2006 Shutdown

 

 

Notices

 

Collision hall is secure.  2006 Shutdown is over.   Detector recommissioning in progress

 

       Testing of upgraded SMT in progress

 

Technical commissioning of L1Cal is in progress

 

Technical commissioning of L1CTT is complete

 

Testing of L1CalTrack in progress

 

L2STT installation is complete

 

Accelerator complex is currently in startup

Beam has been accelerated in the booster

Tevatron is cold

Tevatron beam expected on June 1and first collisions anticipated roughly a week later.

 

 

More Detailed Shutdown Schedule Information

 

Shutdown Schedule Overview xls  pdf   

 

Pre-shutdown reference version of the Shutdown Schedule Overview (23 Feb 2006) xls   pdf

 

Current Microsoft Project Schedule (1 May 2006 version) mpp   pdf    mods relative to previous version of schedule

 

Pre-shutdown reference version of the Microsoft Project Shutdown Schedule Forecast (22 Feb 2006) mpp   pdf

 

 

Run IIb Level 1 Calorimeter Installation Daily Updates

 

Run IIb Level 1 Central Track Trigger Daily Updates

 

Accelerator Division Schedules

 

 

Procedures

 

Layer 0 Installation Procedures are deposited in the appropriate sub-directory of  \\D0server6\projects\run2b\Silicon\Layer0\Procedures

 

 

Picture Archive

 

       Layer 0   \\D0server6\projects\run2b\Silicon\Layer0\Pictures

 

          Level 1 Calorimeter Trigger (and more here)

 

          Level 1 Central Track Trigger

 

 

Additional Reference Information

 

       4 May 2006 DZero PMG

 

Shutdown Updates at All Experimenter’s Meeting

 

28 April 2006 Layer 0 Status (at ADM)

 

21 April 2006 L1CTT Status Update (at ADM)

 

          7 April 2006 Installation of Layer 0 (at ADM)

 

March 2006 Collaboration Meeting Agenda

 

          17 Feb 2006 Shutdown Update (at Operations Meeting)

 

          10 Feb 2006 Status of V15 Trigger List Preparations (at ADM)

 

          10 Feb 2006 Shutdown Overview (at ADM)

 

10 Feb 2006 DZero PMG

 

25 October 2005 Director’s Review of DZero Run IIB Upgrade Installation

 

Run IIB Upgrade DOE Monthly Reports

 

 

Operations Groups Shutdown Plans

          Mechanical Support Group

          Electrical Support Group

          Global Monitoring

          Controls

          Online

          CTT

          Level 1 Muon

          Level 2

          STT

          Level 3

          Luminosity

                   Luminosity Monitor Update    8 March 2006   Lumi monitoring group is planning to replace the scintillators

                   Luminosity Monitor Update 17 March 2006

          SMT

          CFT

          Calorimeter

          Muon

          FPD

         

Last updated: 1 June 2006   G. Ginther