/25/040%
309Produce Disk AdaptersElecTechU12 hTue 10/5/04Mon 10/25/040%
310Finalize Run2b SBC orderPhysicistU24 hTue 11/2/04Mon 11/15/040%
311Acquire Run2b SBCsPhysicistU24 hTue 11/16/04Mon 2/21/050%
311Acquire Run2b SBCsMandS39,840Tue 11/16/04Mon 2/21/050%
312Test production disk adaptersPhysicistU10 hTue 10/26/04Mon 11/1/040%
313Test SBCsPhysicistU10 hTue 2/22/05Mon 2/28/050%
317Production Readiness ReviewElecEngU20 hMon 7/26/04Fri 7/30/040%
317Production Readiness ReviewPhysicistU40 hMon 7/26/04Fri 7/30/040%
317Production Readiness ReviewPhysicistF8 hMon 7/26/04Fri 7/30/040%
317Production Readiness ReviewMandSPass1,292Mon 7/26/04Fri 7/30/040%
321Place ordersElecTechU24 hMon 12/15/03Wed 12/17/03100%
321Place ordersMandSPass480Mon 12/15/03Wed 12/17/03100%
322PartsMandSPass13,591Thu 12/18/03Mon 2/23/0410%
323Fabricate PCBMandSPass7,800Mon 8/2/04Fri 8/27/040%
324AssembleMandSPass14,600Mon 8/30/04Mon 9/27/040%
326TestElecEngU32 hTue 9/28/04Mon 11/22/040%
326TestElecTechU64 hTue 9/28/04Mon 11/22/040%
326TestMandSPass2,400Tue 9/28/04Mon 11/22/040%
329Place ordersElecTechU24 hMon 12/15/03Wed 12/17/03100%
329Place ordersMandSPass480Mon 12/15/03Wed 12/17/03100%
330PartsMandSPass15,786Thu 12/18/03Mon 2/23/0410%
331Fabricate PCBMandSPass4,182Mon 8/2/04Fri 8/27/040%
332AssembleMandSPass1,090Mon 8/30/04Mon 9/27/040%
334TestElecEngU12.8 hTue 9/28/04Mon 11/22/040%
334TestElecTechU25.6 hTue 9/28/04Mon 11/22/040%
334TestMandSPass1,120Tue 9/28/04Mon 11/22/040%
342Place ordersElecTechU12 hMon 12/15/03Tue 12/16/03100%
342Place ordersMandSPass240Mon 12/15/03Tue 12/16/03100%
343PartsMandSPass6,561Tue 12/16/03Fri 2/20/0414%
344Fabricate PCBMandSPass2,190Mon 8/2/04Fri 8/27/040%
345AssembleMandSPass718Mon 8/30/04Mon 9/27/040%
347TestElecTechU79.2 hTue 9/28/04Mon 11/8/040%
347TestMandSPass1,040Tue 9/28/04Mon 11/8/040%
350Place ordersElecTechU12 hMon 12/15/03Tue 12/16/03100%
350Place ordersMandSPass240Mon 12/15/03Tue 12/16/03100%
351PartsMandSPass9,297Tue 12/16/03Fri 2/20/0414%
352Fabricate PCBMandSPass2,010Mon 8/2/04Fri 8/27/040%
353AssembleMandSPass710Mon 8/30/04Mon 9/27/040%
355TestElecTechU84 hTue 9/28/04Mon 11/15/040%
355TestMandSPass920Tue 9/28/04Mon 11/15/040%
358Place ordersElecTechU24 hFri 1/30/04Tue 2/3/040%
358Place ordersMandSPass480Fri 1/30/04Tue 2/3/040%
359PartsMandSPass13,000Wed 2/4/04Tue 3/30/040%
360Fabricate PCBMandSPass3,950Mon 8/2/04Fri 8/27/040%
361AssembleMandSPass1,960Mon 8/30/04Mon 9/27/040%
363TestElecEngU19.2 hTue 9/28/04Mon 11/22/040%
363TestElecTechU64 hTue 9/28/04Mon 11/22/040%
363TestMandSPass2,000Tue 9/28/04Mon 11/22/040%
366PartsMandS25,997Tue 1/20/04Mon 3/15/040%
367Fabricate PCBMandS7,800Mon 8/2/04Fri 8/27/040%
368Assemble and reworkMandS4,600Mon 8/30/04Mon 9/27/040%
370TestElecEngU100 hTue 9/28/04Wed 12/8/040%
370TestMandS4,000Tue 9/28/04Wed 12/8/040%
373Design & prototypingElecEngU320 hTue 1/20/04Mon 3/15/040%
373Design & prototypingMandS5,000Tue 1/20/04Mon 3/15/040%
374ProductionMandS7,500Tue 3/16/04Tue 6/8/040%
375TestElecTechU32 hWed 6/9/04Thu 10/28/040%
375TestMandS600Wed 6/9/04Thu 10/28/040%
378FabricateMandSPass833Wed 9/1/04Wed 9/29/040%
379TestElecTechU8 hThu 9/30/04Wed 10/13/040%
379TestMandSPass160Thu 9/30/04Wed 10/13/040%
383ProcureMandS3,250Tue 1/20/04Mon 5/10/040%
384TestElecTechF24 hTue 5/11/04Tue 6/15/040%
388ProcureMandS1,300Tue 3/30/04Wed 7/21/040%
389TestElecTechF32 hThu 7/22/04Wed 8/18/040%
393Update STC firmwareElecEngU960 hTue 6/1/04Wed 11/17/040%
393Update STC firmwareMandSPass38,400Tue 6/1/04Wed 11/17/040%
395Change TFC codePhysicistU960 hMon 8/2/04Mon 1/31/050%
397Update downloading & monitoring softwarePhysicistU800 hMon 8/2/04Wed 12/22/040%
402Develop prototype L1Cal trigger algorithmPhysicistU761.6 hThu 11/1/01Mon 1/13/03100%
402Develop prototype L1Cal trigger algorithmStudentU1,168 hThu 11/1/01Mon 1/13/03100%
403Optimize algorithm performance with simulationsPhysicistU720 hTue 1/14/03Wed 10/27/0430%
404Integrate algorithm into Dzero Trigger SimulationPhysicistU664 hMon 2/3/03Mon 9/27/0433%
406Develop prototype L1Cal/Track match trigger algorithmPhysicistU1,800 hWed 1/22/03Wed 11/3/0425%
406Develop prototype L1Cal/Track match trigger algorithmStudentU1,800 hWed 1/22/03Wed 11/3/0425%
407Optimize algorithm performance with simulationsPhysicistU80 hThu 11/4/04Wed 1/26/050%
408Integrate algorithm into Dzero Trigger SimulationPhysicistU48 hThu 1/27/05Wed 3/9/050%
410Develop prototype CTT algorithmPhysicistU960 hFri 2/1/02Tue 1/21/03100%
411Develop prototype CTT algorithmPhysicistF1,920 hFri 2/1/02Tue 1/21/03100%
412Develop prototype CTT algorithmPhysicistU960 hFri 2/1/02Tue 1/21/03100%
413Develop prototype CTT algorithmPhysicistU960 hFri 2/1/02Tue 1/21/03100%
414Develop prototype CTT algorithmPhysicistU960 hFri 2/1/02Tue 1/21/03100%
415Optimize algorithm performance with simulationsPhysicistU1,800 hWed 1/22/03Wed 11/3/0470%
416Integrate algorithm into Dzero Trigger SimulationPhysicistU1,500 hTue 4/1/03Tue 9/28/0415%
418Update simulatorPhysicistU800 hMon 12/15/03Wed 5/12/040%
420Project ManagementPhysicistU11,648 hMon 2/3/03Mon 3/7/0541%
421Travel vendor and collaborator visitsMandS3,500Mon 2/3/03Mon 3/7/0541%
422Shipping costsMandS2,000Mon 2/3/03Mon 3/7/0541%