|
|
Next Long Shutdown |
|
Possible Accelerator
Maintenance
There
is a magnet in the accumulator with a turn to turn short, which is resulting in
a 1% impact on pbar stacking rate.
The spare is under test. If the
magnet fails, it is expected to take from 6 to 8 days to replace, during which
time no stacking will be possible. (A
store could be dragged out, and Tevatron studies
might still be possible during that time.)
There
are also issues with the Pelletron discharging. The Pelletron
experts are looking for an opportunity to access the Main Injector for
servicing, which would require draining the SF6.
The
AD Run Coordinator does not currently consider either of these issues to
require urgent response, however, we should be
prepared to take best advantage of a possible few day access opportunity should
it become potentially available.
Some
candidate activities:
·
Installation
of grounding screen for calorimeter cable trays on platform
·
Installation
and commissioning of R2D0
·
ICD
high voltage optimization
·
ICD
individual channel recoveries
·
Further
stabilization of the low beta quad girders
·
Checking
routing of cables in racks (such as M119 and M120)
·
Documentation
Schedule Information
The Fermilab program planning schedule is available via this link.
The Accelerator Division Operations Department has expressed interest in a
several week shutdown during the summer of 2010 to perform preventative
maintenance on the electrical distribution systems. There is no clear official plan for such a
shutdown at this time.
All
requests for survey and/or alignment crew support during the shutdown should
have been submitted through Bill Cooper (Cooper@fnal.gov)
with copies to d0rc@fnal.gov.
Candidate Task List for Next Long Shutdown
Infrastructure
· Perform surveys/alignments
· UPS
maintenance—Cryo and HVAC
· Improve radiation
shielding at low beta quads?
· Improve
stability of low beta quads
· SNEG bake-out?
· Routine
maintenance
o
Check transfer line vacuums and pump as appropriate
o
Warm up solenoid lead
o
Warm up VLPC cryostats to 50K
o
Warm up west VLPC lid gasket
o
Replace ODH heads in collision hall
o
Check Freon charge on silicon chillers
· Investigate possible
water leak in east cathedral between SMT power supplies?
· Perform safety
system tests
o
Test remote power down buttons
o
Check toroid bus
connections
o
Check torques on solenoid bus connections
o
Test rack protection systems?
· Crate/Rack
maintenance
o
Verify blanks in open slots of crates?
o
Clean heat exchangers as appropriate
o
Check status of fans?
o
Check status of
· Volk’s water
level work again
LUMI Monitors
· Replace
luminosity monitor scintillators?
Silicon Microstrip Tracker
· Complete R2D0
installation and commissioning
· Check silicon
chiller setpoint calibration and adjust as
appropriate
· Investigate
possibility of reducing chiller operating setpoint?
· Investigate
possibility of increasing humidity?
· Replace suspect
Interface Boards
· HDI recovery
effort
o
HDIs that failed as gap was
closed last time
o
Download failures
o
Investigate currently disabled chips
· Complete
watchdog installation and commissioning
· Address LVPS readback issues
Central Fiber Tracker
· Thermal cycle
of cryostat—reset heater operating points to 9K
· Investigate
possibility of external crash button for AFE power
· Evaluate and
deploy readout improvement (to save 200 nsec per L1
accept)
· Complete
Temperature Control fix implementation?
· VRB re-assignments
to balance loads?
· Testing AFE
spares on the platform
· Hunt for
sources of rare coherent discriminator noise
· Check on the
power distribution for the AFE fans?
· Investigate
re-biasing of VLPCs?
CALorimeter
· Top off liquid
argon levels?
· Address cal
preamp power supply failures if any
· Continue
investigating root cause of HV related purple haze
·
· Address
individual channel issues
o
Isolate sparking channels
· Investigate
ICD channels that are still not performing up to expectations
o
Individual channel recoveries
o
PMT replacements
o
ICD preamp connector update
o
HV stabilization
o
HV adjustments
· Improve
shielding of cable paths against muon noise
Central MUON
· Remove two PDT
wires and inspect?
· Complete the
process of cleaning up 1553 communications paths?
· Test control
boards in attempt to improve hot link reliability
· Verify thin FEBs in all locations in upper cathedral
· Recover failed
A Layer PDT if any
· Clean PDT HV
service cards as appropriate
· Relocate PDT FEBs to optimize location of FEBs
with ATMEL chips?
· Recover
disabled A layer scintillator channels if any
Forward MUON
· Check all
Front-Ends and refresh MDT firmware
· Verify
calibrations
Level 1 Central Track Trigger
· DFEF
investigations and revival?
· Eliminate
master slave configuration of power supplies (if not previously addressed)
Level 1 CALorimeter
· Hunt for
individual cell noise sources
· Investigate
and recover disabled trigger towers (if any)
· Run VME I/O
stress test
Level 1 Muon
· Verify spare
status
· Address power
supply readback issues
· Perhaps
replace onboard batteries?
Level 2
· Investigate
source of global mismatches—has not been occurring recently
· Investigate
source of trigger rate dips
· Investigate
cause of timeouts on run starts
· Enhance tools
to identify source of FEBs
Level 2 Silicon Track Trigger
· Complete
investigation of the performance problems when beam is near 0
· Verify error
handling and busy assertions?
Trigger
Framework
· TFW
maintenance and stress tests
· Investigate
M122 top scalar crate hangs
· TCC
maintenance/upgrades?
· Trigger rate
tests?
DAQ/Online
· Upgrades/Maintenance
as appropriate
· Test “new” SBCs
· Test DAQ
functionality with network link disconnected (~2 hour test)
Shift Scheduling During the Shutdown
Supervised access keys are to be issued by only
Captains, Ops shifters, or the Run Coordination team.
If a supervised access key is required after 1600,
or before 0800, the Ops shifter will issue the key.
The control room shifter is asked to verify that the
issued keys are understood at the beginning and end of each of their shifts.
Access Plan
Supervised access keys are to be issued by only
Captains, Ops shifters, or the Run Coordination team. Please make sure to return your key before
leaving the area.
Don’t forget to frisk yourself and survey anything
that comes from the collision hall as you exit.
Only
those qualified for gap access are allowed in the gap. Pocket dosimeters must be worn while working
in the gap.
Additional Reference Information
Fermilab Environment, Safety and Health Section
PPD Implementation of Integrated
Safety Management Policy, Hazard Analysis Procedure and Form
Last updated: 18 October 2009 G.
Ginther numeric page 1-630-218-3217