2006 Shutdown |
|
Notices
Collision
hall is secure. 2006 Shutdown is
over. Detector recommissioning
in progress
Testing of upgraded SMT in progress
Technical
commissioning of L1Cal is in progress
Technical
commissioning of L1CTT is complete
Testing
of L1CalTrack in progress
L2STT
installation is complete
Accelerator
complex is currently in startup
Beam
has been accelerated in the booster
Tevatron
is cold
Tevatron
beam expected on June 1and first collisions anticipated roughly a week later.
More Detailed Shutdown Schedule Information
Shutdown
Schedule Overview xls pdf
Pre-shutdown
reference version of the Shutdown Schedule Overview (23 Feb 2006) xls pdf
Current
Microsoft Project Schedule (1 May 2006 version) mpp pdf mods relative to previous version of schedule
Pre-shutdown
reference version of the Microsoft Project Shutdown Schedule Forecast (22 Feb
2006) mpp pdf
Run IIb Level 1 Calorimeter Installation Daily
Updates
Run IIb Level 1 Central Track Trigger Daily
Updates
Accelerator
Division Schedules
Procedures
Layer 0
Installation Procedures are deposited in the appropriate sub-directory of \\D0server6\projects\run2b\Silicon\Layer0\Procedures
Picture Archive
Layer 0 \\D0server6\projects\run2b\Silicon\Layer0\Pictures
Level 1
Calorimeter
Trigger (and more here)
Level 1
Central
Track Trigger
Additional Reference Information
Shutdown
Updates at All Experimenter’s Meeting
28
April 2006 Layer 0 Status (at ADM)
21
April 2006 L1CTT Status Update (at ADM)
7
April 2006 Installation of Layer 0 (at ADM)
March 2006
Collaboration Meeting Agenda
17
Feb 2006 Shutdown Update (at Operations Meeting)
10
Feb 2006 Status of V15 Trigger List Preparations (at ADM)
10
Feb 2006 Shutdown Overview (at ADM)
25
October 2005 Director’s Review of DZero Run IIB
Upgrade Installation
Run
IIB Upgrade DOE Monthly Reports
Operations Groups Shutdown Plans
Luminosity Monitor Update 8
March 2006 Lumi
monitoring group is planning to replace the scintillators
Luminosity Monitor Update 17
March 2006
Last updated: 1 June 2006 G. Ginther