|
|
Post Collider Operations and Detector Decommissioning |
|
Schedule Information
SMT
annealing studies expected to begin on Thursday 22 December
Will
begin shutting down subsystems not required to support SMT annealing studies in
an orderly manner once the warm-up of the silicon for the annealing studies is
underway
Expect
to start warm-up of the solenoid on Tuesday 27 December
Plan
to continue calorimeter bias current studies through Wednesday January 4
Plan
to begin draining liquid argon from the calorimeters on Thursday January 5
Currently
plan to begin warm-up of VLPC cryostats on Wednesday January 11
Post collider
operations period now scheduled for 30 September 2011 through early morning 22
December 2011
Expect to record
global triggers supplemented with CTT based cosmics
and prescaled muon system triggered cosmics
Daily
calibrations
Readout entire
detector
Primarily for
tracker alignment refinement and verification and calibrations
~1 million tracks
through the silicon detectors
Also provides
potential for insights into detector performance in absence of collisions
Investigate
calorimeter bias current evolution in absence of collisions
some parts of
calorimeter will have HV off
Eight weeks with
magnets off
One week in each of
the four magnet polarity combinations
Also provides
opportunity to verify clustering and Lorentz corrections
All
requests for survey and/or alignment crew support should be submitted through
Bill Cooper (Cooper@fnal.gov) with copies
to d0rc@fnal.gov.
Collision Hall Access Plan
Collision hall will generally remain secure during
post-collider operations period to facilitate magnet on operations. Collision hall access requires prior approval
of the Run Coordination team.
Rad safety authorized collision
hall activities include
Routine maintenance
Inspections
Troubleshooting
Installation and removal of
equipment in accordance with procedures
Prohibited collision hall activities
include
Eating, drinking and smoking
Cutting, drilling or
grinding on radioactive materials
Work in areas posted as
High Radiation and/or Contamination Areas
Dont forget to frisk yourself
and survey anything that comes from the collision hall as you exit.
Shift Coverage (and responsibilities) During Post-Collider
Operations Period
Shift coverage through 23 December 2011 is as
follows:
· On-call support for each
subsystem should be available as usual.
· On-call experts are asked to
stop by the control room daily and verify detector performance.
· Captains in control room
during the day (with additional responsibility to attempt to keep DAQ running
when possible), and cosmic shifter in the control room around the clock on
evening.
o
During periods of reduced control room presence, captains and DAQ
shifters are expected to also monitor SMT IDVDD and heartbeat guis to ensure that the SMT is appropriately protected.
o
While cosmics are running, shifter is also
asked to post CTT examine plots and verify that special examine is running at
CFT console
o
Shifter should
monitor for calorimeter noise, post plots as appropriate, and check for alarms,
paging experts for problems they cannot solve.
· Operations shifter scheduled during the day. Cryo and
infrastructure monitoring during the rest of the day via alarms with Auto-Dialer
calls to engineering support.
Reference Material
DZero Detector Decommissioning All Experimenters Meeting 19 Dec 2011
Detector
Decommissioning Talk at DZero Collaboration
Meeting 9 Dec 2011
TeV Decommissioning Working Group Meeting 22 November 2011
Directors
Review of TeV Decommissioning 15 September 2011
Tevatron/CDF/DZero
Decommissioning Plan 6
June 2011 (during DOE Fermilab S&T and Research Review)
DZero Detector
Decommissioning Plan 13 July 2010 (during DOE
Annual Science and Technology Review)
Tevatron
Detector Decommissioning Plan 1 July 2009 (during the DOE
Annual Science and Technology Review)
Tevatron Detector
Decommissioning Plan 25 June 2008 (during the DOE
Annual Science and Technology Review)
Additional Reference Information
2011
Com Ed Scheduled
shutdown web page
Fermilab Environment, Safety and Health Section
Lessons Learned:
Application of Bulk Characterization to Individual Containers
PPD Implementation of Integrated
Safety Management Policy, Hazard Analysis Procedure and Form
Last updated: 21 December 2011 G.
Ginther numeric pager 1-630-218-3217