Hi John Enclosed is the cost estimate. It has been corrected and updated relative to the PMG presentation I made. Here are the changes from the PMG. Note that Harry will make a web page with the cost estimate. System At PMG Now Diff Reason ==================================================================== Track Electr 3584k 3694k 110k 50k was known, 50k from PO vs req amount L1 trig 1440k 1500k 60k Mostly error in cost estimate L2 trig 2080k 2047k -33k Was still being verified at time of PMG, MOU money returned to project ETC Comments ======== * The ETC is calculated as of end Jan 2000 * Any MOU's placed with universities are considered fully obligated and thus not part of the ETC * Prior Year obligations can change because they enter as the req amount and change if the PO changes * There is no contingency in the estimate. Mike