Project Start Date: Mon 10/1/01
Project Finish Date: Thu 5/12/05
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
|---|---|---|---|---|---|---|
| 1 | Run IIb Trigger Upgrade | 873 d? | Thu 11/1/01 | Thu 5/12/05 | 44% | |
| 2 | Level 1 Calorimeter Trigger | 838 d | Wed 1/2/02 | Thu 5/12/05 | 57% | |
| 3 | ADC/Digital Filter (ADF) | 753 d | Wed 1/2/02 | Wed 1/12/05 | 56% | |
| 4 | Saclay Tasks | 697 d | Wed 1/2/02 | Wed 10/13/04 | 73% | |
| 5 | Design prototype ADF | 53 w | Wed 1/2/02 | Fri 1/24/03 | ElecEngU,InKind[189,655.6] | 100% |
| 6 | Layout prototype ADF | 17 w | Mon 1/27/03 | Fri 5/23/03 | ElecTechU,InKind[15,110.4] | 100% |
| 7 | Fabricate/Assemble Prototype ADF | 5.2 w | Tue 5/27/03 | Tue 7/1/03 | ElecTechU[50%],InKind[60,055.2] | 100% |
| 8 | Bench Test Prototype ADF | 13.6 w | Tue 7/15/03 | Fri 10/17/03 | PhysicistU[30%],ElecEngU[20%],ElecTechU[20%],InKind[20,632.24] | 100% |
| 9 | Prototype L1 Calorimeter Trigger ADF Shipped To Fermilab | 0 w | Tue 10/7/03 | Tue 10/7/03 | 100% | |
| 10 | Design analog splitter | 4 w | Fri 3/1/02 | Thu 3/28/02 | ElecEngU,InKind[16,494.4] | 100% |
| 11 | Layout and fabricate analog splitter | 8 w | Mon 7/1/02 | Mon 8/26/02 | ElecTechU[50%],InKind[9,150.2] | 100% |
| 12 | Bench test analog splitter | 9.2 w | Mon 11/4/02 | Fri 1/17/03 | ElecTechU[50%],InKind[1,888.8] | 100% |
| 13 | Design SCL interface | 46.8 w | Mon 7/15/02 | Mon 6/23/03 | ElecEngU[30%],InKind[41,236] | 100% |
| 14 | Layout and fabricate SCL interface | 8.6 w | Tue 6/24/03 | Fri 8/22/03 | ElecTechU[50%],InKind[11,199.2] | 100% |
| 15 | Bench test SCL interface | 7.8 w | Mon 8/25/03 | Fri 10/17/03 | ElecTechU[50%],InKind[3,777.6] | 100% |
| 16 | ADF Prototype in-situ tests | 9.4 w | Wed 10/15/03 | Mon 12/22/03 | PhysicistU,ElecEngU[20%],InKind[13,193.43] | 100% |
| 17 | Final ADF design - Production readiness review | 10 w | Tue 12/9/03 | Thu 2/26/04 | ElecEngU,InKind[41,236] | 0% |
| 18 | Bench test 10% ADF | 8 w | Wed 8/18/04 | Wed 10/13/04 | ElecTechU,ElecEngU[10%],PhysicistU[30%],InKind[18,409.28] | 0% |
| 19 | Digital filter FPGA programming | 80 w | Mon 1/27/03 | Fri 8/27/04 | PhysicistU[30%],ElecEngU[10%],InKind[32,988.8] | 50% |
| 20 | ADF offline software and analysis | 23 w | Mon 10/20/03 | Fri 4/9/04 | PhysicistU[50%] | 0% |
| 21 | MSU Tasks | 301 d | Mon 10/20/03 | Wed 1/12/05 | 5% | |
| 22 | Develop in-situ exercizing/debugging software | 20 w | Mon 10/20/03 | Fri 3/19/04 | ElecEngU[50%],PhysicistU[50%],InKind[41,234.93] | 25% |
| 23 | ADF Prototype v.2 | 140 d | Mon 1/5/04 | Wed 7/21/04 | 0% | |
| 24 | Layout ADF v.2 prototype | 12 w | Mon 1/5/04 | Mon 3/29/04 | 0% | |
| 25 | Fabricate ADF v.2 prototype | 3 w | Tue 3/30/04 | Mon 4/19/04 | 0% | |
| 26 | Assemble ADF v.2 prototype | 3 w | Tue 4/20/04 | Mon 5/10/04 | 0% | |
| 27 | Three ADF Cards Received By MSU | 0 w | Mon 5/10/04 | Mon 5/10/04 | 0% | |
| 28 | Two ADF Cards Received By Saclay | 0 w | Mon 5/10/04 | Mon 5/10/04 | 0% | |
| 29 | Perform bench tests at MSU | 5 w | Tue 5/11/04 | Tue 6/15/04 | 0% | |
| 30 | Perform tests at Fermilab | 4 w | Wed 6/16/04 | Wed 7/14/04 | 0% | |
| 31 | Production Design Approved | 0 w | Wed 7/14/04 | Wed 7/14/04 | 0% | |
| 32 | Production readiness review | 1 w | Thu 7/15/04 | Wed 7/21/04 | 0% | |
| 33 | Release ADF For Production | 0 w | Wed 7/21/04 | Wed 7/21/04 | 0% | |
| 34 | ADF Production | 195 d | Tue 3/30/04 | Wed 1/12/05 | 0% | |
| 35 | Procure ADF components | 16 w | Tue 3/30/04 | Wed 7/21/04 | ElecEngU[4%],MandSPass[118,646.8] | 0% |
| 36 | Fabricate production ADF | 18 w | Thu 8/12/04 | Mon 12/20/04 | ElecTechU[10%],MandSPass[51,746.88] | 0% |
| 37 | Bench test production ADF | 18 w | Thu 8/26/04 | Wed 1/12/05 | ElecTechU,ElecEngU[10%],PhysicistU[30%],MandSPass[59,830.16] | 0% |
| 38 | L1 Calorimeter Trigger ADF Production Complete And Tested | 0 w | Wed 1/12/05 | Wed 1/12/05 | 0% | |
| 39 | ADF Crates | 233 d | Thu 5/1/03 | Thu 4/8/04 | 48% | |
| 40 | Prototypes | 203 d | Thu 5/1/03 | Thu 2/26/04 | 55% | |
| 41 | Design transition backplane | 3.4 w | Thu 5/1/03 | Fri 5/23/03 | ElecEngU,InKind[24,741.6] | 100% |
| 42 | Layout and fabricate transition backplane | 8 w | Tue 5/27/03 | Tue 7/22/03 | ElecTechU[50%],InKind[7,555.2] | 100% |
| 43 | Fabricate/Assemble prototype crate | 9.2 w | Wed 7/23/03 | Thu 9/25/03 | ElecTechU[50%],InKind[7,555.2] | 100% |
| 44 | Test prototype ADF in prototype crate | 16 w | Fri 9/26/03 | Thu 1/29/04 | PhysicistU[30%],ElecEngU[20%],ElecTechU[20%],InKind[9,619.84] | 10% |
| 45 | L1 Calorimeter Trigger ADF+Crate Prototype Complete | 0 w | Thu 1/29/04 | Thu 1/29/04 | 0% | |
| 46 | Final backplane design | 4 w | Fri 1/30/04 | Thu 2/26/04 | ElecEngU,InKind[16,494.4] | 0% |
| 47 | Production | 30 d | Fri 2/27/04 | Thu 4/8/04 | 0% | |
| 48 | Procure crate components | 5 w | Fri 2/27/04 | Thu 4/1/04 | MandSPass[51,144.44],ElecTechU[10%] | 0% |
| 49 | Assemble ADF crates | 1 w | Fri 4/2/04 | Thu 4/8/04 | ElecTechU,MandSPass[5,388.8] | 0% |
| 50 | Trigger Algorithm Board | 746 d | Fri 2/1/02 | Thu 2/3/05 | 76% | |
| 51 | Prototypes | 515 d | Fri 2/1/02 | Fri 2/27/04 | 96% | |
| 52 | Choose L1 Calorimeter Trigger Baseline Jet Algorithm | 0 w | Thu 8/8/02 | Thu 8/8/02 | 100% | |
| 53 | Design prototype Trigger Algorithm Board (TAB) | 49 w | Fri 2/1/02 | Tue 1/28/03 | ElecEngU[75%],InKind[94,972.2] | 100% |
| 54 | Layout prototype TAB | 36.6 w | Fri 8/9/02 | Wed 5/7/03 | ElecEngU[15%],InKind[14,897.6] | 100% |
| 55 | Procure prototype TAB parts | 33.6 w | Fri 8/23/02 | Wed 4/30/03 | ElecTechU[5%],InKind[17,931.2] | 100% |
| 56 | Fabricate/Assemble Prototype TAB | 6.6 w | Thu 5/8/03 | Tue 6/24/03 | ElecTechU[10%],InKind[11,706.56] | 100% |
| 57 | Develop TAB/GAB test software | 60 w | Mon 11/4/02 | Wed 1/28/04 | PostdocU[10%],StudentU[10%] | 94% |
| 58 | Test prototype TAB | 9.4 w | Wed 6/25/03 | Fri 8/29/03 | PhysicistU[20%],ElecEngU[20%],ElecTechU[5%],StudentU[50%],InKind[15,327.72] | 100% |
| 59 | L1 Calorimeter Trigger TAB Prototype Complete | 0 w | Fri 8/29/03 | Fri 8/29/03 | 100% | |
| 60 | Pre-production TAB design | 4 w | Mon 2/2/04 | Fri 2/27/04 | ElecEngU[20%],InKind[2,979.62] | 0% |
| 61 | Production | 171 d | Mon 3/1/04 | Thu 10/28/04 | 0% | |
| 62 | Procure TAB parts | 10 w | Mon 3/1/04 | Fri 5/7/04 | ElecTechU[10%],MandSPass[60,373.2] | 0% |
| 63 | Layout pre-production TAB | 6 w | Mon 3/1/04 | Fri 4/9/04 | ElecEngU[50%],MandSPass[11,173.2] | 0% |
| 64 | Fabricate/Assemple pre-production TAB | 8 w | Mon 4/12/04 | Mon 6/7/04 | ElecTechU[10%],MandSPass[11,706.56] | 0% |
| 65 | Final design and layout changes to TAB | 2 w | Thu 8/19/04 | Wed 9/1/04 | ElecEngU[50%],MandSPass[3,724.4] | 0% |
| 66 | Start Production TAB Fabrication | 0 w | Thu 9/2/04 | Thu 9/2/04 | 0% | |
| 67 | Fabricate production TAB | 8 w | Thu 9/2/04 | Thu 10/28/04 | ElecTechU[10%],MandSPass[16,706.56] | 0% |
| 68 | Bench Testing | 161 d | Tue 6/8/04 | Thu 2/3/05 | 0% | |
| 69 | Bench test pre-production TAB | 6 w | Tue 6/8/04 | Tue 7/20/04 | PhysicistU[30%],StudentU[75%],ElecEngU[30%],ElecTechU[10%],InKind[7,983.84] | 0% |
| 70 | Bench test production TAB | 12 w | Fri 10/29/04 | Thu 2/3/05 | StudentU[20%],ElecEngU[5%],ElecTechU[5%],InKind[3,514.56] | 0% |
| 71 | Global Algorithm Board (GAB) | 692 d | Mon 7/29/02 | Thu 5/12/05 | 68% | |
| 72 | Prototype | 394 d | Mon 7/29/02 | Wed 3/3/04 | 92% | |
| 73 | Design prototype GAB | 45.8 w | Mon 7/29/02 | Mon 6/30/03 | ElecEngU[36%],InKind[49,609.01] | 100% |
| 74 | Layout prototype GAB | 18.4 w | Mon 7/21/03 | Wed 11/26/03 | ElecEngU[50%],InKind[7,443.29] | 100% |
| 75 | Procure prototype GAB parts | 37 w | Fri 8/23/02 | Fri 5/23/03 | ElecTechU[4%],InKind[10,486.66] | 100% |
| 76 | Fabricate/Assemble Prototype GAB | 4 w | Mon 12/1/03 | Tue 1/6/04 | ElecTechU[10%],InKind[5,353.28] | 33% |
| 77 | Test Prototype GAB | 8 w | Wed 1/7/04 | Wed 3/3/04 | PhysicistU[10%],ElecEngU[10%],ElecTechU[5%],StudentU[25%],InKind[3,832.85] | 0% |
| 78 | L1 Calorimeter Trigger GAB Prototype Complete | 0 w | Wed 3/3/04 | Wed 3/3/04 | 0% | |
| 79 | Design/layout prototype VME/SCL interface | 7 w | Mon 2/24/03 | Fri 4/11/03 | InKind[19,553.1],ElecEngU[75%] | 100% |
| 80 | Fabricate/assemble prototype VME/SCL interface | 4.2 w | Mon 4/14/03 | Mon 5/12/03 | InKind[5,140],ElecTechU[10%] | 100% |
| 81 | Test prototype VME/SCL interface | 9.4 w | Thu 5/22/03 | Tue 7/29/03 | InKind[3,832.85],ElecEngU[10%],ElecTechU[5%],StudentU[25%],PhysicistU[10%] | 100% |
| 82 | Production | 321 d | Mon 2/2/04 | Thu 5/12/05 | 0% | |
| 83 | Final GAB design - Production readiness review | 4 w | Mon 2/2/04 | Fri 2/27/04 | ElecEngU[20%],MandSPass[2,979.52] | 0% |
| 84 | Procure GAB parts | 10 w | Mon 3/1/04 | Fri 5/7/04 | ElecTechU[10%],MandSPass[7,133.2] | 0% |
| 85 | Layout final GAB | 6 w | Mon 3/1/04 | Fri 4/9/04 | ElecEngU[12%],MandSPass[2,681.57] | 0% |
| 86 | Fabricate production GAB | 8 w | Fri 2/4/05 | Thu 3/31/05 | ElecTechU[5%],MandSPass[3,853.33] | 0% |
| 87 | Bench test production GAB | 6 w | Fri 4/1/05 | Thu 5/12/05 | PhysicistU[30%],StudentU[75%],ElecEngU[18%],ElecTechU[6%],MandSPass[4,790.35] | 0% |
| 88 | Final design/layout changes to production VME/SCL interface | 4 w | Thu 3/4/04 | Wed 3/31/04 | MandSPass[2,979.52],ElecEngU[20%] | 0% |
| 89 | Fabricate/assemble production VME/SCL interface | 4 w | Thu 4/1/04 | Wed 4/28/04 | MandSPass[3,426.67],ElecTechU[5%] | 0% |
| 90 | Bench test production VME/SCL interface | 4 w | Thu 4/29/04 | Wed 5/26/04 | MandSPass[3,193.57],ElecEngU[18%],ElecTechU[6%],StudentU[25%],PhysicistU[10%] | 0% |
| 91 | Cables | 603 d | Mon 9/9/02 | Thu 2/17/05 | 44% | |
| 92 | Design and Fabricate system to test ADF to TAB cables | 6 w | Mon 9/9/02 | Fri 10/18/02 | ElecTechU[10%],InKind[10,983.92],ElecEngU[30%] | 100% |
| 93 | Test ADF to TAB cables | 2 w | Mon 10/21/02 | Fri 11/1/02 | ElecEngU[20%],StudentU[50%],InKind[1,489.76] | 100% |
| 94 | Procure ADF to TAB cables | 10 w | Tue 11/30/04 | Thu 2/17/05 | ElecTechU[10%],MandSPass[19,914.1] | 0% |
| 95 | TAB Crates and Services | 598 d | Mon 10/28/02 | Thu 3/31/05 | 45% | |
| 96 | Prototype | 101 d | Mon 10/28/02 | Mon 3/31/03 | 100% | |
| 97 | Procure TAB crate for prototype TAB/GAB | 11.2 w | Mon 10/28/02 | Mon 1/27/03 | ElecTechU[10%],InKind[11,513.12] | 100% |
| 98 | Procure VME CPU for prototype TAB/GAB | 10.2 w | Fri 1/17/03 | Mon 3/31/03 | ElecTechU[10%],InKind[4,956.56] | 100% |
| 99 | Production | 235 d | Tue 4/20/04 | Thu 3/31/05 | 0% | |
| 100 | Specify TAB crate/power/cooling | 2 w | Tue 4/20/04 | Mon 5/3/04 | ElecEngU[20%],MandSPass[1,489.76] | 0% |
| 101 | Procure TAB crate | 16 w | Tue 11/30/04 | Thu 3/31/05 | ElecTechU[10%],MandSPass[12,513.12] | 0% |
| 102 | Procure TAB VME CPU | 8 w | Tue 11/30/04 | Thu 2/3/05 | ElecTechU[10%],MandSPass[4,956.56] | 0% |
| 103 | L1 Calorimeter Trigger TAB/GAB Prototyping Complete | 0 w | Wed 3/3/04 | Wed 3/3/04 | 0% | |
| 104 | L1 Calorimeter Trigger TAB/GAB Production and Testing Complete | 0 w | Thu 5/12/05 | Thu 5/12/05 | 0% | |
| 105 | Prototype Integration | 142 d | Tue 7/1/03 | Fri 1/30/04 | 59% | |
| 106 | Develop in-situ exercizing/debugging software | 28 w | Tue 7/1/03 | Wed 1/28/04 | ElecEngU[50%],PhysicistU[50%],InKind[16,494.4] | 87% |
| 107 | Prototype integration test ADF+TAB:Columbia | 11.4 w | Wed 7/30/03 | Fri 10/17/03 | PhysicistU[10%],ElecEngU[20%],StudentU[50%],InKind[2,979.52] | 100% |
| 108 | Prototype integration test ADF+TAB:Saclay | 11.4 w | Wed 7/30/03 | Fri 10/17/03 | PhysicistU[10%],ElecEngU[20%],StudentU[50%],InKind[3,298.88] | 100% |
| 109 | Prototype integration test ADF+TAB+GAB+TFW: MSU | 13 w | Mon 10/20/03 | Fri 1/30/04 | PhysicistU[30%],ElecEngU[20%],InKind[6,597.58] | 25% |
| 110 | Prototype integration test ADF+TAB+GAB+TFW: Columbia | 13 w | Mon 10/20/03 | Fri 1/30/04 | PhysicistU[10%],ElecEngU[20%],StudentU[50%],InKind[5,959.04] | 25% |
| 111 | Prototype integration test ADF+TAB+GAB+TFW: Saclay | 13 w | Mon 10/20/03 | Fri 1/30/04 | PhysicistU[10%],ElecEngU[20%],StudentU[50%],InKind[6,597.76] | 25% |
| 112 | Prototype integration test ADF+TAB+GAB+TFW: Fermilab | 13 w | Mon 10/20/03 | Fri 1/30/04 | ElecTechF[20%] | 25% |
| 113 | Pre-Production Integration | 25 d | Thu 7/15/04 | Wed 8/18/04 | 0% | |
| 114 | Pre-production integration test ADF+TAB+TFW: MSU | 4 w | Thu 7/15/04 | Wed 8/11/04 | ElecEngU[20%],PhysicistU[30%],MandSPass[3,298.79] | 0% |
| 115 | Pre-production integration test ADF+TAB+TFW: Columbia | 4 w | Thu 7/15/04 | Wed 8/11/04 | ElecEngU[20%],PhysicistU[30%],MandSPass[2,979.52] | 0% |
| 116 | Pre-production integration test ADF+TAB+TFW: Saclay | 4 w | Thu 7/15/04 | Wed 8/11/04 | ElecEngU[20%],PhysicistU[30%],InKind[3,298.36] | 0% |
| 117 | Pre-production integration test ADF+TAB+TFW: Fermilab | 4 w | Thu 7/15/04 | Wed 8/11/04 | ElecTechF[60%] | 0% |
| 118 | Production readiness review | 1 w | Thu 8/12/04 | Wed 8/18/04 | ElecEngU,PhysicistU,MandSPass[4,000] | 0% |
| 119 | Production readiness review | 1 w | Thu 8/12/04 | Wed 8/18/04 | ElecEngF[20%] | 0% |
| 120 | L1 Cal Online Software | 475 d | Tue 4/15/03 | Tue 3/15/05 | 33% | |
| 121 | ADF online software | 95 w | Tue 4/15/03 | Tue 3/15/05 | PostdocU[25%],PhysicistU[10%] | 37% |
| 122 | TAB/GAB online software | 87 w | Wed 6/11/03 | Tue 3/15/05 | PostdocU[25%],PhysicistU[10%] | 28% |
| 123 | L1 Calorimeter Trigger Production And Testing Complete | 0 w | Thu 5/12/05 | Thu 5/12/05 | 0% | |
| 124 | Level 1 Calorimeter Track Matching | 590 d | Thu 8/1/02 | Tue 12/14/04 | 54% | |
| 125 | D0 Reviews | 37 d | Thu 6/12/03 | Tue 8/5/03 | 100% | |
| 126 | D0 Internal Design Review Complete | 0 w | Thu 6/12/03 | Thu 6/12/03 | 100% | |
| 127 | D0 Production Readiness Review | 1 w | Wed 7/30/03 | Tue 8/5/03 | ElecEngU[50%],PhysicistU[50%],MandSPass[2,000] | 100% |
| 128 | D0 Production Readiness Review | 1 w | Wed 7/30/03 | Tue 8/5/03 | ElecEngF[20%] | 100% |
| 129 | L1 Trigger Cal-Trk Match R&D MOU (UAZ) Complete | 0 w | Fri 3/14/03 | Fri 3/14/03 | 100% | |
| 130 | L1 Trigger Cal-Trk Match Equipment MOU (UAZ) Complete | 0 w | Fri 3/14/03 | Fri 3/14/03 | 100% | |
| 131 | SLDB | 270 d | Fri 3/14/03 | Tue 4/13/04 | 73% | |
| 132 | Procure SLDB parts | 19 w | Fri 3/14/03 | Mon 7/28/03 | ElecEngU[5%],MandSPass[29,153.22] | 100% |
| 133 | Fabricate and assemble SLDBs | 33 w | Mon 6/16/03 | Tue 2/17/04 | ElecEngU[3%],MandSPass[11,419.14] | 75% |
| 134 | Test SLDBs | 8 w | Wed 2/18/04 | Tue 4/13/04 | ElecTechU[60%],ElecEngU[20%],PhysicistU[20%],MandSPass[3,170.24] | 0% |
| 135 | MTCxx | 440 d | Fri 3/14/03 | Tue 12/14/04 | 54% | |
| 136 | (Small) design changes to MTCxx | 41 w | Fri 3/14/03 | Mon 1/12/04 | ElecEngU[257%],MandSPass[2,296.32] | 98% |
| 137 | Procure MTCxx parts | 16 w | Mon 6/9/03 | Tue 9/30/03 | ElecEngU[10%],MandSPass[23,325.38] | 100% |
| 138 | Fabricate and assemble preproduction MTCxx | 6 w | Tue 1/13/04 | Tue 2/24/04 | ElecEngU[5%],MandSPass[4,005.04] | 0% |
| 139 | Fabrication and Assembly of L1 Trigger Cal-Trk Match Preproduction MTCxx Complete | 0 w | Tue 2/24/04 | Tue 2/24/04 | 0% | |
| 140 | Test preproduction MTCxx | 8 w | Wed 2/25/04 | Tue 4/20/04 | ElecTechU[80%],ElecEngU[30%],PhysicistU[20%],MandS[4,354.56] | 0% |
| 141 | Final design changes to MTCxx | 6 w | Wed 4/21/04 | Wed 6/2/04 | ElecEngU[40%],MandSPass[1,148.16] | 0% |
| 142 | Fabricate and assemble MTCxx's | 16 w | Thu 6/3/04 | Fri 9/24/04 | ElecEngU[5%],MandSPass[8,500.72] | 0% |
| 143 | Fabrication and Assembly of L1 Trigger Cal-Trk Match MTCxx's Complete | 0 w | Fri 9/24/04 | Fri 9/24/04 | 0% | |
| 144 | Test MTCxx's | 11 w | Mon 9/27/04 | Tue 12/14/04 | ElecEngU[20%],ElecTechU[80%],PhysicistF[20%],MandSPass[6,950.72] | 0% |
| 145 | MTCM | 205 d | Mon 10/20/03 | Tue 8/17/04 | 24% | |
| 146 | (Small) design changes to MTCM | 11 w | Mon 10/20/03 | Thu 1/15/04 | ElecEngU[30%],MandSPass[1,148.16] | 90% |
| 147 | Procure MTCM parts | 12 w | Fri 1/16/04 | Fri 4/9/04 | ElecEngU[10%],MandSPass[8,626.08] | 0% |
| 148 | Fabricate and assemble MTCMs | 6 w | Mon 4/12/04 | Fri 5/21/04 | ElecEngU[5%],MandSPass[4,511.04] | 0% |
| 149 | Fabrication and Assembly of L1 Trigger Cal-Trk Match MTCM's Complete | 0 w | Fri 5/21/04 | Fri 5/21/04 | 0% | |
| 150 | Test MTCMs | 12 w | Mon 5/24/04 | Tue 8/17/04 | ElecEngU[30%],MandSPass[1,722.24] | 0% |
| 151 | MT Flavor Board | 500 d | Thu 8/1/02 | Thu 8/5/04 | 75% | |
| 152 | Design prototype cal-trk algorithm | 31.4 w | Thu 8/1/02 | Mon 3/24/03 | PhysicistU[25%] | 100% |
| 153 | Prototype | 346 d | Thu 10/17/02 | Tue 3/16/04 | 89% | |
| 154 | Design prototype MTFB | 13.4 w | Thu 10/17/02 | Fri 1/31/03 | ElecEngU[30%],PhysicistU[20%],ElecTechU[50%],MandS[6,304.32] | 100% |
| 155 | Procure prototype MTFB parts | 4 w | Mon 6/2/03 | Fri 6/27/03 | ElecEngU[5%],MandS[1,635.68] | 100% |
| 156 | Fabricate and assemble prototype MTFB | 6 w | Mon 6/30/03 | Mon 8/11/03 | ElecEngU[5%],MandS[4,631.36] | 100% |
| 157 | Fabrication and Assembly of L1 Trigger Cal-Trk Match Prototype MTFB Complete | 0 w | Mon 8/11/03 | Mon 8/11/03 | 100% | |
| 158 | Test prototype MTFB | 29 w | Tue 8/12/03 | Tue 3/16/04 | ElecEngU,PhysicistU,ElecTechU,MandS[1,985.92] | 80% |
| 159 | Production | 100 d | Wed 3/17/04 | Thu 8/5/04 | 0% | |
| 160 | Procure MTFB parts | 4 w | Wed 3/17/04 | Tue 4/13/04 | ElecEngU[4%],MandSPass[8,623.09] | 0% |
| 161 | Fabricate and assemble MTFB | 8 w | Wed 4/14/04 | Wed 6/9/04 | ElecEngU[5%],MandSPass[6,546.04] | 0% |
| 162 | Fabrication and Assembly of L1 Trigger Cal-Trk Match MTFB's Complete | 0 w | Wed 6/9/04 | Wed 6/9/04 | 0% | |
| 163 | Test MTFB | 8 w | Thu 6/10/04 | Thu 8/5/04 | ElecTechU[60%],ElecEngU[10%],PhysicistU[20%],MandSPass[2,787.52] | 0% |
| 164 | Infrastructure | 387 d | Fri 3/14/03 | Tue 9/28/04 | 41% | |
| 165 | University of Arizona Tasks | 387 d | Fri 3/14/03 | Tue 9/28/04 | 47% | |
| 166 | Procure cables and connectors | 16 w | Mon 6/30/03 | Tue 10/21/03 | ElecEngU[3%],MandSPass[16,639.36] | 100% |
| 167 | Assemble cables | 12 w | Mon 5/24/04 | Tue 8/17/04 | PhysicistU[25%],ElecTechU[20%],MandSPass[601.2] | 0% |
| 168 | Procure VME crates | 14 w | Mon 6/23/03 | Tue 9/30/03 | ElecTechU[3%],MandSPass[8,973.15] | 100% |
| 169 | Procure VME processors | 26 w | Fri 3/14/03 | Tue 9/16/03 | ElecEngU[1%],MandSPass[8,492.38] | 100% |
| 170 | Procure power supplies | 12.8 w | Tue 7/1/03 | Tue 9/30/03 | ElecEngU[1%],MandSPass[13,689.58] | 100% |
| 171 | Assemble and test power supplies | 12.4 w | Tue 1/20/04 | Wed 4/14/04 | PhysicistU[10%],MandSPass[4,304.38],ElecEngU[1%] | 0% |
| 172 | Procure MSPLIT crates, backplanes, and power supplies | 16 w | Thu 1/15/04 | Thu 5/6/04 | ElecTechU[5%],MandSPass[809.6] | 0% |
| 173 | Procure MSPLIT card parts | 16 w | Thu 1/15/04 | Thu 5/6/04 | ElecEngU[5%],MandSPass[7,507.8] | 0% |
| 174 | Fabricate and assemble MSPLIT cards | 12 w | Fri 5/7/04 | Mon 8/2/04 | ElecEngU[5%],ElecTechU[20%],MandSPass[12,808.44] | 0% |
| 175 | Test MSPLIT cards | 8 w | Tue 8/3/04 | Tue 9/28/04 | ElecTechU[20%],ElecEngU[5%],PhysicistU[5%],MandSPass[992.96] | 0% |
| 176 | Fermilab Tasks | 149 d | Tue 1/20/04 | Tue 8/17/04 | 0% | |
| 177 | Assemble cables | 12 w | Mon 5/24/04 | Tue 8/17/04 | ElecTechF[50%] | 0% |
| 178 | Assemble and test power supplies | 12.4 w | Tue 1/20/04 | Wed 4/14/04 | ElecTechF[50%] | 0% |
| 179 | L1 Trigger Cal-Trk Match Production and Testing Completed | 0 w | Tue 12/14/04 | Tue 12/14/04 | 0% | |
| 180 | Level 1 Tracking | 604 d? | Thu 11/7/02 | Wed 4/20/05 | 22% | |
| 181 | Prototype L1 Central Track Trigger Algorithm Coded And Simulated With FPGA Simulation Tools | 0 w | Thu 11/7/02 | Thu 11/7/02 | 100% | |
| 182 | Develop Target CTT Algorithm | 154 d | Thu 11/7/02 | Wed 6/25/03 | 100% | |
| 183 | Develop firmware for target CTT algorithm | 22.8 w | Thu 11/7/02 | Tue 4/29/03 | ElecEngU,InKind[72,352] | 100% |
| 184 | Fit CTT firmware in selected FPGA, do timing studies | 8 w | Wed 4/30/03 | Wed 6/25/03 | ElecEngU,InKind[12,920] | 100% |
| 185 | Target L1 Central Track Trigger Algorithm Firmware Coded And Simulated With FPGA Simulation Tools | 0 w | Wed 6/25/03 | Wed 6/25/03 | 100% | |
| 186 | Develop Test Procedures | 140 d | Thu 6/26/03 | Fri 1/23/04 | 90% | |
| 187 | Develop test procedures | 28 w | Thu 6/26/03 | Fri 1/23/04 | ElecEngU[10%],InKind[1,550.4] | 90% |
| 188 | Develop test procedures | 28 w | Thu 6/26/03 | Fri 1/23/04 | PhysicistU | 90% |
| 189 | DFEA Preproduction I | 184 d | Thu 6/26/03 | Thu 3/25/04 | 82% | |
| 190 | MRI Tasks - BU | 184 d | Thu 6/26/03 | Thu 3/25/04 | 72% | |
| 191 | Layout | 11.2 w | Thu 6/26/03 | Mon 9/15/03 | ElecEngU,ElecTechU[10%],InKind[22,739] | 100% |
| 192 | Procure preproduction DFEA parts | 5.4 w | Fri 8/22/03 | Tue 9/30/03 | ElecTechU[20%],InKind[2,067.2] | 100% |
| 193 | PCB fabrication | 4 w | Mon 9/22/03 | Fri 10/17/03 | ElecTechU[20%],InKind[1,033.6] | 100% |
| 194 | Assembly | 8.8 w | Mon 10/20/03 | Mon 12/22/03 | ElecTechU[15%],InKind[1,162.8] | 100% |
| 195 | Test | 12 w | Tue 12/23/03 | Thu 3/25/04 | ElecEngU[75%],InKind[23,256],PhysicistU[50%] | 3% |
| 196 | DOE EQ Tasks - BU | 124 d | Thu 6/26/03 | Mon 12/22/03 | 100% | |
| 197 | Procure preproduction DFEA FPGAs | 6 w | Thu 6/26/03 | Thu 8/7/03 | MandSPass[48,000],PhysicistU[2%] | 100% |
| 198 | Procure preproduction DFEA parts | 5.4 w | Fri 8/22/03 | Tue 9/30/03 | MandSPass[1,500] | 100% |
| 199 | PCB fabrication | 4 w | Mon 9/22/03 | Fri 10/17/03 | MandSPass[5,801] | 100% |
| 200 | Assembly | 8.8 w | Mon 10/20/03 | Mon 12/22/03 | MandSPass[788] | 100% |
| 201 | DFEA Preproduction II | 80 d | Mon 2/2/04 | Fri 5/21/04 | 0% | |
| 202 | MRI Tasks - BU | 80 d | Mon 2/2/04 | Fri 5/21/04 | 0% | |
| 203 | Layout | 4 w | Mon 2/2/04 | Fri 2/27/04 | ElecEngU,ElecTechU[25%],InKind[12,920] | 0% |
| 204 | PCB fabrication | 2 w | Mon 3/1/04 | Fri 3/12/04 | ElecTechU[20%],InKind[1,033.6] | 0% |
| 205 | Procure preproduction parts | 3 w | Mon 2/23/04 | Fri 3/12/04 | ElecTechU[1%],InKind[77.52] | 0% |
| 206 | Assembly | 2 w | Mon 3/15/04 | Fri 3/26/04 | ElecTechU[20%],InKind[1,033.6] | 0% |
| 207 | Test | 8 w | Mon 3/29/04 | Fri 5/21/04 | ElecEngU[50%],InKind[10,336],PhysicistU | 0% |
| 208 | Test at Fermilab | 6 w | Mon 4/12/04 | Fri 5/21/04 | ElecEngU[10%],InKind[1,550.4],PhysicistU | 0% |
| 209 | DOE EQ Tasks-BU | 25 d | Mon 2/23/04 | Fri 3/26/04 | 0% | |
| 210 | PCB fabrication | 2 w | Mon 3/1/04 | Fri 3/12/04 | MandSPass[5,801] | 0% |
| 211 | Procure preproduction parts | 3 w | Mon 2/23/04 | Fri 3/12/04 | MandSPass[200] | 0% |
| 212 | Assembly | 2 w | Mon 3/15/04 | Fri 3/26/04 | MandSPass[788] | 0% |
| 213 | Test at Fermilab | 6 w | Mon 4/12/04 | Fri 5/21/04 | ElecTechF[50%],ElecEngF | 0% |
| 214 | Test at Fermilab | 6 w | Mon 4/12/04 | Fri 5/21/04 | PhysicistU | 0% |
| 215 | Test at Fermilab | 6 w | Mon 4/12/04 | Fri 5/21/04 | PhysicistU | 0% |
| 216 | L1 Central Track Trigger DFEA Prototype Tested At Fermilab | 0 w | Fri 5/21/04 | Fri 5/21/04 | 0% | |
| 217 | DFEA Production | 225 d | Mon 5/24/04 | Wed 4/20/05 | 0% | |
| 218 | MRI Tasks - BU | 220 d | Tue 6/1/04 | Wed 4/20/05 | 0% | |
| 219 | Procure FPGAs | 20 w | Tue 6/29/04 | Wed 11/17/04 | InKind[356,000] | 0% |
| 220 | Procure FPGAs | 20 w | Tue 6/1/04 | Wed 10/20/04 | ElecTechU[1%],InKind[516.8] | 0% |
| 221 | Design, layout | 4 w | Tue 6/1/04 | Mon 6/28/04 | ElecEngU[50%],ElecTechU[50%],InKind[10,336] | 0% |
| 222 | Procure production parts | 6 w | Tue 6/29/04 | Tue 8/10/04 | ElecTechU[10%],InKind[1,550.4] | 0% |
| 223 | PCB Fabricate | 6 w | Wed 7/21/04 | Tue 8/31/04 | ElecTechU[5%],InKind[775.2] | 0% |
| 224 | Assembly | 4 w | Wed 9/1/04 | Wed 9/29/04 | ElecTechU[3%],InKind[351.95] | 0% |
| 225 | Bench test | 8 w | Thu 9/30/04 | Wed 11/24/04 | ElecEngU[75%],InKind[15,504],PhysicistU[50%] | 0% |
| 226 | Test at Fermilab | 25 w | Thu 10/14/04 | Wed 4/20/05 | ElecEngU[20%],InKind[12,920],PhysicistU | 0% |
| 227 | DOE EQ Tasks-BU | 225 d | Mon 5/24/04 | Wed 4/20/05 | 0% | |
| 228 | Procure FPGAs | 20 w | Tue 6/29/04 | Wed 11/17/04 | MandSPass[83,296] | 0% |
| 229 | Production readiness review-BU | 1 w | Mon 5/24/04 | Fri 5/28/04 | ElecEngU[50%],PhysicistU,MandSPass[1,292] | 0% |
| 230 | Procure production parts | 6 w | Tue 6/29/04 | Tue 8/10/04 | MandSPass[17,600] | 0% |
| 231 | PCB Fabricate | 6 w | Wed 7/21/04 | Tue 8/31/04 | MandSPass[30,800] | 0% |
| 232 | Assembly | 4 w | Wed 9/1/04 | Wed 9/29/04 | MandSPass[8,800] | 0% |
| 233 | Board rework | 25 w | Thu 10/14/04 | Wed 4/20/05 | PhysicistU,MandSPass[8,800] | 0% |
| 234 | Production readiness review-Fermilab | 1 w | Mon 5/24/04 | Fri 5/28/04 | ElecEngF[50%] | 0% |
| 235 | Test at Fermilab | 25 w | Thu 10/14/04 | Wed 4/20/05 | PhysicistU | 0% |
| 236 | Test at Fermilab | 25 w | Thu 10/14/04 | Wed 4/20/05 | PhysicistU,MandS[36,750],ElecTechU | 0% |
| 237 | Test at Fermilab | 25 w | Thu 10/14/04 | Wed 4/20/05 | PhysicistF[50%],ElecTechF | 0% |
| 238 | L1 Central Track Trigger Production And Testing Complete | 0 w | Wed 4/20/05 | Wed 4/20/05 | 0% | |
| 239 | DFEA Backplane (BP) | 183 d? | Fri 1/2/04 | Mon 9/20/04 | 0% | |
| 240 | hardware spec | 21 d | Wed 1/14/04 | Thu 2/12/04 | Jamieson Olsen[20%] | 0% |
| 241 | timing spec (for CC/BP/DFEA) | 14 d | Tue 1/27/04 | Fri 2/13/04 | Jamieson Olsen[20%] | 0% |
| 242 | interface specs (hardware+timing) finished | 1 d? | Mon 2/16/04 | Mon 2/16/04 | 0% | |
| 243 | schematic + layout | 4 mons | Fri 1/2/04 | Fri 4/23/04 | Jamieson Olsen[20%] | 0% |
| 244 | ready for production | 1 d? | Mon 4/26/04 | Mon 4/26/04 | 0% | |
| 245 | production + vendor checkout | 3 mons | Tue 4/27/04 | Wed 7/21/04 | InKind[14,000] | 0% |
| 246 | first BP received | 1 d? | Thu 7/22/04 | Thu 7/22/04 | 0% | |
| 247 | FNAL checkout | 2 w | Fri 7/23/04 | Thu 8/5/04 | Jamieson Olsen[20%] | 0% |
| 248 | crate assembly + bench test | 2 w | Fri 8/6/04 | Thu 8/19/04 | Jamieson Olsen[20%],InKind[7,000] | 0% |
| 249 | test with CC | 2 w | Fri 8/20/04 | Thu 9/2/04 | Jamieson Olsen[20%] | 0% |
| 250 | test with CC + DFEA | 2 w | Fri 9/3/04 | Fri 9/17/04 | Jamieson Olsen[20%] | 0% |
| 251 | delivered to Boston | 1 d? | Mon 9/20/04 | Mon 9/20/04 | Jamieson Olsen | 0% |
| 252 | DFEA Crate Controller (CC) | 297 d? | Mon 12/1/03 | Wed 2/16/05 | Jamieson Olsen | 0% |
| 253 | interface specs | 1 mon | Mon 12/1/03 | Tue 1/6/04 | Jamieson Olsen | 0% |
| 254 | schematic + layout; order long leadtime parts | 3 mons | Wed 1/14/04 | Wed 4/7/04 | Jamieson Olsen[20%] | 0% |
| 255 | PCB production + vendor testing | 1 mon | Thu 4/8/04 | Wed 5/5/04 | 0% | |
| 256 | assembly (vendor) | 2 mons | Thu 5/6/04 | Thu 7/1/04 | InKind[7,500] | 0% |
| 257 | checkout | 2 w | Mon 7/5/04 | Fri 7/16/04 | Jamieson Olsen[20%] | 0% |
| 258 | Serial Command Link Receiver procurement | 2 mons | Mon 3/1/04 | Fri 4/23/04 | Jamieson Olsen[5%],InKind[625] | 0% |
| 259 | test software/firmware | 4 mons | Mon 3/1/04 | Mon 6/21/04 | Jamieson Olsen[20%] | 0% |
| 260 | finish software/firmware | 8 mons | Tue 6/22/04 | Wed 2/16/05 | Jamieson Olsen[20%] | 0% |
| 261 | bench test | 2 w | Mon 7/19/04 | Fri 7/30/04 | Jamieson Olsen[50%] | 0% |
| 262 | CC ready | 1 d? | Mon 8/2/04 | Mon 8/2/04 | 0% | |
| 263 | optical Download and Control Link (DCL) | 160 d? | Thu 2/12/04 | Mon 9/27/04 | Jamieson Olsen | 0% |
| 264 | interface specs | 1 mon | Thu 2/12/04 | Wed 3/10/04 | Jamieson Olsen[20%] | 0% |
| 265 | hardware specs | 1 mon | Thu 3/11/04 | Wed 4/7/04 | Jamieson Olsen[20%] | 0% |
| 266 | specs done | 1 d? | Thu 4/8/04 | Thu 4/8/04 | 0% | |
| 267 | hardware procurement | 1 mon | Fri 4/9/04 | Thu 5/6/04 | Jamieson Olsen[10%],InKind[1,000] | 0% |
| 268 | software: Linux driver | 3 mons | Thu 4/8/04 | Thu 7/1/04 | Ron Rechenmacher or eqv.[30%] | 0% |
| 269 | software: EPICS driver + integration | 3 mons | Thu 5/20/04 | Fri 8/13/04 | Geoff Savage or eqv.[30%] | 0% |
| 270 | software: dfe_ware integration | 3 mons | Mon 7/5/04 | Mon 9/27/04 | Yurii Maravin replacement[50%] | 0% |
| 271 | bench test PC - CC | 2 w | Mon 7/5/04 | Fri 7/16/04 | Jamieson Olsen[20%] | 0% |
| 272 | ||||||
| 273 | L1 Trigger Upgrade Production and Testing Complete | 0 w | Thu 5/12/05 | Thu 5/12/05 | 0% | |
| 274 | Level 2 Beta Processor | 305 d | Mon 12/1/03 | Mon 2/28/05 | 3% | |
| 275 | Finalize Targets For Run2b Beta Upgrades | 195 d | Mon 12/1/03 | Mon 9/13/04 | 6% | |
| 276 | UVA Tasks | 195 d | Mon 12/1/03 | Mon 9/13/04 | 9% | |
| 277 | Assess Performance of Run2a Betas | 8 w | Mon 12/1/03 | Wed 2/4/04 | PhysicistU[25%] | 43% |
| 278 | Develop & Simulate New Run2b Algortihms | 30 w | Thu 2/5/04 | Fri 9/3/04 | PhysicistU | 0% |
| 279 | Production readiness review | 1 w | Tue 9/7/04 | Mon 9/13/04 | PhysicistU[200%] | 0% |
| 280 | University-Other Tasks | 190 d | Mon 12/1/03 | Fri 9/3/04 | 9% | |
| 281 | Assess Performance of Run2a Betas | 8 w | Mon 12/1/03 | Wed 2/4/04 | PhysicistU[200%] | 43% |
| 282 | Develop & Simulate New Run2b Algortihms | 30 w | Thu 2/5/04 | Fri 9/3/04 | PhysicistU[400%] | 0% |
| 283 | Orsay Tasks | 150 d | Thu 2/5/04 | Fri 9/3/04 | 0% | |
| 284 | Develop & Simulate New Run2b Algortihms | 30 w | Thu 2/5/04 | Fri 9/3/04 | PhysicistU | 0% |
| 285 | Develop Prototype | 100 d | Thu 3/18/04 | Fri 8/6/04 | 0% | |
| 286 | UVA Tasks | 20 d | Thu 3/18/04 | Wed 4/14/04 | 0% | |
| 287 | Survey processor market, chose candidate SBCs | 4 w | Thu 3/18/04 | Wed 4/14/04 | PhysicistU[25%] | 0% |
| 288 | Evaluate software impact of new SBCs | 4 w | Thu 3/18/04 | Wed 4/14/04 | PhysicistU[25%] | 0% |
| 289 | Evaluate firmware impact of new SBCs (function) | 4 w | Thu 3/18/04 | Wed 4/14/04 | PhysicistU[25%] | 0% |
| 290 | Acquire 2 new processor SBCs for evaluation | 12 w | Thu 4/15/04 | Fri 7/9/04 | PhysicistU[5%],MandS[8,160] | 0% |
| 291 | Orsay Tasks | 100 d | Thu 3/18/04 | Fri 8/6/04 | 0% | |
| 292 | Evaluate firmware impact of new SBCs (coding) | 4 w | Thu 3/18/04 | Wed 4/14/04 | ElecEngU[50%],InKind[8,247.2] | 0% |
| 293 | Design disk adapter | 4 w | Thu 4/15/04 | Wed 5/12/04 | ElecEngU[25%],InKind[4,123.6] | 0% |
| 294 | Specify/Acquire adapter components | 4 w | Thu 5/13/04 | Thu 6/10/04 | ElecEngU[5%],InKind[1,024.72] | 0% |
| 295 | Layout adapter, generate artwork, etc | 2 w | Fri 6/11/04 | Thu 6/24/04 | ElecEngU,InKind[8,247.2] | 0% |
| 296 | Find manufacturer for disk adapters | 2 w | Fri 6/25/04 | Fri 7/9/04 | ElecEngU[25%],InKind[2,061.8] | 0% |
| 297 | Produce prototype adapters | 3 w | Mon 7/12/04 | Fri 7/30/04 | ElecEngU[5%],InKind[868.54] | 0% |
| 298 | Test prototype adapters | 1 w | Mon 8/2/04 | Fri 8/6/04 | PhysicistU[25%] | 0% |
| 299 | Level 2 Beta Trigger Prototype Preparation Complete | 0 w | Fri 8/6/04 | Fri 8/6/04 | 0% | |
| 300 | Test Prototype | 60 d | Mon 8/9/04 | Mon 11/1/04 | 0% | |
| 301 | UVA Tasks | 60 d | Mon 8/9/04 | Mon 11/1/04 | 0% | |
| 302 | Verify software compatibiity / hardware interface patches | 8 w | Mon 8/9/04 | Mon 10/4/04 | PhysicistU[30%] | 0% |
| 303 | Verify processor operability in Beta motherboards | 8 w | Mon 8/9/04 | Mon 10/4/04 | PhysicistU[60%] | 0% |
| 304 | Shadow mode studies | 4 w | Tue 10/5/04 | Mon 11/1/04 | 0% | |
| 305 | Orsay Tasks | 40 d | Mon 8/9/04 | Mon 10/4/04 | 0% | |
| 306 | Firmware support and tuning | 8 w | Mon 8/9/04 | Mon 10/4/04 | ElecEngU[60%],InKind[19,793.28] | 0% |
| 307 | Level 2 Beta Trigger Prototype Testing Complete | 0 w | Mon 11/1/04 | Mon 11/1/04 | 0% | |
| 308 | Assemble Production Processors | 95 d | Tue 10/5/04 | Mon 2/28/05 | 0% | |
| 309 | Produce Disk Adapters | 3 w | Tue 10/5/04 | Mon 10/25/04 | InKind[1,050],ElecTechU[10%] | 0% |
| 310 | Finalize Run2b SBC order | 2 w | Tue 11/2/04 | Mon 11/15/04 | PhysicistU[30%] | 0% |
| 311 | Acquire Run2b SBCs | 12 w | Tue 11/16/04 | Mon 2/21/05 | PhysicistU[5%],MandS[39,840] | 0% |
| 312 | Test production disk adapters | 1 w | Tue 10/26/04 | Mon 11/1/04 | PhysicistU[25%] | 0% |
| 313 | Test SBCs | 1 w | Tue 2/22/05 | Mon 2/28/05 | PhysicistU[25%] | 0% |
| 314 | L2 Beta Trigger Production And Testing Complete | 0 w | Mon 2/28/05 | Mon 2/28/05 | 0% | |
| 315 | Silicon Track Trigger Upgrade | 504 d | Tue 1/21/03 | Mon 1/31/05 | 8% | |
| 316 | Place Parts Orders for L2 Silicon Track Trigger | 0 w | Mon 12/15/03 | Mon 12/15/03 | 100% | |
| 317 | Production Readiness Review | 1 w | Mon 7/26/04 | Fri 7/30/04 | ElecEngU[50%],PhysicistU,PhysicistF[20%],MandSPass[1,292] | 0% |
| 318 | Begin L2 Silicon Track Trigger Run IIb PCB Production | 0 w | Mon 8/2/04 | Mon 8/2/04 | 0% | |
| 319 | L2 Silicon Track Trigger Run IIb Inputs Finalized | 0 w | Mon 12/15/03 | Mon 12/15/03 | 100% | |
| 320 | VME Motherboard | 235 d | Mon 12/15/03 | Mon 11/22/04 | 6% | |
| 321 | Place orders | 24 h | Mon 12/15/03 | Wed 12/17/03 | ElecTechU,MandSPass[480] | 100% |
| 322 | Parts | 8 w | Thu 12/18/03 | Mon 2/23/04 | MandSPass[13,591] | 10% |
| 323 | Fabricate PCB | 4 w | Mon 8/2/04 | Fri 8/27/04 | MandSPass[7,800] | 0% |
| 324 | Assemble | 4 w | Mon 8/30/04 | Mon 9/27/04 | MandSPass[14,600] | 0% |
| 325 | All L2 Silicon Track Trigger Motherboards Delivered | 0 w | Mon 9/27/04 | Mon 9/27/04 | 0% | |
| 326 | Test | 8 w | Tue 9/28/04 | Mon 11/22/04 | ElecEngU[10%],ElecTechU[20%],MandSPass[2,400] | 0% |
| 327 | L2 Silicon Track Trigger Motherboard Production Complete | 0 w | Mon 11/22/04 | Mon 11/22/04 | 0% | |
| 328 | STC Module | 235 d | Mon 12/15/03 | Mon 11/22/04 | 6% | |
| 329 | Place orders | 0.6 w | Mon 12/15/03 | Wed 12/17/03 | ElecTechU,MandSPass[480] | 100% |
| 330 | Parts | 8 w | Thu 12/18/03 | Mon 2/23/04 | MandSPass[15,786] | 10% |
| 331 | Fabricate PCB | 4 w | Mon 8/2/04 | Fri 8/27/04 | MandSPass[4,182] | 0% |
| 332 | Assemble | 4 w | Mon 8/30/04 | Mon 9/27/04 | MandSPass[1,090] | 0% |
| 333 | All L2 Silicon Track Trigger STCs Delivered | 0 w | Mon 9/27/04 | Mon 9/27/04 | 0% | |
| 334 | Test | 8 w | Tue 9/28/04 | Mon 11/22/04 | ElecEngU[4%],ElecTechU[8%],MandSPass[1,120] | 0% |
| 335 | L2 Silicon Track Trigger STC Production Complete | 0 w | Mon 11/22/04 | Mon 11/22/04 | 0% | |
| 336 | VTM | 86.5 d | Tue 1/21/03 | Wed 5/21/03 | 100% | |
| 337 | Place order | 12 h | Tue 1/21/03 | Wed 1/22/03 | 100% | |
| 338 | Production | 4 w | Wed 1/22/03 | Wed 2/19/03 | 100% | |
| 339 | Test | 13 w | Wed 2/19/03 | Wed 5/21/03 | 100% | |
| 340 | VTM Production Complete for L2 Silicon Track Trigger | 0 w | Wed 5/21/03 | Wed 5/21/03 | 100% | |
| 341 | Link Transmitter Board | 225 d | Mon 12/15/03 | Mon 11/8/04 | 6% | |
| 342 | Place orders | 12 h | Mon 12/15/03 | Tue 12/16/03 | ElecTechU,MandSPass[240] | 100% |
| 343 | Parts | 8 w | Tue 12/16/03 | Fri 2/20/04 | MandSPass[6,561] | 14% |
| 344 | Fabricate PCB | 4 w | Mon 8/2/04 | Fri 8/27/04 | MandSPass[2,190] | 0% |
| 345 | Assemble | 4 w | Mon 8/30/04 | Mon 9/27/04 | MandSPass[718] | 0% |
| 346 | All L2 Silicon Track Trigger LTBs Delivered | 0 w | Mon 9/27/04 | Mon 9/27/04 | 0% | |
| 347 | Test | 6 w | Tue 9/28/04 | Mon 11/8/04 | ElecTechU[33%],MandSPass[1,040] | 0% |
| 348 | L2 Silicon Track Trigger LTB Production Complete | 0 w | Mon 11/8/04 | Mon 11/8/04 | 0% | |
| 349 | Link Receiver Board | 230 d | Mon 12/15/03 | Mon 11/15/04 | 6% | |
| 350 | Place orders | 12 h | Mon 12/15/03 | Tue 12/16/03 | ElecTechU,MandSPass[240] | 100% |
| 351 | Parts | 8 w | Tue 12/16/03 | Fri 2/20/04 | MandSPass[9,297] | 14% |
| 352 | Fabricate PCB | 4 w | Mon 8/2/04 | Fri 8/27/04 | MandSPass[2,010] | 0% |
| 353 | Assemble | 4 w | Mon 8/30/04 | Mon 9/27/04 | MandSPass[710] | 0% |
| 354 | All L2 Silicon Track Trigger LRBs Delivered | 0 w | Mon 9/27/04 | Mon 9/27/04 | 0% | |
| 355 | Test | 7 w | Tue 9/28/04 | Mon 11/15/04 | ElecTechU[30%],MandSPass[920] | 0% |
| 356 | L2 Silicon Track Trigger LRB Production Complete | 0 w | Mon 11/15/04 | Mon 11/15/04 | 0% | |
| 357 | BC Module | 209 d | Fri 1/30/04 | Mon 11/22/04 | 0% | |
| 358 | Place orders | 0.6 w | Fri 1/30/04 | Tue 2/3/04 | ElecTechU,MandSPass[480] | 0% |
| 359 | Parts | 8 w | Wed 2/4/04 | Tue 3/30/04 | MandSPass[13,000] | 0% |
| 360 | Fabricate PCB | 4 w | Mon 8/2/04 | Fri 8/27/04 | MandSPass[3,950] | 0% |
| 361 | Assemble | 4 w | Mon 8/30/04 | Mon 9/27/04 | MandSPass[1,960] | 0% |
| 362 | All L2 Silicon Track Trigger BCs Delivered | 0 w | Mon 9/27/04 | Mon 9/27/04 | 0% | |
| 363 | Test | 8 w | Tue 9/28/04 | Mon 11/22/04 | ElecEngU[6%],ElecTechU[20%],MandSPass[2,000] | 0% |
| 364 | L2 Silicon Track Trigger BC Production Complete | 0 w | Mon 11/22/04 | Mon 11/22/04 | 0% | |
| 365 | TFC Module | 227 d | Tue 1/20/04 | Wed 12/8/04 | 0% | |
| 366 | Parts | 8 w | Tue 1/20/04 | Mon 3/15/04 | MandS[25,997] | 0% |
| 367 | Fabricate PCB | 4 w | Mon 8/2/04 | Fri 8/27/04 | MandS[7,800] | 0% |
| 368 | Assemble and rework | 4 w | Mon 8/30/04 | Mon 9/27/04 | MandS[4,600] | 0% |
| 369 | All L2 Silicon Track Trigger TFCs Delivered | 0 w | Mon 9/27/04 | Mon 9/27/04 | 0% | |
| 370 | Test | 10 w | Tue 9/28/04 | Wed 12/8/04 | ElecEngU[25%],MandS[4,000] | 0% |
| 371 | L2 Silicon Track Trigger TFC Production Complete | 0 w | Wed 12/8/04 | Wed 12/8/04 | 0% | |
| 372 | Hotlink Repeaters | 200 d | Tue 1/20/04 | Thu 10/28/04 | 0% | |
| 373 | Design & prototyping | 8 w | Tue 1/20/04 | Mon 3/15/04 | ElecEngU,MandS[5,000] | 0% |
| 374 | Production | 12 w | Tue 3/16/04 | Tue 6/8/04 | MandS[7,500] | 0% |
| 375 | Test | 20 w | Wed 6/9/04 | Thu 10/28/04 | ElecTechU[4%],MandS[600] | 0% |
| 376 | L2 Silicon Track Trigger Hotlink Repeaters Complete | 0 w | Thu 10/28/04 | Thu 10/28/04 | 0% | |
| 377 | LVDS Cables | 30 d | Wed 9/1/04 | Wed 10/13/04 | 0% | |
| 378 | Fabricate | 4 w | Wed 9/1/04 | Wed 9/29/04 | MandSPass[833] | 0% |
| 379 | Test | 2 w | Thu 9/30/04 | Wed 10/13/04 | ElecTechU[10%],MandSPass[160] | 0% |
| 380 | L2 Silicon Track Trigger LVDS Cable Production Complete | 0 w | Wed 10/13/04 | Wed 10/13/04 | 0% | |
| 381 | Splitters | 223 d | Wed 7/23/03 | Tue 6/15/04 | 9% | |
| 382 | Go out for bids | 2 w | Wed 7/23/03 | Tue 8/5/03 | 100% | |
| 383 | Procure | 16 w | Tue 1/20/04 | Mon 5/10/04 | MandS[3,250] | 0% |
| 384 | Test | 5 w | Tue 5/11/04 | Tue 6/15/04 | ElecTechF[12%] | 0% |
| 385 | L2 Silicon Track Trigger Splitter Procurement Complete | 0 w | Tue 6/15/04 | Tue 6/15/04 | 0% | |
| 386 | Fibers | 268 d | Wed 7/23/03 | Wed 8/18/04 | 9% | |
| 387 | Go out for bids | 2 w | Wed 7/23/03 | Tue 8/5/03 | 100% | |
| 388 | Procure | 16 w | Tue 3/30/04 | Wed 7/21/04 | MandS[1,300] | 0% |
| 389 | Test | 4 w | Thu 7/22/04 | Wed 8/18/04 | ElecTechF[20%] | 0% |
| 390 | L2 Silicon Track Trigger Fiber Procurement Complete | 0 w | Wed 8/18/04 | Wed 8/18/04 | 0% | |
| 391 | L2 Silicon Track Trigger Hardware Production Complete | 0 w | Wed 12/8/04 | Wed 12/8/04 | 0% | |
| 392 | STC firmware | 120 d | Tue 6/1/04 | Wed 11/17/04 | 0% | |
| 393 | Update STC firmware | 24 w | Tue 6/1/04 | Wed 11/17/04 | ElecEngU,MandSPass[38,400] | 0% |
| 394 | TFC Code | 120 d | Mon 8/2/04 | Mon 1/31/05 | 0% | |
| 395 | Change TFC code | 24 w | Mon 8/2/04 | Mon 1/31/05 | PhysicistU | 0% |
| 396 | Downloading & Monitoring | 100 d | Mon 8/2/04 | Wed 12/22/04 | 0% | |
| 397 | Update downloading & monitoring software | 20 w | Mon 8/2/04 | Wed 12/22/04 | PhysicistU | 0% |
| 398 | L2 Silicon Track Trigger Production and Testing Complete | 0 w | Mon 1/31/05 | Mon 1/31/05 | 0% | |
| 399 | L2 Trigger Upgrade Production and Testing Complete | 0 w | Mon 2/28/05 | Mon 2/28/05 | 0% | |
| 400 | Trigger Simulation | 827 d | Thu 11/1/01 | Wed 3/9/05 | 59% | |
| 401 | L1 Cal Simulation Software | 742 d | Thu 11/1/01 | Wed 10/27/04 | 49% | |
| 402 | Develop prototype L1Cal trigger algorithm | 58.4 w | Thu 11/1/01 | Mon 1/13/03 | PhysicistU[50%],StudentU[50%] | 100% |
| 403 | Optimize algorithm performance with simulations | 90 w | Tue 1/14/03 | Wed 10/27/04 | PhysicistU[20%] | 30% |
| 404 | Integrate algorithm into Dzero Trigger Simulation | 83 w | Mon 2/3/03 | Mon 9/27/04 | PhysicistU[20%] | 33% |
| 405 | L1 Cal/Track Match Simulation Software | 530 d | Wed 1/22/03 | Wed 3/9/05 | 21% | |
| 406 | Develop prototype L1Cal/Track match trigger algorithm | 90 w | Wed 1/22/03 | Wed 11/3/04 | PhysicistU[50%],StudentU[50%] | 25% |
| 407 | Optimize algorithm performance with simulations | 10 w | Thu 11/4/04 | Wed 1/26/05 | PhysicistU[20%] | 0% |
| 408 | Integrate algorithm into Dzero Trigger Simulation | 6 w | Thu 1/27/05 | Wed 3/9/05 | PhysicistU[20%] | 0% |
| 409 | L1CTT Simulation | 690 d | Fri 2/1/02 | Wed 11/3/04 | 78% | |
| 410 | Develop prototype CTT algorithm | 48 w | Fri 2/1/02 | Tue 1/21/03 | PhysicistU[50%] | 100% |
| 411 | Develop prototype CTT algorithm | 48 w | Fri 2/1/02 | Tue 1/21/03 | PhysicistF | 100% |
| 412 | Develop prototype CTT algorithm | 48 w | Fri 2/1/02 | Tue 1/21/03 | PhysicistU[50%] | 100% |
| 413 | Develop prototype CTT algorithm | 48 w | Fri 2/1/02 | Tue 1/21/03 | PhysicistU[50%] | 100% |
| 414 | Develop prototype CTT algorithm | 48 w | Fri 2/1/02 | Tue 1/21/03 | PhysicistU[50%] | 100% |
| 415 | Optimize algorithm performance with simulations | 90 w | Wed 1/22/03 | Wed 11/3/04 | PhysicistU[50%] | 70% |
| 416 | Integrate algorithm into Dzero Trigger Simulation | 75 w | Tue 4/1/03 | Tue 9/28/04 | PhysicistU[50%] | 15% |
| 417 | STT Simulator | 100 d | Mon 12/15/03 | Wed 5/12/04 | 0% | |
| 418 | Update simulator | 20 w | Mon 12/15/03 | Wed 5/12/04 | PhysicistU | 0% |
| 419 | Administration | 520 d | Mon 2/3/03 | Mon 3/7/05 | 41% | |
| 420 | Project Management | 104 w | Mon 2/3/03 | Mon 3/7/05 | PhysicistU[280%] | 41% |
| 421 | Travel vendor and collaborator visits | 104 w | Mon 2/3/03 | Mon 3/7/05 | MandS[3,500] | 41% |
| 422 | Shipping costs | 104 w | Mon 2/3/03 | Mon 3/7/05 | MandS[2,000] | 41% |
| ID | Name | Group | Max Units | Peak Units |
|---|---|---|---|---|
| 1 | MechEngF | F | 1,000% | 0% |
| 2 | MechEngU | U | 1,000% | 0% |
| 3 | ElecEngF | F | 1,000% | 100% |
| 4 | ElecEngU | U | 1,000% | 767% |
| 5 | MechTechF | F | 1,000% | 0% |
| 6 | MechTechU | U | 1,000% | 0% |
| 7 | ElecTechF | F | 1,000% | 130% |
| 8 | ElecTechU | U | 1,000% | 534% |
| 9 | PhysicistF | F | 1,000% | 70% |
| 10 | PhysicistU | U | 1,000% | 1,745% |
| 11 | CompProfF | F | 1,000% | 0% |
| 12 | CompProfU | U | 1,000% | 0% |
| 13 | StudentU | U | 400% | 210% |
| 14 | PostdocU | U | 100% | 60% |
| 15 | MandS | 0/d | ||
| 16 | MandSPass | 0/h | ||
| 17 | MandSExempt | 0/d | ||
| 18 | InKind | 0/d | ||
| 19 | AdminAsstF | F | 100% | 0% |
| 20 | Jamieson Olsen | 100% | 320% | |
| 21 | Ron Rechenmacher or eqv. | 100% | 30% | |
| 22 | Geoff Savage or eqv. | 100% | 30% | |
| 23 | Yurii Maravin replacement | 100% | 50% |
| Task ID | Task Name | Resource Name | Work | Start | Finish | % Work Complete |
|---|---|---|---|---|---|---|
| 5 | Design prototype ADF | ElecEngU | 2,120 h | Wed 1/2/02 | Fri 1/24/03 | 100% |
| 5 | Design prototype ADF | InKind | 189,655.6 | Wed 1/2/02 | Fri 1/24/03 | 100% |
| 6 | Layout prototype ADF | ElecTechU | 680 h | Mon 1/27/03 | Fri 5/23/03 | 100% |
| 6 | Layout prototype ADF | InKind | 15,110.4 | Mon 1/27/03 | Fri 5/23/03 | 100% |
| 7 | Fabricate/Assemble Prototype ADF | ElecTechU | 104 h | Tue 5/27/03 | Tue 7/1/03 | 100% |
| 7 | Fabricate/Assemble Prototype ADF | InKind | 60,055.2 | Tue 5/27/03 | Tue 7/1/03 | 100% |
| 8 | Bench Test Prototype ADF | PhysicistU | 163.2 h | Tue 7/15/03 | Fri 10/17/03 | 100% |
| 8 | Bench Test Prototype ADF | ElecEngU | 108.8 h | Tue 7/15/03 | Fri 10/17/03 | 100% |
| 8 | Bench Test Prototype ADF | ElecTechU | 108.8 h | Tue 7/15/03 | Fri 10/17/03 | 100% |
| 8 | Bench Test Prototype ADF | InKind | 20,632.24 | Tue 7/15/03 | Fri 10/17/03 | 100% |
| 10 | Design analog splitter | ElecEngU | 160 h | Fri 3/1/02 | Thu 3/28/02 | 100% |
| 10 | Design analog splitter | InKind | 16,494.4 | Fri 3/1/02 | Fri 3/1/02 | 100% |
| 11 | Layout and fabricate analog splitter | ElecTechU | 160 h | Mon 7/1/02 | Mon 8/26/02 | 100% |
| 11 | Layout and fabricate analog splitter | InKind | 9,150.2 | Mon 7/1/02 | Mon 8/26/02 | 100% |
| 12 | Bench test analog splitter | ElecTechU | 116 h | Mon 11/4/02 | Fri 1/17/03 | 100% |
| 12 | Bench test analog splitter | InKind | 1,888.8 | Mon 11/4/02 | Fri 1/17/03 | 100% |
| 13 | Design SCL interface | ElecEngU | 561.6 h | Mon 7/15/02 | Mon 6/23/03 | 100% |
| 13 | Design SCL interface | InKind | 41,236 | Mon 7/15/02 | Mon 6/23/03 | 100% |
| 14 | Layout and fabricate SCL interface | ElecTechU | 172 h | Tue 6/24/03 | Fri 8/22/03 | 100% |
| 14 | Layout and fabricate SCL interface | InKind | 11,199.2 | Tue 6/24/03 | Fri 8/22/03 | 100% |
| 15 | Bench test SCL interface | ElecTechU | 156 h | Mon 8/25/03 | Fri 10/17/03 | 100% |
| 15 | Bench test SCL interface | InKind | 3,777.6 | Mon 8/25/03 | Fri 10/17/03 | 100% |
| 16 | ADF Prototype in-situ tests | PhysicistU | 376 h | Wed 10/15/03 | Mon 12/22/03 | 100% |
| 16 | ADF Prototype in-situ tests | ElecEngU | 75.2 h | Wed 10/15/03 | Mon 12/22/03 | 100% |
| 16 | ADF Prototype in-situ tests | InKind | 13,193.43 | Wed 10/15/03 | Mon 12/22/03 | 100% |
| 17 | Final ADF design - Production readiness review | ElecEngU | 400 h | Tue 12/9/03 | Thu 2/26/04 | 0% |
| 17 | Final ADF design - Production readiness review | InKind | 41,236 | Tue 12/9/03 | Thu 2/26/04 | 0% |
| 18 | Bench test 10% ADF | ElecTechU | 320 h | Wed 8/18/04 | Wed 10/13/04 | 0% |
| 18 | Bench test 10% ADF | ElecEngU | 32 h | Wed 8/18/04 | Wed 10/13/04 | 0% |
| 18 | Bench test 10% ADF | PhysicistU | 96 h | Wed 8/18/04 | Wed 10/13/04 | 0% |
| 18 | Bench test 10% ADF | InKind | 18,409.28 | Wed 8/18/04 | Wed 10/13/04 | 0% |
| 19 | Digital filter FPGA programming | PhysicistU | 960 h | Mon 1/27/03 | Fri 8/27/04 | 50% |
| 19 | Digital filter FPGA programming | ElecEngU | 320 h | Mon 1/27/03 | Fri 8/27/04 | 50% |
| 19 | Digital filter FPGA programming | InKind | 32,988.8 | Mon 1/27/03 | Fri 8/27/04 | 50% |
| 20 | ADF offline software and analysis | PhysicistU | 460 h | Mon 10/20/03 | Fri 4/9/04 | 0% |
| 22 | Develop in-situ exercizing/debugging software | ElecEngU | 400 h | Mon 10/20/03 | Fri 3/19/04 | 25% |
| 22 | Develop in-situ exercizing/debugging software | PhysicistU | 400 h | Mon 10/20/03 | Fri 3/19/04 | 25% |
| 22 | Develop in-situ exercizing/debugging software | InKind | 41,234.93 | Mon 10/20/03 | Fri 3/19/04 | 25% |
| 35 | Procure ADF components | ElecEngU | 24.62 h | Tue 3/30/04 | Wed 7/21/04 | 0% |
| 35 | Procure ADF components | MandSPass | 118,646.8 | Tue 3/30/04 | Wed 7/21/04 | 0% |
| 36 | Fabricate production ADF | ElecTechU | 72 h | Thu 8/12/04 | Mon 12/20/04 | 0% |
| 36 | Fabricate production ADF | MandSPass | 51,746.88 | Thu 8/12/04 | Mon 12/20/04 | 0% |
| 37 | Bench test production ADF | ElecTechU | 720 h | Thu 8/26/04 | Wed 1/12/05 | 0% |
| 37 | Bench test production ADF | ElecEngU | 72 h | Thu 8/26/04 | Wed 1/12/05 | 0% |
| 37 | Bench test production ADF | PhysicistU | 216 h | Thu 8/26/04 | Wed 1/12/05 | 0% |
| 37 | Bench test production ADF | MandSPass | 59,830.16 | Thu 8/26/04 | Wed 1/12/05 | 0% |
| 41 | Design transition backplane | ElecEngU | 136 h | Thu 5/1/03 | Fri 5/23/03 | 100% |
| 41 | Design transition backplane | InKind | 24,741.6 | Thu 5/1/03 | Fri 5/23/03 | 100% |
| 42 | Layout and fabricate transition backplane | ElecTechU | 160 h | Tue 5/27/03 | Tue 7/22/03 | 100% |
| 42 | Layout and fabricate transition backplane | InKind | 7,555.2 | Tue 5/27/03 | Tue 7/22/03 | 100% |
| 43 | Fabricate/Assemble prototype crate | ElecTechU | 184 h | Wed 7/23/03 | Thu 9/25/03 | 100% |
| 43 | Fabricate/Assemble prototype crate | InKind | 7,555.2 | Wed 7/23/03 | Thu 9/25/03 | 100% |
| 44 | Test prototype ADF in prototype crate | PhysicistU | 192 h | Fri 9/26/03 | Thu 1/29/04 | 10% |
| 44 | Test prototype ADF in prototype crate | ElecEngU | 128 h | Fri 9/26/03 | Thu 1/29/04 | 10% |
| 44 | Test prototype ADF in prototype crate | ElecTechU | 128 h | Fri 9/26/03 | Thu 1/29/04 | 10% |
| 44 | Test prototype ADF in prototype crate | InKind | 9,619.84 | Fri 9/26/03 | Thu 1/29/04 | 20% |
| 46 | Final backplane design | ElecEngU | 160 h | Fri 1/30/04 | Thu 2/26/04 | 0% |
| 46 | Final backplane design | InKind | 16,494.4 | Fri 1/30/04 | Thu 2/26/04 | 0% |
| 48 | Procure crate components | MandSPass | 51,144.44 | Fri 2/27/04 | Thu 4/1/04 | 0% |
| 48 | Procure crate components | ElecTechU | 20 h | Fri 2/27/04 | Thu 4/1/04 | 0% |
| 49 | Assemble ADF crates | ElecTechU | 40 h | Fri 4/2/04 | Thu 4/8/04 | 0% |
| 49 | Assemble ADF crates | MandSPass | 5,388.8 | Fri 4/2/04 | Thu 4/8/04 | 0% |
| 53 | Design prototype Trigger Algorithm Board (TAB) | ElecEngU | 1,453.68 h | Fri 2/1/02 | Tue 1/28/03 | 100% |
| 53 | Design prototype Trigger Algorithm Board (TAB) | InKind | 94,972.2 | Fri 2/1/02 | Tue 1/28/03 | 100% |
| 54 | Layout prototype TAB | ElecEngU | 219.6 h | Fri 8/9/02 | Wed 5/7/03 | 100% |
| 54 | Layout prototype TAB | InKind | 14,897.6 | Fri 8/9/02 | Wed 5/7/03 | 100% |
| 55 | Procure prototype TAB parts | ElecTechU | 67.2 h | Fri 8/23/02 | Wed 4/30/03 | 100% |
| 55 | Procure prototype TAB parts | InKind | 17,931.2 | Fri 8/23/02 | Wed 4/30/03 | 100% |
| 56 | Fabricate/Assemble Prototype TAB | ElecTechU | 26.4 h | Thu 5/8/03 | Tue 6/24/03 | 100% |
| 56 | Fabricate/Assemble Prototype TAB | InKind | 11,706.56 | Thu 5/8/03 | Tue 6/24/03 | 100% |
| 57 | Develop TAB/GAB test software | PostdocU | 240 h | Mon 11/4/02 | Wed 1/28/04 | 94% |
| 57 | Develop TAB/GAB test software | StudentU | 240 h | Mon 11/4/02 | Wed 1/28/04 | 94% |
| 58 | Test prototype TAB | PhysicistU | 75.2 h | Wed 6/25/03 | Fri 8/29/03 | 100% |
| 58 | Test prototype TAB | ElecEngU | 75.2 h | Wed 6/25/03 | Fri 8/29/03 | 100% |
| 58 | Test prototype TAB | ElecTechU | 18.8 h | Wed 6/25/03 | Fri 8/29/03 | 100% |
| 58 | Test prototype TAB | StudentU | 188 h | Wed 6/25/03 | Fri 8/29/03 | 100% |
| 58 | Test prototype TAB | InKind | 15,327.72 | Wed 6/25/03 | Fri 8/29/03 | 100% |
| 60 | Pre-production TAB design | ElecEngU | 32 h | Mon 2/2/04 | Fri 2/27/04 | 0% |
| 60 | Pre-production TAB design | InKind | 2,979.62 | Mon 2/2/04 | Fri 2/27/04 | 0% |
| 62 | Procure TAB parts | ElecTechU | 40 h | Mon 3/1/04 | Fri 5/7/04 | 0% |
| 62 | Procure TAB parts | MandSPass | 60,373.2 | Mon 3/1/04 | Fri 5/7/04 | 0% |
| 63 | Layout pre-production TAB | ElecEngU | 120 h | Mon 3/1/04 | Fri 4/9/04 | 0% |
| 63 | Layout pre-production TAB | MandSPass | 11,173.2 | Mon 3/1/04 | Fri 4/9/04 | 0% |
| 64 | Fabricate/Assemple pre-production TAB | ElecTechU | 32 h | Mon 4/12/04 | Mon 6/7/04 | 0% |
| 64 | Fabricate/Assemple pre-production TAB | MandSPass | 11,706.56 | Mon 4/12/04 | Mon 6/7/04 | 0% |
| 65 | Final design and layout changes to TAB | ElecEngU | 40 h | Thu 8/19/04 | Wed 9/1/04 | 0% |
| 65 | Final design and layout changes to TAB | MandSPass | 3,724.4 | Thu 8/19/04 | Wed 9/1/04 | 0% |
| 67 | Fabricate production TAB | ElecTechU | 32 h | Thu 9/2/04 | Thu 10/28/04 | 0% |
| 67 | Fabricate production TAB | MandSPass | 16,706.56 | Thu 9/2/04 | Thu 10/28/04 | 0% |
| 69 | Bench test pre-production TAB | PhysicistU | 72 h | Tue 6/8/04 | Tue 7/20/04 | 0% |
| 69 | Bench test pre-production TAB | StudentU | 180 h | Tue 6/8/04 | Tue 7/20/04 | 0% |
| 69 | Bench test pre-production TAB | ElecEngU | 72 h | Tue 6/8/04 | Tue 7/20/04 | 0% |
| 69 | Bench test pre-production TAB | ElecTechU | 24 h | Tue 6/8/04 | Tue 7/20/04 | 0% |
| 69 | Bench test pre-production TAB | InKind | 7,983.84 | Tue 6/8/04 | Tue 7/20/04 | 0% |
| 70 | Bench test production TAB | StudentU | 96 h | Fri 10/29/04 | Thu 2/3/05 | 0% |
| 70 | Bench test production TAB | ElecEngU | 24 h | Fri 10/29/04 | Thu 2/3/05 | 0% |
| 70 | Bench test production TAB | ElecTechU | 24 h | Fri 10/29/04 | Thu 2/3/05 | 0% |
| 70 | Bench test production TAB | InKind | 3,514.56 | Fri 10/29/04 | Thu 2/3/05 | 0% |
| 73 | Design prototype GAB | ElecEngU | 450.9 h | Mon 7/29/02 | Mon 6/30/03 | 100% |
| 73 | Design prototype GAB | InKind | 49,609.01 | Mon 7/29/02 | Mon 6/30/03 | 100% |
| 74 | Layout prototype GAB | ElecEngU | 368 h | Mon 7/21/03 | Wed 11/26/03 | 100% |
| 74 | Layout prototype GAB | InKind | 7,443.29 | Mon 7/21/03 | Wed 11/26/03 | 100% |
| 75 | Procure prototype GAB parts | ElecTechU | 59.2 h | Fri 8/23/02 | Fri 5/23/03 | 100% |
| 75 | Procure prototype GAB parts | InKind | 10,486.66 | Fri 8/23/02 | Fri 5/23/03 | 100% |
| 76 | Fabricate/Assemble Prototype GAB | ElecTechU | 16 h | Mon 12/1/03 | Tue 1/6/04 | 33% |
| 76 | Fabricate/Assemble Prototype GAB | InKind | 5,353.28 | Mon 12/1/03 | Tue 1/6/04 | 33% |
| 77 | Test Prototype GAB | PhysicistU | 32 h | Wed 1/7/04 | Wed 3/3/04 | 0% |
| 77 | Test Prototype GAB | ElecEngU | 32 h | Wed 1/7/04 | Wed 3/3/04 | 0% |
| 77 | Test Prototype GAB | ElecTechU | 16 h | Wed 1/7/04 | Wed 3/3/04 | 0% |
| 77 | Test Prototype GAB | StudentU | 80 h | Wed 1/7/04 | Wed 3/3/04 | 0% |
| 77 | Test Prototype GAB | InKind | 3,832.85 | Wed 1/7/04 | Wed 3/3/04 | 0% |
| 79 | Design/layout prototype VME/SCL interface | InKind | 19,553.1 | Mon 2/24/03 | Fri 4/11/03 | 100% |
| 79 | Design/layout prototype VME/SCL interface | ElecEngU | 210 h | Mon 2/24/03 | Fri 4/11/03 | 100% |
| 80 | Fabricate/assemble prototype VME/SCL interface | InKind | 5,140 | Mon 4/14/03 | Mon 5/12/03 | 100% |
| 80 | Fabricate/assemble prototype VME/SCL interface | ElecTechU | 16.8 h | Mon 4/14/03 | Mon 5/12/03 | 100% |
| 81 | Test prototype VME/SCL interface | InKind | 3,832.85 | Thu 5/22/03 | Tue 7/29/03 | 100% |
| 81 | Test prototype VME/SCL interface | ElecEngU | 37.6 h | Thu 5/22/03 | Tue 7/29/03 | 100% |
| 81 | Test prototype VME/SCL interface | ElecTechU | 18.8 h | Thu 5/22/03 | Tue 7/29/03 | 100% |
| 81 | Test prototype VME/SCL interface | StudentU | 94 h | Thu 5/22/03 | Tue 7/29/03 | 100% |
| 81 | Test prototype VME/SCL interface | PhysicistU | 37.6 h | Thu 5/22/03 | Tue 7/29/03 | 100% |
| 83 | Final GAB design - Production readiness review | ElecEngU | 32 h | Mon 2/2/04 | Fri 2/27/04 | 0% |
| 83 | Final GAB design - Production readiness review | MandSPass | 2,979.52 | Mon 2/2/04 | Fri 2/27/04 | 0% |
| 84 | Procure GAB parts | ElecTechU | 40 h | Mon 3/1/04 | Fri 5/7/04 | 0% |
| 84 | Procure GAB parts | MandSPass | 7,133.2 | Mon 3/1/04 | Fri 5/7/04 | 0% |
| 85 | Layout final GAB | ElecEngU | 28.8 h | Mon 3/1/04 | Fri 4/9/04 | 0% |
| 85 | Layout final GAB | MandSPass | 2,681.57 | Mon 3/1/04 | Fri 4/9/04 | 0% |
| 86 | Fabricate production GAB | ElecTechU | 16 h | Fri 2/4/05 | Thu 3/31/05 | 0% |
| 86 | Fabricate production GAB | MandSPass | 3,853.33 | Fri 2/4/05 | Thu 3/31/05 | 0% |
| 87 | Bench test production GAB | PhysicistU | 72 h | Fri 4/1/05 | Thu 5/12/05 | 0% |
| 87 | Bench test production GAB | StudentU | 180 h | Fri 4/1/05 | Thu 5/12/05 | 0% |
| 87 | Bench test production GAB | ElecEngU | 43.2 h | Fri 4/1/05 | Thu 5/12/05 | 0% |
| 87 | Bench test production GAB | ElecTechU | 14.4 h | Fri 4/1/05 | Thu 5/12/05 | 0% |
| 87 | Bench test production GAB | MandSPass | 4,790.35 | Fri 4/1/05 | Thu 5/12/05 | 0% |
| 88 | Final design/layout changes to production VME/SCL interface | MandSPass | 2,979.52 | Thu 3/4/04 | Wed 3/31/04 | 0% |
| 88 | Final design/layout changes to production VME/SCL interface | ElecEngU | 32 h | Thu 3/4/04 | Wed 3/31/04 | 0% |
| 89 | Fabricate/assemble production VME/SCL interface | MandSPass | 3,426.67 | Thu 4/1/04 | Wed 4/28/04 | 0% |
| 89 | Fabricate/assemble production VME/SCL interface | ElecTechU | 8 h | Thu 4/1/04 | Wed 4/28/04 | 0% |
| 90 | Bench test production VME/SCL interface | MandSPass | 3,193.57 | Thu 4/29/04 | Wed 5/26/04 | 0% |
| 90 | Bench test production VME/SCL interface | ElecEngU | 28.8 h | Thu 4/29/04 | Wed 5/26/04 | 0% |
| 90 | Bench test production VME/SCL interface | ElecTechU | 9.6 h | Thu 4/29/04 | Wed 5/26/04 | 0% |
| 90 | Bench test production VME/SCL interface | StudentU | 40 h | Thu 4/29/04 | Wed 5/26/04 | 0% |
| 90 | Bench test production VME/SCL interface | PhysicistU | 16 h | Thu 4/29/04 | Wed 5/26/04 | 0% |
| 92 | Design and Fabricate system to test ADF to TAB cables | ElecTechU | 9.6 h | Mon 9/9/02 | Fri 10/18/02 | 100% |
| 92 | Design and Fabricate system to test ADF to TAB cables | InKind | 10,983.92 | Mon 9/9/02 | Fri 10/18/02 | 100% |
| 92 | Design and Fabricate system to test ADF to TAB cables | ElecEngU | 7.2 h | Wed 10/16/02 | Fri 10/18/02 | 100% |
| 93 | Test ADF to TAB cables | ElecEngU | 16 h | Mon 10/21/02 | Fri 11/1/02 | 100% |
| 93 | Test ADF to TAB cables | StudentU | 40 h | Mon 10/21/02 | Fri 11/1/02 | 100% |
| 93 | Test ADF to TAB cables | InKind | 1,489.76 | Mon 10/21/02 | Fri 11/1/02 | 100% |
| 94 | Procure ADF to TAB cables | ElecTechU | 40 h | Tue 11/30/04 | Thu 2/17/05 | 0% |
| 94 | Procure ADF to TAB cables | MandSPass | 19,914.1 | Tue 11/30/04 | Thu 2/17/05 | 0% |
| 97 | Procure TAB crate for prototype TAB/GAB | ElecTechU | 44.8 h | Mon 10/28/02 | Mon 1/27/03 | 100% |
| 97 | Procure TAB crate for prototype TAB/GAB | InKind | 11,513.12 | Mon 10/28/02 | Mon 1/27/03 | 100% |
| 98 | Procure VME CPU for prototype TAB/GAB | ElecTechU | 40.8 h | Fri 1/17/03 | Mon 3/31/03 | 100% |
| 98 | Procure VME CPU for prototype TAB/GAB | InKind | 4,956.56 | Fri 1/17/03 | Mon 3/31/03 | 100% |
| 100 | Specify TAB crate/power/cooling | ElecEngU | 16 h | Tue 4/20/04 | Mon 5/3/04 | 0% |
| 100 | Specify TAB crate/power/cooling | MandSPass | 1,489.76 | Tue 4/20/04 | Mon 5/3/04 | 0% |
| 101 | Procure TAB crate | ElecTechU | 64 h | Tue 11/30/04 | Thu 3/31/05 | 0% |
| 101 | Procure TAB crate | MandSPass | 12,513.12 | Tue 11/30/04 | Thu 3/31/05 | 0% |
| 102 | Procure TAB VME CPU | ElecTechU | 32 h | Tue 11/30/04 | Thu 2/3/05 | 0% |
| 102 | Procure TAB VME CPU | MandSPass | 4,956.56 | Tue 11/30/04 | Thu 2/3/05 | 0% |
| 106 | Develop in-situ exercizing/debugging software | ElecEngU | 560 h | Tue 7/1/03 | Wed 1/28/04 | 87% |
| 106 | Develop in-situ exercizing/debugging software | PhysicistU | 560 h | Tue 7/1/03 | Wed 1/28/04 | 87% |
| 106 | Develop in-situ exercizing/debugging software | InKind | 16,494.4 | Tue 7/1/03 | Wed 1/28/04 | 96% |
| 107 | Prototype integration test ADF+TAB:Columbia | PhysicistU | 45.6 h | Wed 7/30/03 | Fri 10/17/03 | 100% |
| 107 | Prototype integration test ADF+TAB:Columbia | ElecEngU | 91.2 h | Wed 7/30/03 | Fri 10/17/03 | 100% |
| 107 | Prototype integration test ADF+TAB:Columbia | StudentU | 228 h | Wed 7/30/03 | Fri 10/17/03 | 100% |
| 107 | Prototype integration test ADF+TAB:Columbia | InKind | 2,979.52 | Wed 7/30/03 | Fri 10/17/03 | 100% |
| 108 | Prototype integration test ADF+TAB:Saclay | PhysicistU | 45.6 h | Wed 7/30/03 | Fri 10/17/03 | 100% |
| 108 | Prototype integration test ADF+TAB:Saclay | ElecEngU | 91.2 h | Wed 7/30/03 | Fri 10/17/03 | 100% |
| 108 | Prototype integration test ADF+TAB:Saclay | StudentU | 228 h | Wed 7/30/03 | Fri 10/17/03 | 100% |
| 108 | Prototype integration test ADF+TAB:Saclay | InKind | 3,298.88 | Wed 7/30/03 | Fri 10/17/03 | 100% |
| 109 | Prototype integration test ADF+TAB+GAB+TFW: MSU | PhysicistU | 156 h | Mon 10/20/03 | Fri 1/30/04 | 25% |
| 109 | Prototype integration test ADF+TAB+GAB+TFW: MSU | ElecEngU | 104 h | Mon 10/20/03 | Fri 1/30/04 | 25% |
| 109 | Prototype integration test ADF+TAB+GAB+TFW: MSU | InKind | 6,597.58 | Mon 10/20/03 | Fri 1/30/04 | 34% |
| 110 | Prototype integration test ADF+TAB+GAB+TFW: Columbia | PhysicistU | 52 h | Mon 10/20/03 | Fri 1/30/04 | 25% |
| 110 | Prototype integration test ADF+TAB+GAB+TFW: Columbia | ElecEngU | 104 h | Mon 10/20/03 | Fri 1/30/04 | 25% |
| 110 | Prototype integration test ADF+TAB+GAB+TFW: Columbia | StudentU | 260 h | Mon 10/20/03 | Fri 1/30/04 | 25% |
| 110 | Prototype integration test ADF+TAB+GAB+TFW: Columbia | InKind | 5,959.04 | Mon 10/20/03 | Fri 1/30/04 | 34% |
| 111 | Prototype integration test ADF+TAB+GAB+TFW: Saclay | PhysicistU | 52 h | Mon 10/20/03 | Fri 1/30/04 | 25% |
| 111 | Prototype integration test ADF+TAB+GAB+TFW: Saclay | ElecEngU | 104 h | Mon 10/20/03 | Fri 1/30/04 | 25% |
| 111 | Prototype integration test ADF+TAB+GAB+TFW: Saclay | StudentU | 260 h | Mon 10/20/03 | Fri 1/30/04 | 25% |
| 111 | Prototype integration test ADF+TAB+GAB+TFW: Saclay | InKind | 6,597.76 | Mon 10/20/03 | Fri 1/30/04 | 34% |
| 112 | Prototype integration test ADF+TAB+GAB+TFW: Fermilab | ElecTechF | 104 h | Mon 10/20/03 | Fri 1/30/04 | 25% |
| 114 | Pre-production integration test ADF+TAB+TFW: MSU | ElecEngU | 32 h | Thu 7/15/04 | Wed 8/11/04 | 0% |
| 114 | Pre-production integration test ADF+TAB+TFW: MSU | PhysicistU | 48 h | Thu 7/15/04 | Wed 8/11/04 | 0% |
| 114 | Pre-production integration test ADF+TAB+TFW: MSU | MandSPass | 3,298.79 | Thu 7/15/04 | Wed 8/11/04 | 0% |
| 115 | Pre-production integration test ADF+TAB+TFW: Columbia | ElecEngU | 32 h | Thu 7/15/04 | Wed 8/11/04 | 0% |
| 115 | Pre-production integration test ADF+TAB+TFW: Columbia | PhysicistU | 48 h | Thu 7/15/04 | Wed 8/11/04 | 0% |
| 115 | Pre-production integration test ADF+TAB+TFW: Columbia | MandSPass | 2,979.52 | Thu 7/15/04 | Wed 8/11/04 | 0% |
| 116 | Pre-production integration test ADF+TAB+TFW: Saclay | ElecEngU | 32 h | Thu 7/15/04 | Wed 8/11/04 | 0% |
| 116 | Pre-production integration test ADF+TAB+TFW: Saclay | PhysicistU | 48 h | Thu 7/15/04 | Wed 8/11/04 | 0% |
| 116 | Pre-production integration test ADF+TAB+TFW: Saclay | InKind | 3,298.36 | Thu 7/15/04 | Wed 8/11/04 | 0% |
| 117 | Pre-production integration test ADF+TAB+TFW: Fermilab | ElecTechF | 96 h | Thu 7/15/04 | Wed 8/11/04 | 0% |
| 118 | Production readiness review | ElecEngU | 40 h | Thu 8/12/04 | Wed 8/18/04 | 0% |
| 118 | Production readiness review | PhysicistU | 40 h | Thu 8/12/04 | Wed 8/18/04 | 0% |
| 118 | Production readiness review | MandSPass | 4,000 | Thu 8/12/04 | Wed 8/18/04 | 0% |
| 119 | Production readiness review | ElecEngF | 8 h | Thu 8/12/04 | Wed 8/18/04 | 0% |
| 121 | ADF online software | PostdocU | 950 h | Tue 4/15/03 | Tue 3/15/05 | 37% |
| 121 | ADF online software | PhysicistU | 380 h | Tue 4/15/03 | Tue 3/15/05 | 37% |
| 122 | TAB/GAB online software | PostdocU | 870 h | Wed 6/11/03 | Tue 3/15/05 | 28% |
| 122 | TAB/GAB online software | PhysicistU | 348 h | Wed 6/11/03 | Tue 3/15/05 | 28% |
| 127 | D0 Production Readiness Review | ElecEngU | 20 h | Wed 7/30/03 | Tue 8/5/03 | 100% |
| 127 | D0 Production Readiness Review | PhysicistU | 20 h | Wed 7/30/03 | Tue 8/5/03 | 100% |
| 127 | D0 Production Readiness Review | MandSPass | 2,000 | Wed 7/30/03 | Tue 8/5/03 | 100% |
| 128 | D0 Production Readiness Review | ElecEngF | 8 h | Wed 7/30/03 | Tue 8/5/03 | 100% |
| 132 | Procure SLDB parts | ElecEngU | 38 h | Fri 3/14/03 | Mon 7/28/03 | 100% |
| 132 | Procure SLDB parts | MandSPass | 29,153.22 | Fri 3/14/03 | Mon 7/28/03 | 100% |
| 133 | Fabricate and assemble SLDBs | ElecEngU | 39.6 h | Mon 6/16/03 | Tue 2/17/04 | 75% |
| 133 | Fabricate and assemble SLDBs | MandSPass | 11,419.14 | Mon 6/16/03 | Tue 2/17/04 | 75% |
| 134 | Test SLDBs | ElecTechU | 192 h | Wed 2/18/04 | Tue 4/13/04 | 0% |
| 134 | Test SLDBs | ElecEngU | 64 h | Wed 2/18/04 | Tue 4/13/04 | 0% |
| 134 | Test SLDBs | PhysicistU | 64 h | Wed 2/18/04 | Tue 4/13/04 | 0% |
| 134 | Test SLDBs | MandSPass | 3,170.24 | Wed 2/18/04 | Tue 4/13/04 | 0% |
| 136 | (Small) design changes to MTCxx | ElecEngU | 4,214 h | Fri 3/14/03 | Mon 1/12/04 | 98% |
| 136 | (Small) design changes to MTCxx | MandSPass | 2,296.32 | Fri 3/14/03 | Mon 1/12/04 | 98% |
| 137 | Procure MTCxx parts | ElecEngU | 64 h | Mon 6/9/03 | Tue 9/30/03 | 100% |
| 137 | Procure MTCxx parts | MandSPass | 23,325.38 | Mon 6/9/03 | Tue 9/30/03 | 100% |
| 138 | Fabricate and assemble preproduction MTCxx | ElecEngU | 12 h | Tue 1/13/04 | Tue 2/24/04 | 0% |
| 138 | Fabricate and assemble preproduction MTCxx | MandSPass | 4,005.04 | Tue 1/13/04 | Tue 2/24/04 | 0% |
| 140 | Test preproduction MTCxx | ElecTechU | 256 h | Wed 2/25/04 | Tue 4/20/04 | 0% |
| 140 | Test preproduction MTCxx | ElecEngU | 96 h | Wed 2/25/04 | Tue 4/20/04 | 0% |
| 140 | Test preproduction MTCxx | PhysicistU | 64 h | Wed 2/25/04 | Tue 4/20/04 | 0% |
| 140 | Test preproduction MTCxx | MandS | 4,354.56 | Wed 2/25/04 | Tue 4/20/04 | 0% |
| 141 | Final design changes to MTCxx | ElecEngU | 96 h | Wed 4/21/04 | Wed 6/2/04 | 0% |
| 141 | Final design changes to MTCxx | MandSPass | 1,148.16 | Wed 4/21/04 | Wed 6/2/04 | 0% |
| 142 | Fabricate and assemble MTCxx's | ElecEngU | 32 h | Thu 6/3/04 | Fri 9/24/04 | 0% |
| 142 | Fabricate and assemble MTCxx's | MandSPass | 8,500.72 | Thu 6/3/04 | Fri 9/24/04 | 0% |
| 144 | Test MTCxx's | ElecEngU | 88 h | Mon 9/27/04 | Tue 12/14/04 | 0% |
| 144 | Test MTCxx's | ElecTechU | 352 h | Mon 9/27/04 | Tue 12/14/04 | 0% |
| 144 | Test MTCxx's | PhysicistF | 88 h | Mon 9/27/04 | Tue 12/14/04 | 0% |
| 144 | Test MTCxx's | MandSPass | 6,950.72 | Mon 9/27/04 | Tue 12/14/04 | 0% |
| 146 | (Small) design changes to MTCM | ElecEngU | 132 h | Mon 10/20/03 | Thu 1/15/04 | 90% |
| 146 | (Small) design changes to MTCM | MandSPass | 1,148.16 | Mon 10/20/03 | Thu 1/15/04 | 93% |
| 147 | Procure MTCM parts | ElecEngU | 48 h | Fri 1/16/04 | Fri 4/9/04 | 0% |
| 147 | Procure MTCM parts | MandSPass | 8,626.08 | Fri 1/16/04 | Fri 4/9/04 | 0% |
| 148 | Fabricate and assemble MTCMs | ElecEngU | 12 h | Mon 4/12/04 | Fri 5/21/04 | 0% |
| 148 | Fabricate and assemble MTCMs | MandSPass | 4,511.04 | Mon 4/12/04 | Fri 5/21/04 | 0% |
| 150 | Test MTCMs | ElecEngU | 144 h | Mon 5/24/04 | Tue 8/17/04 | 0% |
| 150 | Test MTCMs | MandSPass | 1,722.24 | Mon 5/24/04 | Tue 8/17/04 | 0% |
| 152 | Design prototype cal-trk algorithm | PhysicistU | 314 h | Thu 8/1/02 | Mon 3/24/03 | 100% |
| 154 | Design prototype MTFB | ElecEngU | 160.8 h | Thu 10/17/02 | Fri 1/31/03 | 100% |
| 154 | Design prototype MTFB | PhysicistU | 107.2 h | Thu 10/17/02 | Fri 1/31/03 | 100% |
| 154 | Design prototype MTFB | ElecTechU | 268 h | Thu 10/17/02 | Fri 1/31/03 | 100% |
| 154 | Design prototype MTFB | MandS | 6,304.32 | Thu 10/17/02 | Fri 1/31/03 | 100% |
| 155 | Procure prototype MTFB parts | ElecEngU | 8 h | Mon 6/2/03 | Fri 6/27/03 | 100% |
| 155 | Procure prototype MTFB parts | MandS | 1,635.68 | Mon 6/2/03 | Fri 6/27/03 | 100% |
| 156 | Fabricate and assemble prototype MTFB | ElecEngU | 12 h | Mon 6/30/03 | Mon 8/11/03 | 100% |
| 156 | Fabricate and assemble prototype MTFB | MandS | 4,631.36 | Mon 6/30/03 | Mon 8/11/03 | 100% |
| 158 | Test prototype MTFB | ElecEngU | 1,160 h | Tue 8/12/03 | Tue 3/16/04 | 80% |
| 158 | Test prototype MTFB | PhysicistU | 1,160 h | Tue 8/12/03 | Tue 3/16/04 | 80% |
| 158 | Test prototype MTFB | ElecTechU | 1,160 h | Tue 8/12/03 | Tue 3/16/04 | 80% |
| 158 | Test prototype MTFB | MandS | 1,985.92 | Tue 8/12/03 | Tue 3/16/04 | 78% |
| 160 | Procure MTFB parts | ElecEngU | 6.4 h | Wed 3/17/04 | Tue 4/13/04 | 0% |
| 160 | Procure MTFB parts | MandSPass | 8,623.09 | Wed 3/17/04 | Tue 4/13/04 | 0% |
| 161 | Fabricate and assemble MTFB | ElecEngU | 16 h | Wed 4/14/04 | Wed 6/9/04 | 0% |
| 161 | Fabricate and assemble MTFB | MandSPass | 6,546.04 | Wed 4/14/04 | Wed 6/9/04 | 0% |
| 163 | Test MTFB | ElecTechU | 192 h | Thu 6/10/04 | Thu 8/5/04 | 0% |
| 163 | Test MTFB | ElecEngU | 32 h | Thu 6/10/04 | Thu 8/5/04 | 0% |
| 163 | Test MTFB | PhysicistU | 64 h | Thu 6/10/04 | Thu 8/5/04 | 0% |
| 163 | Test MTFB | MandSPass | 2,787.52 | Thu 6/10/04 | Thu 8/5/04 | 0% |
| 166 | Procure cables and connectors | ElecEngU | 19.2 h | Mon 6/30/03 | Tue 10/21/03 | 100% |
| 166 | Procure cables and connectors | MandSPass | 16,639.36 | Mon 6/30/03 | Tue 10/21/03 | 100% |
| 167 | Assemble cables | PhysicistU | 120 h | Mon 5/24/04 | Tue 8/17/04 | 0% |
| 167 | Assemble cables | ElecTechU | 96 h | Mon 5/24/04 | Tue 8/17/04 | 0% |
| 167 | Assemble cables | MandSPass | 601.2 | Mon 5/24/04 | Tue 8/17/04 | 0% |
| 168 | Procure VME crates | ElecTechU | 16.8 h | Mon 6/23/03 | Tue 9/30/03 | 100% |
| 168 | Procure VME crates | MandSPass | 8,973.15 | Mon 6/23/03 | Tue 9/30/03 | 100% |
| 169 | Procure VME processors | ElecEngU | 10.4 h | Fri 3/14/03 | Tue 9/16/03 | 100% |
| 169 | Procure VME processors | MandSPass | 8,492.38 | Fri 3/14/03 | Tue 9/16/03 | 100% |
| 170 | Procure power supplies | ElecEngU | 5.12 h | Tue 7/1/03 | Tue 9/30/03 | 100% |
| 170 | Procure power supplies | MandSPass | 13,689.58 | Tue 7/1/03 | Tue 9/30/03 | 100% |
| 171 | Assemble and test power supplies | PhysicistU | 49.6 h | Tue 1/20/04 | Wed 4/14/04 | 0% |
| 171 | Assemble and test power supplies | MandSPass | 4,304.38 | Tue 1/20/04 | Wed 4/14/04 | 0% |
| 171 | Assemble and test power supplies | ElecEngU | 4.97 h | Tue 1/20/04 | Wed 4/14/04 | 0% |
| 172 | Procure MSPLIT crates, backplanes, and power supplies | ElecTechU | 32 h | Thu 1/15/04 | Thu 5/6/04 | 0% |
| 172 | Procure MSPLIT crates, backplanes, and power supplies | MandSPass | 809.6 | Thu 1/15/04 | Thu 5/6/04 | 0% |
| 173 | Procure MSPLIT card parts | ElecEngU | 32 h | Thu 1/15/04 | Thu 5/6/04 | 0% |
| 173 | Procure MSPLIT card parts | MandSPass | 7,507.8 | Thu 1/15/04 | Thu 5/6/04 | 0% |
| 174 | Fabricate and assemble MSPLIT cards | ElecEngU | 24 h | Fri 5/7/04 | Mon 8/2/04 | 0% |
| 174 | Fabricate and assemble MSPLIT cards | ElecTechU | 96 h | Fri 5/7/04 | Mon 8/2/04 | 0% |
| 174 | Fabricate and assemble MSPLIT cards | MandSPass | 12,808.44 | Fri 5/7/04 | Mon 8/2/04 | 0% |
| 175 | Test MSPLIT cards | ElecTechU | 64 h | Tue 8/3/04 | Tue 9/28/04 | 0% |
| 175 | Test MSPLIT cards | ElecEngU | 16 h | Tue 8/3/04 | Tue 9/28/04 | 0% |
| 175 | Test MSPLIT cards | PhysicistU | 16 h | Tue 8/3/04 | Tue 9/28/04 | 0% |
| 175 | Test MSPLIT cards | MandSPass | 992.96 | Tue 8/3/04 | Tue 9/28/04 | 0% |
| 177 | Assemble cables | ElecTechF | 240 h | Mon 5/24/04 | Tue 8/17/04 | 0% |
| 178 | Assemble and test power supplies | ElecTechF | 248 h | Tue 1/20/04 | Wed 4/14/04 | 0% |
| 183 | Develop firmware for target CTT algorithm | ElecEngU | 912 h | Thu 11/7/02 | Tue 4/29/03 | 100% |
| 183 | Develop firmware for target CTT algorithm | InKind | 72,352 | Thu 11/7/02 | Tue 4/29/03 | 100% |
| 184 | Fit CTT firmware in selected FPGA, do timing studies | ElecEngU | 320 h | Wed 4/30/03 | Wed 6/25/03 | 100% |
| 184 | Fit CTT firmware in selected FPGA, do timing studies | InKind | 12,920 | Wed 4/30/03 | Wed 6/25/03 | 100% |
| 187 | Develop test procedures | ElecEngU | 56 h | Thu 6/26/03 | Fri 1/23/04 | 97% |
| 187 | Develop test procedures | InKind | 1,550.4 | Thu 6/26/03 | Fri 1/23/04 | 98% |
| 188 | Develop test procedures | PhysicistU | 560 h | Thu 6/26/03 | Fri 1/23/04 | 97% |
| 191 | Layout | ElecEngU | 448 h | Thu 6/26/03 | Mon 9/15/03 | 100% |
| 191 | Layout | ElecTechU | 44.8 h | Thu 6/26/03 | Mon 9/15/03 | 100% |
| 191 | Layout | InKind | 22,739 | Thu 6/26/03 | Mon 9/15/03 | 100% |
| 192 | Procure preproduction DFEA parts | ElecTechU | 43.2 h | Fri 8/22/03 | Tue 9/30/03 | 100% |
| 192 | Procure preproduction DFEA parts | InKind | 2,067.2 | Fri 8/22/03 | Tue 9/30/03 | 100% |
| 193 | PCB fabrication | ElecTechU | 32 h | Mon 9/22/03 | Fri 10/17/03 | 100% |
| 193 | PCB fabrication | InKind | 1,033.6 | Mon 9/22/03 | Fri 10/17/03 | 100% |
| 194 | Assembly | ElecTechU | 17.12 h | Mon 10/20/03 | Mon 12/22/03 | 100% |
| 194 | Assembly | InKind | 1,162.8 | Mon 10/20/03 | Mon 12/22/03 | 100% |
| 195 | Test | ElecEngU | 360 h | Tue 12/23/03 | Thu 3/25/04 | 3% |
| 195 | Test | InKind | 23,256 | Tue 12/23/03 | Thu 3/25/04 | 3% |
| 195 | Test | PhysicistU | 240 h | Tue 12/23/03 | Thu 3/25/04 | 3% |
| 197 | Procure preproduction DFEA FPGAs | MandSPass | 48,000 | Thu 6/26/03 | Thu 8/7/03 | 100% |
| 197 | Procure preproduction DFEA FPGAs | PhysicistU | 4.8 h | Thu 6/26/03 | Thu 8/7/03 | 100% |
| 198 | Procure preproduction DFEA parts | MandSPass | 1,500 | Fri 8/22/03 | Tue 9/30/03 | 100% |
| 199 | PCB fabrication | MandSPass | 5,801 | Mon 9/22/03 | Fri 10/17/03 | 100% |
| 200 | Assembly | MandSPass | 788 | Mon 10/20/03 | Mon 12/22/03 | 100% |
| 203 | Layout | ElecEngU | 160 h | Mon 2/2/04 | Fri 2/27/04 | 0% |
| 203 | Layout | ElecTechU | 40 h | Mon 2/2/04 | Fri 2/27/04 | 0% |
| 203 | Layout | InKind | 12,920 | Mon 2/2/04 | Fri 2/27/04 | 0% |
| 204 | PCB fabrication | ElecTechU | 16 h | Mon 3/1/04 | Fri 3/12/04 | 0% |
| 204 | PCB fabrication | InKind | 1,033.6 | Mon 3/1/04 | Fri 3/12/04 | 0% |
| 205 | Procure preproduction parts | ElecTechU | 1.2 h | Mon 2/23/04 | Fri 3/12/04 | 0% |
| 205 | Procure preproduction parts | InKind | 77.52 | Mon 2/23/04 | Fri 3/12/04 | 0% |
| 206 | Assembly | ElecTechU | 16 h | Mon 3/15/04 | Fri 3/26/04 | 0% |
| 206 | Assembly | InKind | 1,033.6 | Mon 3/15/04 | Fri 3/26/04 | 0% |
| 207 | Test | ElecEngU | 160 h | Mon 3/29/04 | Fri 5/21/04 | 0% |
| 207 | Test | InKind | 10,336 | Mon 3/29/04 | Fri 5/21/04 | 0% |
| 207 | Test | PhysicistU | 320 h | Mon 3/29/04 | Fri 5/21/04 | 0% |
| 208 | Test at Fermilab | ElecEngU | 24 h | Mon 4/12/04 | Fri 5/21/04 | 0% |
| 208 | Test at Fermilab | InKind | 1,550.4 | Mon 4/12/04 | Fri 5/21/04 | 0% |
| 208 | Test at Fermilab | PhysicistU | 240 h | Mon 4/12/04 | Fri 5/21/04 | 0% |
| 210 | PCB fabrication | MandSPass | 5,801 | Mon 3/1/04 | Fri 3/12/04 | 0% |
| 211 | Procure preproduction parts | MandSPass | 200 | Mon 2/23/04 | Fri 3/12/04 | 0% |
| 212 | Assembly | MandSPass | 788 | Mon 3/15/04 | Fri 3/26/04 | 0% |
| 213 | Test at Fermilab | ElecTechF | 120 h | Mon 4/12/04 | Fri 5/21/04 | 0% |
| 213 | Test at Fermilab | ElecEngF | 240 h | Mon 4/12/04 | Fri 5/21/04 | 0% |
| 214 | Test at Fermilab | PhysicistU | 240 h | Mon 4/12/04 | Fri 5/21/04 | 0% |
| 215 | Test at Fermilab | PhysicistU | 240 h | Mon 4/12/04 | Fri 5/21/04 | 0% |
| 219 | Procure FPGAs | InKind | 356,000 | Tue 6/29/04 | Wed 11/17/04 | 0% |
| 220 | Procure FPGAs | ElecTechU | 8 h | Tue 6/1/04 | Wed 10/20/04 | 0% |
| 220 | Procure FPGAs | InKind | 516.8 | Tue 6/1/04 | Wed 10/20/04 | 0% |
| 221 | Design, layout | ElecEngU | 80 h | Tue 6/1/04 | Mon 6/28/04 | 0% |
| 221 | Design, layout | ElecTechU | 80 h | Tue 6/1/04 | Mon 6/28/04 | 0% |
| 221 | Design, layout | InKind | 10,336 | Tue 6/1/04 | Mon 6/28/04 | 0% |
| 222 | Procure production parts | ElecTechU | 24 h | Tue 6/29/04 | Tue 8/10/04 | 0% |
| 222 | Procure production parts | InKind | 1,550.4 | Tue 6/29/04 | Tue 8/10/04 | 0% |
| 223 | PCB Fabricate | ElecTechU | 12 h | Wed 7/21/04 | Tue 8/31/04 | 0% |
| 223 | PCB Fabricate | InKind | 775.2 | Wed 7/21/04 | Tue 8/31/04 | 0% |
| 224 | Assembly | ElecTechU | 4.8 h | Wed 9/1/04 | Wed 9/29/04 | 0% |
| 224 | Assembly | InKind | 351.95 | Wed 9/1/04 | Wed 9/29/04 | 0% |
| 225 | Bench test | ElecEngU | 240 h | Thu 9/30/04 | Wed 11/24/04 | 0% |
| 225 | Bench test | InKind | 15,504 | Thu 9/30/04 | Wed 11/24/04 | 0% |
| 225 | Bench test | PhysicistU | 160 h | Thu 9/30/04 | Wed 11/24/04 | 0% |
| 226 | Test at Fermilab | ElecEngU | 200 h | Thu 10/14/04 | Wed 4/20/05 | 0% |
| 226 | Test at Fermilab | InKind | 12,920 | Thu 10/14/04 | Wed 4/20/05 | 0% |
| 226 | Test at Fermilab | PhysicistU | 1,000 h | Thu 10/14/04 | Wed 4/20/05 | 0% |
| 228 | Procure FPGAs | MandSPass | 83,296 | Tue 6/29/04 | Wed 11/17/04 | 0% |
| 229 | Production readiness review-BU | ElecEngU | 20 h | Mon 5/24/04 | Fri 5/28/04 | 0% |
| 229 | Production readiness review-BU | PhysicistU | 40 h | Mon 5/24/04 | Fri 5/28/04 | 0% |
| 229 | Production readiness review-BU | MandSPass | 1,292 | Mon 5/24/04 | Fri 5/28/04 | 0% |
| 230 | Procure production parts | MandSPass | 17,600 | Tue 6/29/04 | Tue 8/10/04 | 0% |
| 231 | PCB Fabricate | MandSPass | 30,800 | Wed 7/21/04 | Tue 8/31/04 | 0% |
| 232 | Assembly | MandSPass | 8,800 | Wed 9/1/04 | Wed 9/29/04 | 0% |
| 233 | Board rework | PhysicistU | 1,000 h | Thu 10/14/04 | Wed 4/20/05 | 0% |
| 233 | Board rework | MandSPass | 8,800 | Thu 10/14/04 | Wed 4/20/05 | 0% |
| 234 | Production readiness review-Fermilab | ElecEngF | 20 h | Mon 5/24/04 | Fri 5/28/04 | 0% |
| 235 | Test at Fermilab | PhysicistU | 1,000 h | Thu 10/14/04 | Wed 4/20/05 | 0% |
| 236 | Test at Fermilab | PhysicistU | 1,000 h | Thu 10/14/04 | Wed 4/20/05 | 0% |
| 236 | Test at Fermilab | MandS | 36,750 | Thu 10/14/04 | Wed 4/20/05 | 0% |
| 236 | Test at Fermilab | ElecTechU | 1,000 h | Thu 10/14/04 | Wed 4/20/05 | 0% |
| 237 | Test at Fermilab | PhysicistF | 500 h | Thu 10/14/04 | Wed 4/20/05 | 0% |
| 237 | Test at Fermilab | ElecTechF | 1,000 h | Thu 10/14/04 | Wed 4/20/05 | 0% |
| 240 | hardware spec | Jamieson Olsen | 33.6 h | Wed 1/14/04 | Thu 2/12/04 | 0% |
| 241 | timing spec (for CC/BP/DFEA) | Jamieson Olsen | 22.4 h | Tue 1/27/04 | Fri 2/13/04 | 0% |
| 243 | schematic + layout | Jamieson Olsen | 128 h | Fri 1/2/04 | Fri 4/23/04 | 0% |
| 245 | production + vendor checkout | InKind | 14,000 | Tue 4/27/04 | Wed 7/21/04 | 0% |
| 247 | FNAL checkout | Jamieson Olsen | 16 h | Fri 7/23/04 | Thu 8/5/04 | 0% |
| 248 | crate assembly + bench test | Jamieson Olsen | 16 h | Fri 8/6/04 | Thu 8/19/04 | 0% |
| 248 | crate assembly + bench test | InKind | 7,000 | Fri 8/6/04 | Thu 8/19/04 | 0% |
| 249 | test with CC | Jamieson Olsen | 16 h | Fri 8/20/04 | Thu 9/2/04 | 0% |
| 250 | test with CC + DFEA | Jamieson Olsen | 16 h | Fri 9/3/04 | Fri 9/17/04 | 0% |
| 251 | delivered to Boston | Jamieson Olsen | 8 h | Mon 9/20/04 | Mon 9/20/04 | 0% |
| 252 | DFEA Crate Controller (CC) | Jamieson Olsen | 2,376 h | Mon 12/1/03 | Wed 2/16/05 | 0% |
| 253 | interface specs | Jamieson Olsen | 160 h | Mon 12/1/03 | Tue 1/6/04 | 0% |
| 254 | schematic + layout; order long leadtime parts | Jamieson Olsen | 96 h | Wed 1/14/04 | Wed 4/7/04 | 0% |
| 256 | assembly (vendor) | InKind | 7,500 | Thu 5/6/04 | Thu 7/1/04 | 0% |
| 257 | checkout | Jamieson Olsen | 16 h | Mon 7/5/04 | Fri 7/16/04 | 0% |
| 258 | Serial Command Link Receiver procurement | Jamieson Olsen | 16 h | Mon 3/1/04 | Fri 4/23/04 | 0% |
| 258 | Serial Command Link Receiver procurement | InKind | 625 | Mon 3/1/04 | Fri 4/23/04 | 0% |
| 259 | test software/firmware | Jamieson Olsen | 128 h | Mon 3/1/04 | Mon 6/21/04 | 0% |
| 260 | finish software/firmware | Jamieson Olsen | 256 h | Tue 6/22/04 | Wed 2/16/05 | 0% |
| 261 | bench test | Jamieson Olsen | 40 h | Mon 7/19/04 | Fri 7/30/04 | 0% |
| 263 | optical Download and Control Link (DCL) | Jamieson Olsen | 1,280 h | Thu 2/12/04 | Mon 9/27/04 | 0% |
| 264 | interface specs | Jamieson Olsen | 32 h | Thu 2/12/04 | Wed 3/10/04 | 0% |
| 265 | hardware specs | Jamieson Olsen | 32 h | Thu 3/11/04 | Wed 4/7/04 | 0% |
| 267 | hardware procurement | Jamieson Olsen | 16 h | Fri 4/9/04 | Thu 5/6/04 | 0% |
| 267 | hardware procurement | InKind | 1,000 | Fri 4/9/04 | Thu 5/6/04 | 0% |
| 268 | software: Linux driver | Ron Rechenmacher or eqv. | 144 h | Thu 4/8/04 | Thu 7/1/04 | 0% |
| 269 | software: EPICS driver + integration | Geoff Savage or eqv. | 144 h | Thu 5/20/04 | Fri 8/13/04 | 0% |
| 270 | software: dfe_ware integration | Yurii Maravin replacement | 240 h | Mon 7/5/04 | Mon 9/27/04 | 0% |
| 271 | bench test PC - CC | Jamieson Olsen | 16 h | Mon 7/5/04 | Fri 7/16/04 | 0% |
| 277 | Assess Performance of Run2a Betas | PhysicistU | 80 h | Mon 12/1/03 | Wed 2/4/04 | 43% |
| 278 | Develop & Simulate New Run2b Algortihms | PhysicistU | 1,200 h | Thu 2/5/04 | Fri 9/3/04 | 0% |
| 279 | Production readiness review | PhysicistU | 80 h | Tue 9/7/04 | Mon 9/13/04 | 0% |
| 281 | Assess Performance of Run2a Betas | PhysicistU | 640 h | Mon 12/1/03 | Wed 2/4/04 | 43% |
| 282 | Develop & Simulate New Run2b Algortihms | PhysicistU | 4,800 h | Thu 2/5/04 | Fri 9/3/04 | 0% |
| 284 | Develop & Simulate New Run2b Algortihms | PhysicistU | 1,200 h | Thu 2/5/04 | Fri 9/3/04 | 0% |
| 287 | Survey processor market, chose candidate SBCs | PhysicistU | 40 h | Thu 3/18/04 | Wed 4/14/04 | 0% |
| 288 | Evaluate software impact of new SBCs | PhysicistU | 40 h | Thu 3/18/04 | Wed 4/14/04 | 0% |
| 289 | Evaluate firmware impact of new SBCs (function) | PhysicistU | 40 h | Thu 3/18/04 | Wed 4/14/04 | 0% |
| 290 | Acquire 2 new processor SBCs for evaluation | PhysicistU | 24 h | Thu 4/15/04 | Fri 7/9/04 | 0% |
| 290 | Acquire 2 new processor SBCs for evaluation | MandS | 8,160 | Thu 4/15/04 | Fri 7/9/04 | 0% |
| 292 | Evaluate firmware impact of new SBCs (coding) | ElecEngU | 80 h | Thu 3/18/04 | Wed 4/14/04 | 0% |
| 292 | Evaluate firmware impact of new SBCs (coding) | InKind | 8,247.2 | Thu 3/18/04 | Wed 4/14/04 | 0% |
| 293 | Design disk adapter | ElecEngU | 40 h | Thu 4/15/04 | Wed 5/12/04 | 0% |
| 293 | Design disk adapter | InKind | 4,123.6 | Thu 4/15/04 | Wed 5/12/04 | 0% |
| 294 | Specify/Acquire adapter components | ElecEngU | 8 h | Thu 5/13/04 | Thu 6/10/04 | 0% |
| 294 | Specify/Acquire adapter components | InKind | 1,024.72 | Thu 5/13/04 | Thu 6/10/04 | 0% |
| 295 | Layout adapter, generate artwork, etc | ElecEngU | 80 h | Fri 6/11/04 | Thu 6/24/04 | 0% |
| 295 | Layout adapter, generate artwork, etc | InKind | 8,247.2 | Fri 6/11/04 | Thu 6/24/04 | 0% |
| 296 | Find manufacturer for disk adapters | ElecEngU | 20 h | Fri 6/25/04 | Fri 7/9/04 | 0% |
| 296 | Find manufacturer for disk adapters | InKind | 2,061.8 | Fri 6/25/04 | Fri 7/9/04 | 0% |
| 297 | Produce prototype adapters | ElecEngU | 6 h | Mon 7/12/04 | Fri 7/30/04 | 0% |
| 297 | Produce prototype adapters | InKind | 868.54 | Mon 7/12/04 | Fri 7/30/04 | 0% |
| 298 | Test prototype adapters | PhysicistU | 10 h | Mon 8/2/04 | Fri 8/6/04 | 0% |
| 302 | Verify software compatibiity / hardware interface patches | PhysicistU | 96 h | Mon 8/9/04 | Mon 10/4/04 | 0% |
| 303 | Verify processor operability in Beta motherboards | PhysicistU | 192 h | Mon 8/9/04 | Mon 10/4/04 | 0% |
| 306 | Firmware support and tuning | ElecEngU | 192 h | Mon 8/9/04 | Mon 10/4/04 | 0% |
| 306 | Firmware support and tuning | InKind | 19,793.28 | Mon 8/9/04 | Mon 10/4/04 | 0% |
| 309 | Produce Disk Adapters | InKind | 1,050 | Tue 10/5/04 | Mon 10/25/04 | 0% |
| 309 | Produce Disk Adapters | ElecTechU | 12 h | Tue 10/5/04 | Mon 10/25/04 | 0% |
| 310 | Finalize Run2b SBC order | PhysicistU | 24 h | Tue 11/2/04 | Mon 11/15/04 | 0% |
| 311 | Acquire Run2b SBCs | PhysicistU | 24 h | Tue 11/16/04 | Mon 2/21/05 | 0% |
| 311 | Acquire Run2b SBCs | MandS | 39,840 | Tue 11/16/04 | Mon 2/21/05 | 0% |
| 312 | Test production disk adapters | PhysicistU | 10 h | Tue 10/26/04 | Mon 11/1/04 | 0% |
| 313 | Test SBCs | PhysicistU | 10 h | Tue 2/22/05 | Mon 2/28/05 | 0% |
| 317 | Production Readiness Review | ElecEngU | 20 h | Mon 7/26/04 | Fri 7/30/04 | 0% |
| 317 | Production Readiness Review | PhysicistU | 40 h | Mon 7/26/04 | Fri 7/30/04 | 0% |
| 317 | Production Readiness Review | PhysicistF | 8 h | Mon 7/26/04 | Fri 7/30/04 | 0% |
| 317 | Production Readiness Review | MandSPass | 1,292 | Mon 7/26/04 | Fri 7/30/04 | 0% |
| 321 | Place orders | ElecTechU | 24 h | Mon 12/15/03 | Wed 12/17/03 | 100% |
| 321 | Place orders | MandSPass | 480 | Mon 12/15/03 | Wed 12/17/03 | 100% |
| 322 | Parts | MandSPass | 13,591 | Thu 12/18/03 | Mon 2/23/04 | 10% |
| 323 | Fabricate PCB | MandSPass | 7,800 | Mon 8/2/04 | Fri 8/27/04 | 0% |
| 324 | Assemble | MandSPass | 14,600 | Mon 8/30/04 | Mon 9/27/04 | 0% |
| 326 | Test | ElecEngU | 32 h | Tue 9/28/04 | Mon 11/22/04 | 0% |
| 326 | Test | ElecTechU | 64 h | Tue 9/28/04 | Mon 11/22/04 | 0% |
| 326 | Test | MandSPass | 2,400 | Tue 9/28/04 | Mon 11/22/04 | 0% |
| 329 | Place orders | ElecTechU | 24 h | Mon 12/15/03 | Wed 12/17/03 | 100% |
| 329 | Place orders | MandSPass | 480 | Mon 12/15/03 | Wed 12/17/03 | 100% |
| 330 | Parts | MandSPass | 15,786 | Thu 12/18/03 | Mon 2/23/04 | 10% |
| 331 | Fabricate PCB | MandSPass | 4,182 | Mon 8/2/04 | Fri 8/27/04 | 0% |
| 332 | Assemble | MandSPass | 1,090 | Mon 8/30/04 | Mon 9/27/04 | 0% |
| 334 | Test | ElecEngU | 12.8 h | Tue 9/28/04 | Mon 11/22/04 | 0% |
| 334 | Test | ElecTechU | 25.6 h | Tue 9/28/04 | Mon 11/22/04 | 0% |
| 334 | Test | MandSPass | 1,120 | Tue 9/28/04 | Mon 11/22/04 | 0% |
| 342 | Place orders | ElecTechU | 12 h | Mon 12/15/03 | Tue 12/16/03 | 100% |
| 342 | Place orders | MandSPass | 240 | Mon 12/15/03 | Tue 12/16/03 | 100% |
| 343 | Parts | MandSPass | 6,561 | Tue 12/16/03 | Fri 2/20/04 | 14% |
| 344 | Fabricate PCB | MandSPass | 2,190 | Mon 8/2/04 | Fri 8/27/04 | 0% |
| 345 | Assemble | MandSPass | 718 | Mon 8/30/04 | Mon 9/27/04 | 0% |
| 347 | Test | ElecTechU | 79.2 h | Tue 9/28/04 | Mon 11/8/04 | 0% |
| 347 | Test | MandSPass | 1,040 | Tue 9/28/04 | Mon 11/8/04 | 0% |
| 350 | Place orders | ElecTechU | 12 h | Mon 12/15/03 | Tue 12/16/03 | 100% |
| 350 | Place orders | MandSPass | 240 | Mon 12/15/03 | Tue 12/16/03 | 100% |
| 351 | Parts | MandSPass | 9,297 | Tue 12/16/03 | Fri 2/20/04 | 14% |
| 352 | Fabricate PCB | MandSPass | 2,010 | Mon 8/2/04 | Fri 8/27/04 | 0% |
| 353 | Assemble | MandSPass | 710 | Mon 8/30/04 | Mon 9/27/04 | 0% |
| 355 | Test | ElecTechU | 84 h | Tue 9/28/04 | Mon 11/15/04 | 0% |
| 355 | Test | MandSPass | 920 | Tue 9/28/04 | Mon 11/15/04 | 0% |
| 358 | Place orders | ElecTechU | 24 h | Fri 1/30/04 | Tue 2/3/04 | 0% |
| 358 | Place orders | MandSPass | 480 | Fri 1/30/04 | Tue 2/3/04 | 0% |
| 359 | Parts | MandSPass | 13,000 | Wed 2/4/04 | Tue 3/30/04 | 0% |
| 360 | Fabricate PCB | MandSPass | 3,950 | Mon 8/2/04 | Fri 8/27/04 | 0% |
| 361 | Assemble | MandSPass | 1,960 | Mon 8/30/04 | Mon 9/27/04 | 0% |
| 363 | Test | ElecEngU | 19.2 h | Tue 9/28/04 | Mon 11/22/04 | 0% |
| 363 | Test | ElecTechU | 64 h | Tue 9/28/04 | Mon 11/22/04 | 0% |
| 363 | Test | MandSPass | 2,000 | Tue 9/28/04 | Mon 11/22/04 | 0% |
| 366 | Parts | MandS | 25,997 | Tue 1/20/04 | Mon 3/15/04 | 0% |
| 367 | Fabricate PCB | MandS | 7,800 | Mon 8/2/04 | Fri 8/27/04 | 0% |
| 368 | Assemble and rework | MandS | 4,600 | Mon 8/30/04 | Mon 9/27/04 | 0% |
| 370 | Test | ElecEngU | 100 h | Tue 9/28/04 | Wed 12/8/04 | 0% |
| 370 | Test | MandS | 4,000 | Tue 9/28/04 | Wed 12/8/04 | 0% |
| 373 | Design & prototyping | ElecEngU | 320 h | Tue 1/20/04 | Mon 3/15/04 | 0% |
| 373 | Design & prototyping | MandS | 5,000 | Tue 1/20/04 | Mon 3/15/04 | 0% |
| 374 | Production | MandS | 7,500 | Tue 3/16/04 | Tue 6/8/04 | 0% |
| 375 | Test | ElecTechU | 32 h | Wed 6/9/04 | Thu 10/28/04 | 0% |
| 375 | Test | MandS | 600 | Wed 6/9/04 | Thu 10/28/04 | 0% |
| 378 | Fabricate | MandSPass | 833 | Wed 9/1/04 | Wed 9/29/04 | 0% |
| 379 | Test | ElecTechU | 8 h | Thu 9/30/04 | Wed 10/13/04 | 0% |
| 379 | Test | MandSPass | 160 | Thu 9/30/04 | Wed 10/13/04 | 0% |
| 383 | Procure | MandS | 3,250 | Tue 1/20/04 | Mon 5/10/04 | 0% |
| 384 | Test | ElecTechF | 24 h | Tue 5/11/04 | Tue 6/15/04 | 0% |
| 388 | Procure | MandS | 1,300 | Tue 3/30/04 | Wed 7/21/04 | 0% |
| 389 | Test | ElecTechF | 32 h | Thu 7/22/04 | Wed 8/18/04 | 0% |
| 393 | Update STC firmware | ElecEngU | 960 h | Tue 6/1/04 | Wed 11/17/04 | 0% |
| 393 | Update STC firmware | MandSPass | 38,400 | Tue 6/1/04 | Wed 11/17/04 | 0% |
| 395 | Change TFC code | PhysicistU | 960 h | Mon 8/2/04 | Mon 1/31/05 | 0% |
| 397 | Update downloading & monitoring software | PhysicistU | 800 h | Mon 8/2/04 | Wed 12/22/04 | 0% |
| 402 | Develop prototype L1Cal trigger algorithm | PhysicistU | 761.6 h | Thu 11/1/01 | Mon 1/13/03 | 100% |
| 402 | Develop prototype L1Cal trigger algorithm | StudentU | 1,168 h | Thu 11/1/01 | Mon 1/13/03 | 100% |
| 403 | Optimize algorithm performance with simulations | PhysicistU | 720 h | Tue 1/14/03 | Wed 10/27/04 | 30% |
| 404 | Integrate algorithm into Dzero Trigger Simulation | PhysicistU | 664 h | Mon 2/3/03 | Mon 9/27/04 | 33% |
| 406 | Develop prototype L1Cal/Track match trigger algorithm | PhysicistU | 1,800 h | Wed 1/22/03 | Wed 11/3/04 | 25% |
| 406 | Develop prototype L1Cal/Track match trigger algorithm | StudentU | 1,800 h | Wed 1/22/03 | Wed 11/3/04 | 25% |
| 407 | Optimize algorithm performance with simulations | PhysicistU | 80 h | Thu 11/4/04 | Wed 1/26/05 | 0% |
| 408 | Integrate algorithm into Dzero Trigger Simulation | PhysicistU | 48 h | Thu 1/27/05 | Wed 3/9/05 | 0% |
| 410 | Develop prototype CTT algorithm | PhysicistU | 960 h | Fri 2/1/02 | Tue 1/21/03 | 100% |
| 411 | Develop prototype CTT algorithm | PhysicistF | 1,920 h | Fri 2/1/02 | Tue 1/21/03 | 100% |
| 412 | Develop prototype CTT algorithm | PhysicistU | 960 h | Fri 2/1/02 | Tue 1/21/03 | 100% |
| 413 | Develop prototype CTT algorithm | PhysicistU | 960 h | Fri 2/1/02 | Tue 1/21/03 | 100% |
| 414 | Develop prototype CTT algorithm | PhysicistU | 960 h | Fri 2/1/02 | Tue 1/21/03 | 100% |
| 415 | Optimize algorithm performance with simulations | PhysicistU | 1,800 h | Wed 1/22/03 | Wed 11/3/04 | 70% |
| 416 | Integrate algorithm into Dzero Trigger Simulation | PhysicistU | 1,500 h | Tue 4/1/03 | Tue 9/28/04 | 15% |
| 418 | Update simulator | PhysicistU | 800 h | Mon 12/15/03 | Wed 5/12/04 | 0% |
| 420 | Project Management | PhysicistU | 11,648 h | Mon 2/3/03 | Mon 3/7/05 | 41% |
| 421 | Travel vendor and collaborator visits | MandS | 3,500 | Mon 2/3/03 | Mon 3/7/05 | 41% |
| 422 | Shipping costs | MandS | 2,000 | Mon 2/3/03 | Mon 3/7/05 | 41% |